Question 1

The first step in the project control process of the measurement and evaluation of project performance is to

Answer

Set a baseline plan

Determine the project objectives

Determine the project deliverables

Analyze the project budget

Review the project priority matrix

Question 2

The third step in the project control process of the measurement and evaluation of project performance is to:

Answer

Review the baseline plan with top management

Analyze inputs to the control system

Compare the plan against actual performance

Measure both progress and performance

Review spending with team members