BUS 419 QUIZ 2
olufunmilola
Question 1
- The ____ trade-off methodology is used to incrementally reduce the project duration with the smallest associated increase in incremental cost.
a.
time-quality
b.
time–cost
c.
schedule-quality
d.
cost-production
3 points
Question 2
- Earliest start time (ES) is the earliest time at which a specific activity can begin
a.
calculated on the basis of the project estimated start time and the estimated durations of approaching activities.
b.
calculated on the basis of the project estimated start time and the estimated durations of preceding activities.
c.
calculated on the basis of the project estimated finish time and the estimated durations of preceding activities.
d.
calculated on the basis of the project estimated start time and the estimated durations of succeeding activities.
3 points
Question 3
- A concentrated effort to accelerate project progress must be applied to the paths with negative slack to activities that
a.
are near term and those with long durations.
b.
are scheduled at the end of the project.
c.
are short in duration and can be easily completed.
d.
have the lowest cost.
3 points
Question 4
- Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.
a.
Cannot be calculated based upon information given.
b.
day 3
c.
day 7
d.
day 5
3 points
Question 5
- The estimated types and quantities of resources required for an activity together with the availability of those resources will influence the
a.
actual costs of work performed.
b.
project scope document description.
c.
estimated duration for how long it will take to perform the activity.
d.
project's acceptance criteria.
3 points
Question 6
- People sometimes perform to expectations, their effort will expand to fill the whole number of scheduled days allotted,
a.
even if part of the time for the task is waiting time.
b.
even if the number of resources assigned to the task is reduced.
c.
even if the activity could have been performed in a longer time.
d.
even if the activity could have been performed in a shorter time.
3 points
Question 7
- Activities in a network diagram are drawn in a ____ relationship because, from a technical standpoint, they must be performed in that sequence.
a.
serial
b.
vector
c.
parallel
d.
interlocking
3 points
Question 8
- Which of the following is likely not to be a process in a project management information system?
a.
Level or smooth the resources automatically.
b.
Use the nine-step problem solving method in the system.
c.
Test resolutions to any scheduling conflicts.
d.
Create charges for resources.
3 points
Question 9
- Resource leveling attempts to establish a schedule in which resource utilization is made as level as possible
a.
without extending the project beyond its required completion time.
b.
by assigning one resource to work per day.
c.
by extending the project beyond its required completion time.
d.
by adding additional resources to the project.
3 points
Question 10
- ___ is a method for developing the shortest schedule when the number or amount of available resources is fixed.
a.
Resource limited scheduling
b.
Resource leveling
c.
Resource evaluation scheduling
d.
Resource monitoring
3 points
Question 11
- Resource leveling uses a trial-and-error method to test delaying
a.
all non-critical activities
b.
all critical activities
c.
all activities with a positive slack
d.
only non-critical activities with positive slack
3 points
Question 12
- Resource requirements graphs based on an as-late-as-possible schedule are drawn
a.
based on each activity's earliest start time
b.
based on each activity's latest finish time.
c.
based on each activity's earliest finish time.
d.
based on each activity's latest start time.
3 points
Question 13
- The ____ is the amount that was budgeted to accomplish the work that was scheduled to be performed up to that point in time.
a.
cumulative budgeted cost (CBC)
b.
cumulative earned value (CEV)
c.
total budgeted cost (TBC)
d.
cumulative actual cost (CAC)
3 points
Question 14
- Allocating total project costs for the various elements to the appropriate work packages will establish
a.
the committed costs for the work package.
b.
the anticipated expense for the work package.
c.
a total budgeted cost (TBC) for each work package.
d.
how to apply resources to the work package.
3 points
Question 15
- Committed costs need to be treated in a special way so that the system
a.
periodically assigns a portion of their total cost to actual cost.
b.
audits the amounts assigned.
c.
enters the amount of the cost one time at the beginning of the project.
d.
enters the amount of the cost one time at the end of the project.
3 points
Question 16
- For a project, the TBC = $200,000, the CEV = $120,000, the CAC = $100,000. Which of the following statements is true?
a.
The project has a negative cost variance and corrective action is needed.
b.
The FCAC is greater than the budget and the project scope should be adjusted.
c.
The project is progressing well and should be continued.
d.
The CPI is less than 1.0.
3 points
Question 17
- To keep track of ____, it’s necessary to set up a system to collect, on a regular and timely basis, data on funds actually expended.
a.
budgeted cost of work scheduled
b.
budgeted cost of work performed
c.
actual cost on a project
d.
planned cost of the project
3 points
Question 18
- The contractor might try to negotiate payment terms that require the customer to do one or more of the following except
a.
make equal monthly payments based on the expected duration of the project.
b.
provide frequent payments, such as weekly or monthly payments rather than quarterly payments.
c.
make a single payment at the end of the project.
d.
provide a down payment at the start of the project.
3 points
Question 19
- A good forum for regularly reviewing, updating, and addressing risks is
a.
phone conversation with project stakeholders.
b.
project meeting.
c.
during social events to get inside information from others.
d.
the meeting for addressing the risk after it has occurred.
3 points
Question 20
- If the risks seem ____, the contractor may decide to not bid on a proposed project.
a.
easily mitigated
b.
within reason
c.
acceptable
d.
too great
3 points
Question 21
- Risks can be prioritized based on
a.
the amount of funds planned to manage the risk.
b.
the project team member that identified the risk.
c.
the amount of time the project team has to manage the risk.
d.
the likelihood of occurrence and degree of impact.
3 points
Question 22
- ____ includes taking action to prevent or minimize the likelihood of occurrence or the impact of such unfavorable events.
a.
Naming the person responsible for the risk response plan
b.
Managing risk
c.
Identifying the trigger point
d.
Taking chances