lOMoARcPSD|22671317
BUSI 411 Exam 3 – 202120 Spring 2021
BUSI
International Business (Liberty University)
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
es My
Profile
Jennifer Harris1
Student Dashboard myBlackboard Libraries Resourc
Course Content
...Assignmen
ts
Review Test Submission: Exam 3
Review Test Submission: Exam 3
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 1/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Question 2
3 out of 3 points
Focusing a supply chain on is a modern way of ensuring high-
quality inputs and extending an organization’s continuous improvement
efforts.
Selected Answer:
close, collaborative ties with suppliers
Response correct
Feedback:
MC Qu. 94 Focusing a supply chain
on... AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 09-02 Define the term quality as it
relates to
products and as it relates to services.
Topic: Quality and the Supply Chain
Question 3
3 out of 3 points
The quality certification that deals primarily with conformance to
customer requirements is ISO
; ISO
is concerned
primarily with the organization's effect on the environment.
Selected Answer: 9000; 14000
Response correct
Feedback:
MC Qu. 56 The quality certification that deals
primarily... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 09-08 Discuss quality certification and its
importance.
Topic: Quality Certification
Question 4
3 out of 3 points
Cause-and-effect diagrams are sometimes called:
Selected Answer: fishbone (Ishikawa) diagrams.
Response correct
Feedback:
MC Qu. 88 Cause-and-effect diagrams
are... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 1 Easy
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 2/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Learning Objective: 09-13 Describe and use various
quality
tools.
Topic: Quality Tools
Question 5
3 out of 3 points
Before a dimension of quality can be made operationally useful, it must
be restated in some form.
Selected Answer:
measurable
Response correct
Feedback:
MC Qu. 97 Before a dimension of quality can be
made...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 09-02 Define the term quality as it
relates to
products and as it relates to services.
Topic: Insights on Quality Management
Question 6
3 out of 3 points
The traditional view is that the optimum level of inspection is where the:
Selected Answer:
total cost of inspection and defectives is minimum.
Response correct
Feedback:
MC Qu. 71 The traditional view is that the optimum...
AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 10-02 Discuss the basic issues of
inspection.
Topic: Inspection
Question 7
3 out of 3 points
The chair of the operations management department at Quality
University wants to construct a p-chart for determining whether the four
faculty teaching the basic P/OM course are in control with regard to the
number of students who fail the course.
Accordingly, he sampled 100 final grades from last year for each
instructor, with the following results:
Instructor
Number
of
Failures
Prof. A 13
Prof. B 0
Prof. C 11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 3/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Prof. D 16
What is the estimate of the mean proportion of failures for these instructors?
Selected Answer: .10
Response correct
Feedback:
MC Qu. 95 The chair of the operations management
department...
AACSB: Analytical
Thinking
Blooms:
Apply
Difficulty: 2 Medium
Learning Objective: 10-05 Use and interpret control
charts. Topic: Statistical Process Control
Question 8
3 out of 3 points
Which of the following quality control sample statistics indicates a
quality characteristic that is an attribute?
Selected Answer:
proportion
Response Feedback: correct
MC Qu. 55 Which of the following quality control
sample...
AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms:
Remember
Difficulty: 2 Medium
Learning Objective: 10-05 Use and interpret control
charts. Topic: Statistical Process Control
Question 9
3 out of 3 points
Which of the following is not a step in the control process?
Selected Answer:
100 percent inspection.
Response correct
Feedback:
MC Qu. 65 Which of the following is not a step in
the... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 3 Hard
Learning Objective: 10-03 List and briefly explain the
elements of
the control process.
Topic: Statistical Process Control
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 4/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Question 10
3 out of 3 points
When a process is in control, it results in there being, on average, 16
defects per unit of output. c-chart limits of 4 and 28 would lead to a
percent chance of a
Type I error.
Selected Answer: 0.26
Response correct
Feedback:
MC Qu. 111 When a process is in control, it results in there...
AACSB: Analytical Thinking
Accessibility: Keyboard
Navigation
Blooms: Apply
Difficulty: 1 Easy
Learning Objective: 10-04 Explain how control charts are
used to
monitor a process and the concepts that underlie
their use.
Topic: Statistical Process Control
Question 11
3 out of 3 points
In doing aggregate planning for a firm producing paint, the aggregate
planners would
most likely deal with:
Selected
Answer: just gallons of paint, without concern for the different
colors and sizes.
Response correct
Feedback:
MC Qu. 33 In doing aggregate planning for a firm
producing... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 11-01 Explain what aggregate planning
is and
how it is useful.
Topic: Aggregate Planning and Master Scheduling
Question 12
3 out of 3 points
Using variable pricing in response to demand variability to maximize revenue
using perishable capacity is known as:
Selected Answer: yield management.
Response correct
Feedback:
MC Qu. 59 Using variable pricing in response to
demand...
AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 5/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Difficulty: 2 Medium
Learning Objective: 11-06 Discuss aggregate
planning in
services.
Topic: Aggregate Planning in Services
Question 13
3 out of 3 points
Aggregate planning in the case of a high-volume product output business
such as a restaurant is directed toward:
Selected Answer:
smoothing the service rate.
Response correct
Feedback:
MC Qu. 63 Aggregate planning in the case of a high-
volume... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 11-06 Discuss aggregate
planning in
services.
Topic: Aggregate Planning in Services
Question 14
3 out of 3 points
Which one of the following is not a basic option for altering demand?
Selected Answer: subcontracting
Response correct
Feedback:
MC Qu. 39 Which one of the following is not a
basic... AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 11-02 Identify the variables decision
makers have
to work with in aggregate planning.
Topic: Aggregate Planning and Master Scheduling
Question 15
3 out of 3 points
A firm has 56 units of product X on hand. Forecasts of demand are for 20
units per week. An MPS quantity of 100 units is planned to arrive in
period 3. Customer orders are 24 for period 1, 18 for period 2, and 15 for
period 3.
What quantity is available for commitment to new customers prior to the
receipt of the MPS quantity in week 3?
Selected Answer: 14
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 6/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Response correct
Feedback:
MC Qu. 68 A firm has...
AACSB: Analytical
Thinking
Accessibility: Keyboard Navigation
Blooms: Apply
Difficulty: 2 Medium
Learning Objective: 11-08 Describe the master scheduling
process
and explain its importance.
Topic: The Master Scheduling Process
Question 16
3 out of 3 points
Which one of the following is not an input in an MRP system?
Selected Answer:
planned-order schedules
Response Planned-order schedules are outputs from MRP.
Feedback:
MC Qu. 46 Which one of the following is not an
input...
AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 12-02 Describe the inputs, outputs, and
nature
of MRP processing.
Topic: MRP Inputs
Question 17
3 out of 3 points
Under lot-for-lot, order sizes for component parts are essentially
determined directly from which one of the following?
Selected Answer:
net requirements
Response correct
Feedback:
MC Qu. 55 Under lot-for-lot, order sizes for
component...
AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 12-03 Explain how requirements in a
master
production schedule are translated into material
requirements for lower-level items.
Topic: MRP Processing
Question 18
3 out of 3 points
Which one of the following most closely describes net requirements for the
current
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 7/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
period?
Selecte
d
Answer
:
Respons
e
Feedbac
k:
gross requirements for current period - projected on-hand
inventory for current period
correct
MC Qu. 52 Which one of the following most closely...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 12-03 Explain how requirements in a
master
production schedule are translated into material
requirements for lower-level items.
Topic: MRP Processing
Question 19
3 out of 3 points
The MRP input storing information on the status of each item by time period
(e.g.,
scheduled receipts, lead time, lot size) is the:
Selected
Answer:
Respons
e
Feedbac
k:
inventory records.
Inventory records contain this information.
MC Qu. 51 The MRP input storing information on
the...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 12-02 Describe the inputs, outputs, and
nature
of MRP processing.
Topic: MRP Inputs
Question 20
3 out of 3 points
Bunny Helpers, Inc., has just received an order for 100 Deluxe Easter Baskets, which
must be
ready for delivery at the start of week 6. An MRP planner has prepared the
following table
showing product structure, lead times (orders are lot-for-lot), and
quantities on hand:
Deluxe Easter Basket BOM Lead Time On-Hand
Deluxe Easter Basket 1 week 10
Dark Chocolate Truffles (2 per) 2 weeks 30
Carved Chocolate Eggs (4 per) 1 week 50
Each Deluxe Basket contains two dark chocolate tru½es and four carved
chocolate eggs.
How many dark chocolate eggs should be ordered?
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 8/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Selected Answer: 310
Response correct
Feedback:
MC Qu. 76 Bunny Helpers, Inc., has just received an...
AACSB: Analytical
Thinking
Blooms:
Apply
Difficulty: 2 Medium
Learning Objective: 12-03 Explain how requirements in a master
production schedule are translated into material requirements for
lower-level items.
Topic: MRP Processing
Question 21
3 out of 3 points
The Baldrige award can only be won by manufacturing organizations.
Selected Answer: False
Response The Baldrige Award is awarded to organizations in multiple
categories
Feedback:
including service, health care, and education.
TF Qu. 8 The Baldrige award can only be
won by... AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 1 Easy
Learning Objective: 09-07 Compare the quality
awards. Topic: Quality Awards
Question 22
3 out of 3 points
A c-chart is used to monitor the number of defects per unit for process output.
Selected Answer: True
Response A c-chart monitors the number of defects per unit for process
output.
Feedback:
TF Qu. 22 A c-chart is used to monitor the number of...
AACSB: Reflective Thinking
Accessibility: Keyboard Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 10-04 Explain how control charts are used
to
monitor a process and the concepts that underlie their
use.
Topic: Statistical Process Control
Question 23
3 out of 3 points
Master schedulers are employed primarily by service organizations.
Selected Answer: False
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&return… 9/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
Response Master schedulers are primarily employed in manufacturing, with
most
Feedback: manufacturing organizations having a master scheduler.
TF Qu. 21 Master schedulers are employed
primarily by... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms:
Remember
Difficulty: 1 Easy
Learning Objective: 11-08 Describe the master scheduling
process and
explain its importance.
Topic: The Master Scheduling Process
Question 24
3 out of 3 points
Safety time is sometimes used in MRP rather than safety stock quantities.
Selected Answer: True
Response
Safety time is a substitute for safety stock; particularly when lead
Feedback: times are variable.
TF Qu. 24 Safety time is sometimes used in MRP
rather... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms: Remember
Difficulty: 2 Medium
Learning Objective: 12-02 Describe the inputs, outputs, and
nature
of MRP processing.
Topic: Other Considerations
Question 25
3 out of 3 points
Independent demand tends to be more "lumpy" than dependent demand,
meaning that we need large quantities followed by periods of no demand.
Selected Answer: False
Response Independent demand from customers for end items tends to be
Feedback: distributed more uniformly throughout the planning horizon.
Dependent demand for components tends to be more lumpy
due to lot sizing in the master production schedule and as we
move to lower levels of the bill of materials in the MRP
explosion.
TF Qu. 3 Independent demand tends to be more
"lumpy"... AACSB: Reflective Thinking
Accessibility: Keyboard
Navigation
Blooms:
Understand
Difficulty: 3 Hard
Learning Objective: 12-03 Explain how requirements in a
master
production schedule are translated into material
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
requirements for
https://learn.liberty.edu/webapps/assessment/review/review.jsp?
attempt_id=_95683242_1&course_id=_749216_1&content_id=_45101724_1&retur… 10/11
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
lower-level items.
Topic: MRP
Processing
Monday, February 8, 2021 8:47:36 PM EST
←
OK
lOMoARcPSD|22671317
2/8/202
1
Review Test Submission: Exam 3 – 202120 Spring
2021
BUSI...
https://learn.liberty.edu/webapps/assessment/review/review.jsp?