Question 1
The first step in the project control process of the measurement and evaluation of project performance is to
Answer
Set a baseline plan
Determine the project objectives
Determine the project deliverables
Analyze the project budget
Review the project priority matrix
Question 2
The third step in the project control process of the measurement and evaluation of project performance is to:
Answer
Review the baseline plan with top management
Analyze inputs to the control system
Compare the plan against actual performance
Measure both progress and performance
Review spending with team members