Wk 6 - Apply: Summative Assessment: Work Breakdown Structure
Exam Content
1.
Top of Form
As a project manager, your projects may be allocated the resources needed by the organization’s PMO. You are likely to be most concerned with securing the resources you need for your project, but the PMO is going to be focused on allocating the resources available to the right projects at the right time. When you articulate the project deliverables and the associated tasks and work packages clearly, the scope of the project is well-defined and helps to ensure delivery of the project outcomes successfully and within the project schedule.
In this assignment, you will show your project scoping skills when you prepare a project summary and work breakdown structure (WBS) for PMO review so your project’s resources can be allocated to meet your project schedule. Consider what the PMO needs from you so that your project gets what it needs from the PMO.
Select project from the case study listed below (also attached):
· Crosby Manufacturing Corporation using information from the Crosby Manufacturing Corporation Case Study (Kerzner, 2022)
Use the case study you selected and prepare a WBS that you will submit to the PMO.
Summarize or outline the project’s critical factors, including the following:
· Project details:
· Project name
· Project sponsor
· Estimated start date
· Estimated date of completion
· Project scope description, including what is in and out of scope
· List of project deliverables:
· Project acceptance criteria
· Project constraints
· Project assumptions
Consider the key takeaways you learned in your course textbook, The DNA of Strategy Execution. These may help you consider what information a PMO will be looking for. Reference the textbook, as needed.
Prepare a WBS for this project in Microsoft Word, PowerPoint, or another program of your choice and include a detailed list of major project deliverables, subtasks, and work packages. Additionally:
· Consider the work needed to deliver each major deliverable or phase of the project.
· Include at least 2 phases with main tasks or deliverables that you can break down into subtasks and work packages.
Cite any references used and format citation and references according to APA guidelines.
Submit your WBS.
Resources
· Center for Writing Excellence
· Reference and Citation Generator
From Project Management Case Studies (6th ed.) (pp. 187–191 and pp. 209–212), by H. Kerzner, 2022, John Wiley & Sons, Inc. Copyright 2021 by John Wiley & Sons, Inc. Reprinted with permission.
Bottom of Form
pm583_v1_wiley_crosby_manufacturing_corporation_case_study.pdf
Crosby Manufacturing Corporation Case Study
For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.
Crosby Manufacturing Corporation “I’ve called this meeting to resolve a major problem with our management cost and control system [MCCS],” remarked Wilfred Livingston, president of Crosby Manufacturing Corporation. “We’re having one hell of a time trying to meet competition with our antiquated MCCS reporting procedures. Last year we were considered nonresponsive to three large government contracts because we could not adhere to the customer’s financial reporting requirements. The government has recently shown a renewed interest in Crosby Manufacturing. If we can computerize our project financial reporting procedure, we’ll be in great shape to meet the competition head on. The customer might even waive the financial reporting requirements if we show our immediate intent to convert.”
Crosby Manufacturing was a $250-million-a- year electronics component manufacturing firm in 2005, at which time Wilfred “Willy” Livingston became president. His first major act was to reorganize the 700 employees into a modified matrix structure. This reorganization was the first step in Livingston’s long- range plan to obtain large government contracts. The matrix provided the customer focal point policy that government agencies prefer. After three years, the matrix seemed to be working. Now the company could begin the second phase, an improved MCCS policy.
On October 20, 2007, Livingston called a meeting with department managers from project management, cost accounting, management information systems (MIS), data processing, and planning. Livingston: “We have to replace our current computer with a more advanced model so as to update our MCCS reporting procedures. In order for us to grow, we’ll have to develop capabilities for keeping two or even three different sets of books for our customers. Our current computer does not have this capability. We’re talking about a sizable cash outlay, not necessarily to impress our customers, but to increase our business base and grow. We need weekly, or even daily, cost data so as to better control our projects.”
MIS manager: “I guess the first step in the design, development, and implementation process would be the feasibility study. I have prepared a list of the major topics which are normally included in a feasibility study of this sort.” [See Exhibit I.]
Livingston: “What kind of costs are you considering in the feasibility study?”
MIS manager: “The major cost items include input–output demands; processing; storage capacity; rental, purchase, or lease of a system; nonrecurring expenditures; recurring expenditures; cost of supplies; facility requirements; and training requirements. We’ll have to get a lot of this information from the Electronic data processing (EDP) department.”
EDP manager: “You must remember that, for a short period of time, we’ll end up with two computer systems in operation at the same time. This cannot be helped. However, I have prepared a typical (abbreviated) schedule of my own. [See Table I.] You’ll notice from the right-hand column that I’m somewhat optimistic as to how long it should take us.”
Livingston: “Have we prepared a checklist on how to evaluate a vendor?”
EDP manager: “Besides the benchmark test, I have prepared a list of topics that we must include in evaluating any vendor. (See Exhibit II.). We should plan to call on or visit other installations that have purchased the same equipment and see the system in action. Unfortunately, we may have to commit real early and begin developing software packages. As a matter of fact, using the principle of concurrency, we should begin developing our software packages right now.
EXHIBIT I. FEASIBILITY STUDY
• Objectives of the study • Costs • Benefits • Manual or computer-based solution?
Crosby Manufacturing Corporation Case Study Page 2 of 3
For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.
• Objectives of the system • Input requirements • Output requirements • Processing requirements • Preliminary system description • Evaluation of bids from vendors • Financial analysis • Conclusions
TABLE I TYPICAL SCHEDULE (IN MONTHS)
Activity Normal Time to Complete Crash Time to Complete
Management go-ahead 0 0
Release of preliminary system specs. 6 2
Receipt of bids on specs. 2 1
Order hardware and systems software 2 1
Flow charts completed 2 2
Applications programs completed 3 6
Receipt of hardware and systems software 3 3
Testing and debugging done 2 2
Documentation, if required 2 2
Changeover completed 22 15* * This assumes that some of the activities can be run in parallel, instead of in series.
EXHIBIT II. VENDOR SUPPORT EVALUATION FACTORS
• Availability of hardware and software packages • Hardware performance, delivery, and past track record • Vendor proximity and service-and-support record • Emergency backup procedure • Availability of applications programs and their compatibility with our other systems • Capacity for expansion • Documentation • Availability of consultants for systems programming and general training • Who burdens training cost? • Risk of obsolescence • Ease of use
Livingston: “Because of the importance of this project, I’m going to violate our normal structure and appoint Tim Emary from our planning group as project leader. He’s not as knowledgeable as your people are in regard to computers, but he does know how to lay out a schedule and get the job done. I’m sure your people will give him all the necessary support he needs. Remember, I’ll be behind this project all the way. We’re going to convene again one week from today, at which time I expect to see a detailed schedule with all major milestones, team meetings, design review meetings, et cetera, shown and identified. I’d like the project to be complete in 18 months, if possible. If there are risks in the schedule, identify them. Any questions?”
Crosby Manufacturing Corporation Case Study Page 3 of 3
For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.
References
Kerzner, H. (2022). Project management case studies (6th ed.). John Wiley & Sons, Inc.
- Crosby Manufacturing Corporation
- Eng essay
- EVALUATION PACKET
- Week 1 Payment Link
- .
- Psychology - Discussions
- Chef best company
- Research, select and review industry and companies of interest in areas of Operations, Supply and Value Chains in context of the global competitive...
- Writing Print Copy
- For Prof Dan
- 10 page evolution paper for FOR WIZARD KIM