1
MANAGING STRATEGIES FOR THE FULFILLMENT OF PUBLIC
INVESTMENT INITIATIVES IN GUYANA
Section 1: Foundation of the Study
Researchers have found weak public investment management institutions in many
low-income and developing countries (e.g., Klakegg & Volden, 2017; Volden & Samset,
2017). Khan, Waris et al. (2019) found that public institutions could considerably
increase project efficiency in the form of value for money through a prudent investment
program with business strategy alignment. Improved infrastructure investment projects
may result in long-term economic gains with links to other sectors. For example, in India,
enhanced railroads decreased trade costs with increased profits for producers and reduced
market prices, improving citizens' real income (Donaldson, 2018. The most sought-after
project management studies are those of project success factors and causes of project
failure. Project failure was first popularized as a topic for research in 1986 at the annual
Project Management Institute (PMI) seminar and symposium and has since become one
of the most discussed themes, according to Montequín et al. (2018). Researchers are
continually looking for recommendations for the necessary actions to derive the most
significant benefit from superior quality research that enhances knowledge.
Background of the Problem
While projects are the building blocks for economic development, developmental
plans will only appear as a simple wish list without successful preparation and
implementation. For example, public sector projects have not yielded their citizens'
intended results (Arezki et al., 2017). Many projects delivered poor results because of
misaligned project outcomes with government management strategies, including time,
cost and scope, cost overruns, corruption, and reduced project maintenance (Arezki et al.,
2
2017; Cristóbal et al., 2018; Joslin & Müller, 2016). Adeyemi and Idoko (2008)
recommended a new project model in a seminal study using PMI’s guide to project
methodology. The World Bank forged a partnership with PMI to strengthen project
management applications in developing countries. It was seen as a valuable consideration
because the institution represented the global conception for project management,
according to Waheed (2016).
Guyana is an excellent case for further study because experiences have shown no
formal guidelines within the various agencies to dictate how public projects should be
selected and managed. Often, the users do not experience the fullest benefits from the
investments (Shako, 2016). The World Bank (2018) estimated that Guyana’s gross
domestic product (GDP) would surge from the newly discovered oil and gas sector. With
increasing GDP and foreign direct investments, both will stimulate a myriad of public
and private projects in Guyana. The government can execute its public sector investment
programs (PSIP) to create competitive advantages in businesses that benefit citizens.
Problem Statement
Many PSIPs experience poor project performance and failure because of the
misalignment between the government strategies and project outcomes (Erceg & Gukam,
2018; PricewaterhouseCoopers, 2017). In a survey, strategic implementation
misalignment accounted for 37% of the common factors associated with poor
performance and project failure (PMI, 2017a). The general business problem is that the
common factors of management capability, power structures, and the external project
environment have caused project outcomes to be misaligned with government strategy.
3
The specific business problem is that some project managers in the public sector struggle
to maximize project performance because they lack strategies to align the project
outcomes with the government’s strategies.
Purpose Statement
The purpose of this qualitative multiple case study was to explore effective
strategies that public sector project managers can use to align the project outcomes with
government strategies to maximize project performance. The specific population was
those public sector project managers who successfully aligned their projects’ outcomes
with government strategies and worked for four project-based units within the
geographic administrative region of Demerara/Mahaica (Region 4) Guyana. They
participated in a semistructured interview and provided their perspectives and
experiences in project management, which formed the source of the data collection
process. A project is determined aligned if 80% of its expected outcomes are aligned with
the organizational strategy (PMI, 2017a). The examined project reports verified the
successful alignment from three constructs: (a) identification of set goals from the
baseline studies and how they were captured within the project goals on a percentage
basis, (b) examination of each of the alignment factors within the cost, time, and budget,
and (c) examination of the end user's satisfaction from the stated goals of both the project
and organization, all from a compliance rate of at least 80%. The study may contribute to
positive social change if project managers can use the study findings to create a
community of successful project practitioners to implement projects better.
4
Nature of the Study
The three research methods are qualitative, quantitative, and mixed methods, each
with unique characteristics depending on the study’s purpose (Marshall & Rossman,
2016). Quantitative methods are appropriate for measuring a phenomenon’s impact,
which involves studying situations that can influence outcomes using experiments and
surveys (Molina-Azorin et al., 2017). The study objective required a deeper
understanding of the phenomenon from knowledge-gathering, which does not involve
variables. Given the qualitative nature, the research study did not include statistical tests
of variables. The design methods associated with quantitative and mixed methods were
unsuitable because qualitative research does not account for inferential statistics.
The four qualitative designs are (a) narrative, (b) phenomenological, (c)
ethnographic, and (d) case study, each with unique designs and attributes. Researchers
use the narrative design to explore a research subject's specific life experiences (Johnsen,
2016). Researchers use the phenomenological design when studying individuals’
perceptions and experiences (Neubauer et al., 2019). Ethnographic is another design used
by researchers to examine complex undertakings. Ethnographic researchers immerse
themselves within a specific context to gather the data (Fusch & Ness, 2015). The study's
purpose did not require the study of individuals’ perceptions, life stories, or immersion
into a group. Instead, I explored strategies for aligning projects’ outcomes with the
government’s strategies, so I selected a case study design. Case studies offer researchers
a better understanding of a phenomenon's “how and why” (Yin, 2018). The multiple case
study design was suitable for the study. I explored the phenomenon using open-ended
5
questions, observations, coding, methodological triangulation, and documentation review,
mainly because of the unclear circumstances and events when the phenomenon was
explored (see Fusch et al., 2018).
Qualitative Research Question
RQ: What strategies do public sector project managers use to align project
outcomes with government strategies to maximize project performance?
Interview/Survey Questions
1. What techniques do you use to manage relationship dynamics, engagement,
and project stakeholders' support?
2. What techniques and tools do you use to handle project attributes such as
project scope, timelines, budgets, risk, quality, and complexity?
3. What are the critical challenges associated with aligning infrastructure
projects with business management techniques and tools, and how have the
challenges been addressed?
4. What techniques do you use that allows for support and resources from the
ministry to ensure project success?
5. How and when do you leverage or mitigate organizational characteristics,
such as governance, structure, systems, incentives, and socio/cultural factors,
to ensure project management success?
6. How is the concept of alignment communicated throughout the organization,
and what are its effects on the project deliverables and milestones?
7. How do you share your personal project experiences?
6
8. How are issues and constraints dealt with within the project management
processes?
9. What other feedback can you provide that you think can be critical for project
success?
Conceptual Framework
The conceptual framework for the study was the contingency theory. According
to Fiedler (1964), there is no single suitable method of doing things. The contextual
setting will dictate the best workable approach, described as “job engineering.” The idea
is that a project manager's role is to find the best possible fit between the organization, its
environment, and subsystems. According to Fiedler (1964), leadership effectiveness is
helpful from two methods, the leaders’ general temperaments and the circumstances they
find themselves. Therefore, selecting an outlook broader than one tailored just for a
unique/individual project is recommended by Teller et al. (2014). The suggestion implied
that effectiveness lies in applying management behaviors to specific situations.
Researchers have found that project performance offers contradictory results
because of the varying situational and environmental factors. The contingency approach
is functional when exploring project practitioners' alignment (Floricel et al., 2016; Khan,
Waris, et al., 2019). Researchers found the contingency theory to be a simplified
approach that involves three different conceptual alignments: selection, interaction, and
systems (Joslin & Müller, 2016). Strategies, processes, and structures can affect the
project outcomes, all a logical progression of ideas between such studies' structural
elements (Saunders et al., 2016).
7
In approaching projects with complexity, researchers found an inverse
relationship with project success. The relationship is affected by strategy alignment, for
which seasoned project practitioners used tools, techniques, and processes for successful
alignment (Joslin & Müller, 2016). The choice of the contingency theory allows for
insights into how best to accommodate those tools, techniques, and processes with the
organization’s management strategies within a given environment to satisfy project
management's objectives (Floricel et al., 2016). The contingency theory was most
beneficial for this study because it captured project novelty and complexity. I provided a
medium by which skilled public sector project practitioners demonstrated successful
project outcomes' alignment with government strategy maximized project performance.
Operational Definitions
To avoid misinterpretation of the concepts employed, a contextual understanding
of the terms used is expressed in the following definitions:
Infrastructure project: The underlying physical system of a nation’s
transportation system, electrical system, water system, railway system, hospitals, and
other publicly accessed and government-funded projects for the sole purpose of
improving the standard of living of citizens and residents (Cole, 2017)
Project success: The result of a project meeting the expected/proposed
deliverables that can be summarized in the triple project constraint of time, quality, and
cost (PMI, 2018).
8
Project complexity: The extent of structural complexity, uncertainty, pace,
dynamic complexity, novelty, and social-political and institutional complexities (Bolzan
de Rezende & Blackwell, 2019).
Project Sector Investment Program: A“roadmap” exercise for governments to
have in place with comprehensive statements on development objectives, policies, and
programs for each of the key sectors to strengthen the linkages among programs across
agencies and sectors (World Bank, 2018)
Strategic alignment: The process and the result of linking an organization's
structure and resources with its strategy and business environment (Zolfaghari et al.,
2017)
Portfolio management: The identification, prioritization, authorization,
management, and control of projects, programs, and other related work to achieve
specific strategic business objectives (PMI, 2017a).
Socioeconomic development: The process that involves both social and economic
development in a country. The measured indicators are the GDP, life expectancy, and
employment levels, among others (O'Neill-Carrillo et al., 2018).
Assumptions, Limitations, and Delimitations
Assumptions
Assumptions are factual beliefs that researchers have found indispensable when
conducting a study, although they cannot be proven (Pyrczak & Bruce, 2017; Simon &
Goes, 2018). Researchers make assumptions concerning the participants' interviews on
the premise that the constraints associated with time and effort to validate each
9
participant's answer allow for the assumptions (Simon & Goes, 2018). I assumed that the
selected project managers were adequately diverse in experience and would report their
project experiences accurately. Given the anonymity requirement, I further believed that
the chosen project managers provided their honest reflections of their project success
indicators. Anonymous participants are more likely, to be honest and accurate than when
their participation is known (Allen, 2017). To promote a fair, reasonable, and factual
response from the participants, I notified them of the right to refuse to answer any
question. All responses would remain confidential concerning any classified information
provided.
Limitations
Limitations are those potential weaknesses that result in constraints or flaws and
are beyond the researcher's control. Limitations can also influence the outcome and
validity of a study (Pyrczak & Bruce, 2017). Researchers identify the specific limitations
of their studies to prevent the inappropriate generalizations of the findings and
conclusions (Simon & Goes, 2018). My research included project managers who
successfully aligned their projects’ outcomes with government strategies to maximize
project performance. My foremost concern was the lack of random selection in the
chosen participants resulting in validity issues due to possible selection bias. The
selection bias often affects the generalization of the results beyond the sample.
Researchers may not replicate my research's conclusions and recommendations if their
study settings are relatively different. Yin (2017) suggested using interview protocols to
maintain uniformity during interviews to mitigate bias.
10
Delimitations
Delimitations represent a study's parameters within the researcher's control that
define the survey's scope (Pyrczak & Bruce, 2017). Researchers use delimitations to
explain the extent of the research scope's span (Simon & Goes, 2018). Researchers
should not generalize my study's conclusions and recommendations if their research
scope is not similar. My research included a specific population: A group of project
managers who work for four project-based units. They participated in an interview that
provided their perspectives and experiences in project management. The selected
organizations are those with successful project results from seasoned project practitioners
who demonstrated alignment of project outcomes with government management
strategy, measured from three constructs: (a) identification of the set goals from the
baseline studies and how they were captured within the project goals on a percentage
basis; (b) exploration of each of the alignment factors of cost, time, and budget; and (c)
examination of the end user's satisfaction from stated goals of both the project and
organization, all from a compliance rate of at least 80%. A successfully aligned project
represents a compliance rate of over 80% within budget, time, and scope while meeting
original goals and business intent (PMI, 2017a).
Significance of the Study
Public sector investment project misalignment can affect other businesses with
strategies linked to the public projects’ completion. While citizens generally do not
thoroughly scrutinize their government’s expenditures, the net result is sometimes the
misallocation of public spending with struggling economies (Klakegg & Volden, 2017).
11
Public investment faces unique challenges from the external environment. Finding a
functional relationship between organization alignment attributes and successful project
outcomes may provide new critical success factors for public sector investment. A
project may create societal value when it meets social and environmental needs, bringing
positive social change by allocating the project resources to social welfare (Santhosh &
Baral, 2015).
Contribution to Business Practice
The study result may contribute to better public investment practices by providing
policymakers with the competence to select and implement public strategic-based
investment projects needed for economic development. Enhanced knowledge about
alignment and performance output methods, coupled with government strategic
development, can improve project decision-making resulting in a competitive advantage
for other projects with linked strategies to that public investment.
Implications for Social Change
The study results may lead to positive social change through enhanced public
sector project management, fostering citizens' satisfaction. In addition, maximized
projects’ outcomes will enable the government to enjoy value for money in its
expenditure programs, which helps expand social programs for development. Essential to
the project selection and planning is supporting a clear understanding of those fiscal
conditions and associated risks (Ahmad et al., 2018). Public project fulfillment may
become less tedious as project managers better understand project outcomes' alignment
with government strategies for success in public infrastructure programs.
12
A Review of the Professional and Academic Literature
This literature review focuses on the concept/role of strategic management in
achieving public sector infrastructure project efficiency in developing countries such as
Guyana. This review explored public sector project managers' strategies to maximize
project performance and align project outcomes with government strategies. According to
Saunders et al. (2015), the literature review presents a perspective that speaks to the
theoretical approach within a framework for the conducted research. The review also
accounts for the associated literature concerning the specific business problem forming
the research justification. The specific business problem was that some project managers
in the public sector struggle to maximize project performance because they lack strategies
to align the project outcomes with the government’s strategies.
Extensive research on government strategy alignment may help public sector
project managers understand how to employ tactics to maximize project performance.
However, few researchers have ventured into the field owing to the complex project
environment in which public projects operate (Cristóbal et al., 2018). Further, researchers
have noted significant causative factors that affect project outcomes associated with
infrastructure projects (Cristóbal et al., 2018). To fully appreciate the challenges and the
impending risks concerning project success, I explored the professional and academic
literature available to public project managers to align with government strategies to
maximize project outcomes.
The literature review provides a description and an analysis of other researchers'
works (Saunders et al., 2015). The literature review outlines a systematic approach a
13
researcher uses to identify and analyze the work of other researchers. Literature mapping
effectively organizes a significant amount of data and aids in synthesizing other research
findings. A researcher can use the literature mapping to determine the relationship
between themes and highlight research gaps, according to Chei-Chang (2009).
The reviewed literature provided the theoretical lens through which I considered
the contingency approach. Because no single management approach will yield a
compelling result, a more adaptive system is needed. Therefore, in using the literature
mapping, I structured the literature review into the following topics: (a) conceptual
framework, the contingency approach; (b) development assistance and its effect on public
sector development; (c) public projects investment and its linkages with other sector
development; (d) PSIP in developing countries, (e) general infrastructure project
background information on Guyana; (f) public sector investment in Guyana; (g)
importance of project management; (h) project goals, ethics, and communication
management; (i) project management processes; (j) business management strategy in
project management; (k) project success factors; (l) best practices in project management;
(m) alignment of project management with organizational strategies; and (n) project,
programs, and portfolio management.
In considering the literature review, I relied on information from the following
resource centers; Walden University online library, Google Scholar, ProQuest, Emerald
Management Journals, Business Source Complete, ABI/INFORM, SAGE, and EBSCO.
The resource collection included peer-reviewed journal articles, dissertations, newspaper
articles, and textbooks, all of which informed the subject of this study. The keywords
14
used to search the databases for references relevant to the study's objectives included
contingency theory, project management theory, infrastructure project management,
project management governance, project success, and infrastructure project failure. I
achieved Walden University's stipulated requirements of having 85% of my references
peer-reviewed and published well within the 5-year requirement before my expected
graduation date.
Conceptual Framework
The contingency theory was the conceptual framework used for this study.
According to the theorists, there is no single correct method of doing things (Burns &
Stalker, 1961; Fiedler, 1964). However, the contextual setting will dictate the best
workable approach, described as ‘job engineering’ (Fiedler, 1964). Internal and external
circumstances will decide the optimal course of action. The contingency approach is
considered the most appropriate for investment projects’ management. Its flexibility has
given the typical uncertainty from the nonroutine site environment of operations and
supportive adaptation (Teller et al., 2014). Given organizations' uniqueness, their
management system (both mechanistic and organic) must respond to the market's
changing dynamics and the technological environment, whether stable or innovative
(Burns &Stalker, 1961).
The mechanistic and organic management systems proposed by Woodward
(1958) and later discussed by Burns and Stalker (1961) offer no single management
practice to achieve organizational resource management efficiency. The perfect
management system will depend on the changing market and technological environment
15
(Burns & Stalker, 1961). The mechanistic management method involves stable conditions
with full knowledge of its requirements through its breakdown structure. The organic
process of management involves project characteristics subject to changing conditions. It
would not be possible to provide scope details at the project’s onset (Wysocki, 2019).
Therefore, the organic system allows for teams to become self-organizing, self-sufficient,
and self-directing.
The current understanding of the contingency theory shaped by Nebeker (1975) is
an integration of Fiedler’s work on leadership style effectiveness, according to Northouse
(2019). Starkey et al. (1991) consolidated the contingency theory using strategic
flexibility to extend the framework to organizational choice utilizing the goodness-of-fit
of strategy and business activities against management systems’ structure. Besides,
project management challenges of complexity and uncertainty allow for no formal or
universally accepted theoretical foundation for project management. The most considered
and applied theoretical perspective is that of contingency theory. Therefore, the project's
success is contingent upon a combination of organizational, project, and people-based
determinants (Fiedler, 1964).
The contingency model is appropriate when explaining the organization's
decision concerning the project management strategies' design. The process helps address
diversity in project contexts in changing environmental conditions (Wysocki, 2019).
Project complexity and project uncertainty are two variables that project managers
encounter on every project. They are even more challenging within public sector
megaprojects, according to Hazir and Ulusoy (2020). Saunders et al. (2016) described
16
project complexity as a state where all facts concerning a particular situation are
unknown. Project uncertainty is seen as a potential favorable or unfavorable risk that
surfaces throughout a project (Qazi et al., 2020). Because projects include ever-changing
dependent and contingent activities, contingency theory regularly works as a designated
framework for describing success or failure.
Several studies in the literature review focused on project complexity and the
factors that can influence project success. While there is little evidence concerning
differences in complexity and project success factors, researchers have found that project
success has an inverse relationship to project complexity (Floricel et al., 2016).
Researchers have also seen the need for a clear distinction in complexity, as
categorization helps identify the appropriate model for managing the project (Cristóbal et
al., 2018). Depending on the complication's source, the complexity may be classified as
either structural, technical, directional, or temporal that needs to be integrated for a better
approach. Cristóbal et al. (2018) found that managing projects in complex environments
require aligning management techniques that support planning, scheduling, executing,
and controlling. While strategy formulation is delicate, Adeyemi and Idoko (2008) found
that putting a strategy to work can be even more challenging within cross-functional
cultures.
The contingency approach may help understand risk management for complex
projects in explaining an organization’s success or failure (Wysocki, 2019). Complexities
in project management were considered best in light of the contingency theory because of
its alignment with my study purpose. The challenges of the external project environment,
17
power structures, and management capability are the complex factors that public sector
project managers must meet. The benefit is that it will result in successful project
outcomes aligned with the government strategies that maximize project performance.
Oputa (2017) combined the techniques used to manage successful megaprojects as a
simplified approach within three conceptual alignments: selection, interaction, and
systems.
Researchers use contingency theory analysis to determine the relationship
between a firm’s structure and its environment and how its structure will react when
faced with contingencies at different performance levels (San et al., 2018). The
contingency theory is a concept that promotes flexibility in the choice of actions to
succeed in an uncertain environment. Project managers get insights into how best to
apply management strategies within the given context to satisfy project management
outcomes (Cristóbal et al., 2018). Project results are superior when project practitioners
match executive actions with internal organizational characteristics and external
environments. According to Joslin and Müller (2015), the approach must focus on the
internal project characteristics and those project management activities that need to match
the project's novelty and complexity.
Horning's (2018) conceptual framework, a product of Fiedler’s contingency
theory, focused on organizations' project success in Pennsylvania health care. The
researcher found a high possibility of completion when the project manager knows the
essential factors that define success or failure and can modify strategy alignment when
appropriate. Oputa (2017) opined that contingency theory has now widened to include a
18
class of methods whose outcomes are contingent on a multiplicity of factors. Oputa
(2017) invoked a specific application for those unique situations. It requires a
methodology that explains all processes in aggregate, and its relatedness must be
considered. Because there is no single best way to manage, there will be no universal
helpful strategy in any given situation. Therefore, the contingency approach helps
promote flexibility in any chosen actions to succeed in an environment of complexity and
uncertainty.
Development Assistance and its Effect on Public Sector Development.
At a conference in Ethiopia, both low-income and developing countries pledged
their commitment to resolve their bilateral partners' developmental challenges. The hope
was that the financial aid would be used prudently to build countries' public expenditure
for economic growth. The result revealed that government expenditure negatively affects
economic growth in the short and long run (United Nations, 2015). Still, the developing
countries had asked their developmental partners for space and independence to prepare
domestically (United Nations, 2015). The conference provided a sound basis for
development funding; on the one hand, the global community wanted a collective
sustainability accord. Simultaneously, the developing countries' leaders hoped their donor
partners honored the pledged assistance needed to achieve the United Nations millennium
goals (United Nations, 2015). Developing countries depended on assistance for their
long-term infrastructural development, even though the literature points to many
developing countries having diminishing returns to aid (Presbitero, 2016).
19
Research on the various bottlenecks to developmental assistance impeding
countries' capacities to absorb foreign aid found the primary challenge to be cross-
cultural complexities (Presbitero, 2016). A project assessment by the World Bank
measured the extent to which cross-country differences impacted the project outcomes
and found the following to be impactful: (a) institutional quality, (b) macroeconomic
policies, and (c) macroeconomic performance, which together explain project outcome
variability (Bulman et al., 2015). Bulman et al. (2015) found that country-level macro
measures of sound institutional policies are correlated with project outcomes. This
explains how country-level performance is essential for the effective use of resources.
The empirical literature does not provide a consistent body of evidence supporting
a positive association between the scaling-up of public investment and economic growth,
according to Presbitero (2016). In contrast, Easterly and Rebelo (1993) found that public
investment program outputs correlate with growth across countries in a seminal study.
Similarly, Global Infrastructure Hub (2019) found that every dollar spent on
infrastructure development yields an estimated increased GDP between USD 0.05 to
USD 0.25, which created an economic return of between 5% - 25% in the long run
(Global Infrastructure Hub, 2019). The opposite is true in Devarajan et al.’s (1996)
study, which found that public capital in developing countries' expenditures was
negatively associated with economic growth. The economic arguments led to another
study premised on a precisely formulated synthetic physical infrastructure index that
estimated public investment's productivity impact (Calderón et al.,2015).
20
Similarly, researchers found that 10 % of infrastructure expenditure increased the
per capita outcomes by 0.7 % in the long run. Researchers can also point to the literature
supporting the notion that infrastructure investment could create long-term development
(e.g., Easterly & Rebelo, 1993; Global Infrastructure Hub, 2019). Besides, even when
project implementation ends, the short-term outcomes may be negligible. The long-term
outcomes can be successful because the broader sets of goals are met instead of a narrow
subset (Radujkovic & Sjekavica, 2017).
The historical experiences of the 1980s concerning the effects of government
infrastructure investments on productivity provided little guidance on projects'
management worthiness. For example, several public-sector investment projects
delivered poor results both in the short and long term, primarily because of cost
overruns, corruption, and reduced project maintenance (Arezki et al., 2017). Given the
challenges of the developing countries, the World Bank and other financial institutions
have since created social safeguarding norms and policies for their funded projects.
Those safeguards resulted from the bank’s challenges with their continued loan
advancement to developing countries (World Bank, 2017).
Despite having achieved independence in 1966, Guyana still lacks the local
capacity for project execution and management. The international institutions did not
spare that observation from their country report (International Monetary Fund[IMF],
2017; World Bank, 2017). Guyana’s traditional approaches to public administration offer
little value in preparing project administrators for the complex tasks of planning and
executing public investment projects, according to the IMF country report (2017).
21
Guyana’s unique challenges include the external project environment, power structures,
and management capability. Shako (2016) opined that the challenges also include (a)
poor construction designs missing critical details; (b) costs overrun with missed
deadlines; (c) approved substandard work from inadequate consulting supervision; and
(d) early destruction leading to remedial work within the defect liability period and, in
other cases, well within design life-spans, for which there were little or no penalized
action against the contractor. In addition, government bureaucracy and regulatory
measures are inadequate to deal with the dynamics of change. The IMF country report
(2017) found little consideration when formulating operational frameworks for project
management as an integrated system. Guyana’s sugar industry modernization is a case of
strategy misalignment. Singh (2015) argued that modernization occurred when the world
market prices for sugar were dramatically declining and still pursued without any
projected payback plan. Singh noted that a detailed sensitivity analysis concerning
pricing options could have ascertained the project’s viability. Nevertheless, the new
sugar factory became a reality, Singh stated.
Given Guyana’s discoveries in oil and gas, spending through the accelerator
principle will spur development within the other economic sectors. Boehm (2019)
postulated that governments could increase spending to boost their economy, often
through infrastructure development, thereby increasing their aggregate demand
depending on the multiplier. The Guyana government has since embarked on reforms to
diversify the economy through oil windfalls into human development. According to the
22
IMF country report (2017), what is continuously missing in Guyana is the capacity for
sustainable project execution.
In support of the country’s capacity building, the World Bank (2018) approved a
US$35 million development policy credit for fiscal management support. Various
stakeholders have raised concerns and inquired about political interference issues in
every stage of Guyana's infrastructure projects' cycle. Shako (2016) suggested that such
an obstruction can affect critical decisions that impact the project's success.
Simultaneously, there are well-intended project execution units in Guyana, many of
which work best to adjoin the already established government bureaucracy.
Public Projects Investment and its Linkages to Other Sectors’ Development
Public sector investment constitutes a more comprehensive developmental
program for governments, including roads, highways, education, power plants, and water
supply (Donaldson, 2018. increasing expenditure spending is expected to boost their
economy, often through infrastructure development (Boehm (2019). Therefore,
infrastructure investment can be considered as a public policy tool that can result in
economic growth. Besides, the nature and linkages of the other sectors' interactions with
the governments' fiscal policies may also yield economic growth in developing countries.
Development planners have integrated backward and forward linkages to benefit from the
interactions (Dash, 2016).
In illustrating linkages in public sector investment, both forward and backward
linkages are of importance. A forward linkage encourages investments in subsequent
stages in other linked sectors. In contrast, the backward linkage occurs when the project
23
encourages investment by facilitating and enabling other projects to succeed (Das et al.,
2018). Infrastructure and its linkages are best in constructing roads, railways, water,
ports, communication, and power grids. However, Khan, Waris et al. (2019) found that a
country's public infrastructure investment can also open new opportunities in other
country sectors. Successful implementation of infrastructure projects' resources requires
synergies between public and private investments to ensure shared use of the
infrastructure and realize mutual benefits to businesses and, ultimately, citizens'
satisfaction.
Public capital for infrastructure has also impacted private investment in countries'
growth and development. According to Nguyen and Phong (2017), economists use the
Cobb-Douglas production function to represent a technological relationship between the
amounts of two or more inputs - physical capital (K) and labor (L) - and the outcomes
(Y) produced from those inputs. Nguyen and Phong (2017) found a variation of the
model by Robest (1956), who used the Solow model (another production function) to
analyze growth. The Solow model evaluates the product from three inputs (capital,
labor, and knowledge) over time. Further, the researchers explained the relationship
between inputs and the growth of a nation's productive capacity, which economists refer
to as the production function (Nguyen & Phong, 2017). As a prevailing view, public
investment strongly affects economic growth, reflected by aggregate supply and
demand. Public investment directly impacts aggregate demand as government
expenditure and aggregate supply as a production function (capital factor).
24
Today, government expenditures extend beyond the traditional view of supplying
goods and services with an integrating link that supports infrastructure projects
development and assists the other sectors' growth and development. Private investment
correlates with government spending and is directly related to the existing public
investment. Researchers found a positive correlation between public infrastructure and
private investment (Donaldson, 2018).
An expansion in public investment can increase private investment, allowing
firms to have broader access to markets due to construction in roads, ports, and railways
(Donaldson, 2018). Public sector investment projects with linkages to the other sectors in
the economy play a central role in production functions by providing the required capital
for development without private financing (UNCTAD, 2018). UNCTAD (2018) found
that infrastructure development with broader strategic objectives and socioeconomic
requirements effectively counter the bankability approach for project approval. Relative
to cost-benefit analysis, development strategies are not pursued solely on financial
viability but also on other socioeconomics criteria.
There is always the risk that expanding public sector investment may consume
available finances that otherwise would have gone to the private sector. According to
Deleidi et al. (2019), the correlative relationship of private financing investment
suggested that the private sector's credit availability declines because the government's
fiscal spending crowds out of private sector investment. Investments undertaken by
highly subsidized state economic programs are in many instances financed through
printing money and internal and external debt financing, resulting in deficit spending.
25
Governments may sometimes be forced into deficit spending because the needed
investment is costly. The high cost sometimes works as a disincentive to the private
sector - a non-profitable investment opportunity, leaving the government to invest. Public
investment plays many competing and offsetting roles in the private sector's investment
activities (Deleidi et al., 2019). The net result of public investment on private investment
can be expressed as both leakages and linkages. Private sector investment activities may
enhance future growth in real income and become much more sensitive to capital
provision. Deleidi et al. (2019) found that public infrastructure has an overall simulative
impact on private investment. The authors found that public sector investment policies
can have permanent real-effect that can enhance the economy's physical and financial
resources.
An essential consideration in selecting public projects is establishing an efficient
network that integrates the investments into compatible and existing infrastructure.
Doing this allows for business strategy linkages in both the public and private sectors,
according to Boehm (2019). For example, China led a more public-investment-driven
economy with state control and gained sustainable growth by strongly influencing the
private sector. China further designed public policies for citizens' benefit rather than
prioritizing the private sector (Ari & Koc, 2020). The country implemented new policies
in the 1990s that enabled foreign direct investment in the economy through free
enterprise and capitalist ideas within a socialist framework. In so doing, China
empowered the private sector by aligning them with public policy and supporting public
investment, resulting in
26
a solid direct causal relationship between the public and private sectors (Ari & Koc,
2020).
Public sector investment forms part of a country's broader developmental plan.
For example, roads that support farms to market for farmers' access have reduced the cost
for farmers and consumers. Similarly, the government invests in power grids that reduce
the average cost and increase scale advantages during production (Donaldson, 2018;
Khan, Memon, & Ahmad, 2019). There are limited "farm to market" access roads, with
no beneficial network effects for domestic farmers. Public investments in roads and
supporting infrastructure and incremental node's benefits may increase project outcomes.
Khan, Waris et al. (2019) found that the marginal benefit of investing in infrastructure in
developing countries is highest when it adds to an existing but not fully matured network.
Coordinating public investment programs is essential for adding incremental linkages in
an emerging network that can yield more benefits.
The government's public investment decisions should be held at a portfolio level
to account for those network effects, evaluating projects as part of a broader system
rather than one in isolation. Assessing the influence of public infrastructure expenditure
and its outcomes on linkage industries requires special consideration. Different cross-
country cultural factors may create additional reviews to deal with country-specific
effects. Interestingly, the most significant impact occurs in the faster-growing countries -
the "Asian tiger" economies. For example, the Singapore government initiated linked
companies similar to state-owned enterprises after their independence in 1965 to develop
the economy (Yahya, 2012). The intention was to create commercial entities in the
27
private sector because the private sector alone lacked entrepreneurial capacity and
venture capital. The creation of linked companies was strategic because they operated
solely as profit-driven (Yahya, 2012). The comparative advantages derived from the
public investment provided the link where the investment outcomes became the factor
input for those in commerce to gain economies of scale. Khan, Waris et al. (2019) found
that political factors often influence the selection of public sector investment projects.
Governments must consistently prioritize capital investment in new ventures with a
convenient, politically aligned strategy, even if the project has a weak economic
rationale.
An essential function of public sector investment is to provide services that meet
the citizens' needs efficiently and effectively. Hvidman and Andersen (2014) held that
achieving the goal to fully realize the end users’ satisfaction is significantly linked to
successful organizational performance. It would help governments establish a portfolio
of high-quality projects with clear metrics supporting their contribution to sectoral
linkages for social and economic growth. Mishra et al. (2019) found that the projects'
holistic management is improved by establishing a project management office (PMO).
The Chilean example best illustrates how the approach works. In Chile, all proposed
public sector investment projects go to the Ministry of Housing and Urban Planning and
the National Investment System. They use standardized procedures and metrics to
evaluate the soundness and benefits of the projects' linkages. Bielenberg et al. (2020)
found that project proposal rejection is approximately 25% to 35% in Chile. Based on
objective criteria, the Chilean illustration included direct and indirect economic impact
and social
28
aspects, the allocation of financing, and a combination of cost-benefit analysis and
national goals.
In Malaysia, the government implemented a government transformation program
under the new public management approach. This initiative was titled ‘one Malaysia,
people first, performance now.’ Under the program, the emphasis was on implementing
KPIs in seven priority areas to infuse private sector philosophy in the public sector by
measuring and improving government service deliverability (Hughes, 2012). Similarly,
Lubbe (2016) opined that PSIPs support the local economy by creating the public
infrastructure to achieve economic growth and development.
In specific instances, some public investment undertakings result from market
failure - where the private sector considers some investments to be too risky. They cannot
or are unwilling to engage in those projects, citing substantial financial costs and the lack
of profit from the investments. Guyana offers a comparative illustration concerning who
bears the cost for a significant investment with low returns. The absence of private capital
caused the government to undertake a massive public investment project to bridge the
digital divide under the information communication technology (ICT) Access and
eServices for the hinterland poor and remote communities project (Guyana Redd+
Investment Fund, 2017).
Public Sector Investment Program in Developing Countries
Stuckenbruck and Zomorrodian (1987) seminal study investigated project
management in developing countries. The researchers found that project management
practice requiring drastic modification tailored to localized cultures' adaption is essential
29
for developing countries. The researchers did not use empirical data but suggested that
plans associated with implementing projects in a developing country should consider; (a)
cultural factors, (b) economic, (c) political, and (d) the administrative system within
public sector agencies
While projects are implemented and managed locally, their applications are
practically in the strictest manner of widely international project management standards
(Waheed, 2016). Project professionals from associations such as the PMI and
multinational organizations that frequently partner with local project management
associations help bridge the organization’s project capacity knowledge gaps. The
management of infrastructure projects is a function of their location, purpose, objectives,
and stakeholders, which significantly impact performance. In their project, governments
with global participants will experience varying cultural differences and political systems
that attract high public and political interest (Hoxha & McMahan, 2019). Understanding
the appropriate practices of project management in developing countries, given their
cross-culture factors, will facilitate a better understanding of how best to manage those
projects successfully.
The flow of foreign capital into a country is often a function of developing
countries’ financial systems. Further, economic and financial considerations often
constrain infrastructure development. Economic development contributes to both the
quality and quantity of capital available in the financial markets. However, the ‘quality of
capital’ influences economic growth and development in an economy (Lubbe, 2016).
Although project finance is a complex mechanism, it is successful in weak financial
30
economies. Project financing helps eradicate infrastructure backlogs to improve
economic development. Lubbe (2016) concluded that policy changes should create an
enabling environment for conducive infrastructure development.
Contrary to the view that public-sector investment projects enjoy long-term
successes, several of those investments in the 1980s delivered poor short-term and long-
term results: Issues encountered were cost overruns, corruption, and reduced project
maintenance (Arezki et al., 2017). When examined, the challenges of the 1980s carried
the same thrust – the project management strategies employed were all biased towards
the principles of the North American standards of project management, research, and
experiences (Adeyemi & Idoko, 2008).
Interestingly, Adeyemi and Idoko's (2008) observation of the project
management's western-oriented techniques is not straightforward for anyone to quickly
learn and implement in developing countries. Developing countries with many cross-
cultural traits have found those tools and techniques problematic, which led to the
conclusion that a unique project management approach is needed to address country-
specific impediments to local implementation (Adeyemi & Idoko, 2008)
Calderón et al. (2015) asked two fundamental questions while conducting their
research. The questions were within the ambit of government-administered public
projects to determine project management practice relevance in developed countries.
First, is project management equally applicable to all nations? Second, when is it
appropriate, and what form of project management to recommend? Most of the
challenges associated with projects in developing countries remain intracultural in nature.
31
The frequently asked questions are those of a non-technical cultural approach to
improving project execution in developing countries, according to Akade (2017). The
design method accounted for the complex dynamics and multi-faceted activities in the
project managers’ experiences and possible improvements to their practice. The results
reveal a positive correlation between culture and project outcome and the relationship
between culture and behavior (Akade, 2017). In effect, those challenges that are
intracultural in nature remain burdened by misaligned strategies.
Adeyemi and Idoko (2008) asked the following questions in light of developing
countries' challenges with project management: (a) How do we define project and project
management? (b) What factors drive the conception of projects in developing countries?
(c) What barriers and impediments exist as hindrances to project management? (d) Why
local capacity development exists for project management? (e) Is there a suggested model
for local project management capacity and process? The answer may imply that project
management, techniques, and training in management strategies may be productive if
there is a realistic understanding of developing countries' complexities and uncertainties.
Volden’s and Andersen's (2018) study is the first step towards better. The researchers
identified a hierarchical system that explains the relationship between project owners
from three state levels - the cabinet, the sectoral ministries, and the executing government
agency. In addition, the study provided innovative ideas to understand the stage-gate
approach within a country’s public sector project management.
Public investment project execution in developing countries contributes
considerably to their citizens' improvement. According to Garemo et al. (2020), the world
32
spends approximately $2.5 trillion a year on infrastructure; $ 3.7 trillion is the yearly
estimate needed through to 2035 to keep pace with the world's projected GDP. The
investment in public infrastructure may experience a high socioeconomic rate of return
for developing countries. The McKinsey study found that $1 of infrastructure investment
can raise GDP by 20 cents in the long run (Bielenberg et al., 2020). In contrast, failed
projects usually carry a more far-reaching effect on developing countries, according to
Bielenberg et al. (2020). For example, Calderón et al. (2015) found that 10% of
investments resulted in only a 1% growth for developing countries. Such volatile
performances can affect the business strategies linked to the successful completion of
these public investment projects that rely on public investment success. Public sector
agencies must have the executive capacity and capability to deliver successful programs
under their purview and vital to national or sectoral development. According to Khan,
Waris et al. (2019), gains from public sector investments are fully realized when they
generate economic growth. However, the public policy process often challenges
competing interests in the already scarce resources needed to satisfy ever-increasing and
competing national needs.
While there are undoubtedly several issues, finding a balance between competing
interests may sometimes be elusive and delicate. Economic growth is a function of
taxation benefits in developing countries. The positive contribution gained from the
state's revenue through those public infrastructure projects enhances citizens' standard of
living (Chauvet & Ferry, 2020). Besides, many governments often find difficulties
selecting those projects that may yield substantial returns for citizens' enhanced
33
livelihood. Ramlee et al. (2016) found many other considerations beyond the concept of
cost, time, and scope. They observed/concluded that organizational management, quality
assurance, technology and tools, stakeholder satisfaction, safety, and the environment
significantly impacted public infrastructure projects' success.
While program management concerns with managing different but related
projects- program management cannot fulfill its mandate without fundamentally
overhauling, specifically addressing organizational structure and changes. The changes in
many successful cases came with developing a flexible conceptual project management
office (PMO) that brings together the project into a manageable portfolio. Determining
the strategies needed to identify challenges associated with project portfolio governance
to enhance growth and economic development was the subject of a study in Pakistan. In
that study, Khan, Memon, and Ahmad (2019) used a quantitative study to validate the
latent construct of project governance and measured the construct from three dimensions
across fifteen observed items using confirmatory factor analysis (CFA). The relative
importance index (RII) is Khan, Memon, and Ahmad's (2019) recommendation to
examine different relative occurrence practices. Khan, Waris et al. (2019) found that the
most practiced item in project governance was its portfolio alignment with organizational
objectives and strategies. The traditional form of public sector management is no longer
appropriate due to the associated staff competency gaps. Strategic planning for
sustainability needs organizational capabilities to perform project management tasks for
the achievement of organizational objectives. Such requires interaction among the project
teams, management, and employees from the different business units; and an
34
understanding of the roles of the various stakeholders and the organization's corporate
structure and culture (Khan, Memon, & Ahmad, 2019).
General Background Information on Guyana
On 26th May 1966, British Guiana became the Co-operative Republic of Guyana
by achieving independence and ending over three and a half centuries of European
colonization. British Guiana had comprised three separate colonies, Essequibo,
Demerara, and Berbice. In 1831, the British combined the three colonies (Essequibo,
Demerara, and Berbice) to form British Guiana. The country had internal self-
government at its independence, except over foreign affairs, which remained under
British control (Ishmael, 2005). Guyana, an Amerindian word meaning "land of many
waters," is bordered north by 430-kilometers of the Atlantic Ocean. Its neighboring
countries are Suriname (along the Corentyne River) to the east, Brazil to the
south/southwest, and Venezuela to the west.
The International Monetary Fund projected that Guyana’s economy would grow
at 19% per annum from 2019 to 2023. In their estimation, the export value is projected to
grow by 37% per year, imports by 14% over the corresponding period, and revenues to
increase by 15% per year. As a result, government oil revenues are projected to exceed
US$3 billion in 2028 in an economy with a current GDP of US$ 3.6 billion (World
Economic Outlook, 2018).
Like many other developing countries, Guyana faces real economic challenges,
e.g., poverty and inequality. Other challenges include critical infrastructure backlogs,
which are not limited to creating new infrastructure and upgrading, refurbishing, and
35
rehabilitating existing infrastructure. However, as previously indicated, Lubbe (2016)
found that the fiscal expenditure on infrastructure and construction generally increased
aggregate demand and ultimately increased GDP. Hence, infrastructure project
investment can be essential to a country’s growth and economic development.
Since its launch in 2016, the INFRALATAM website has become an essential
tool for deliberation on infrastructure investment in Latin America and the Caribbean.
INFRALATAM provides data that supports the analytical work and decision-making of
countries and governments in Latin America and the Caribbean region. Other regional
and global bodies, such as the World Bank and the International Monetary Fund, will use
the data provided (ECLAC, 2019). Infrastructure investment in Guyana has reportedly
averaged 3.4% of GDP between 2011 and 2015, below the Latin America and Caribbean
average of 3.7% (INFRALATAM, 2016). Government investment measurement of net
proceeds of non-financial assets as a percentage of GDP was below the 10-year average
of 8.5% but has since increased in 2015 and is projected to reach 13% of GDP in 2022
(INFRALATAM, 2016). Guyana’s initial test will translate the government’s newfound
income into economic transformation and development agents in the medium term.
Guyana’s economic growth improved significantly, based primarily on the construction
sector (ECLAC, 2019). Under the PSIP, a high spending rate occurred in 2018, spurring
other economic activities. The construction sector grew by 11.0% in 2018, mainly
because the government (traditionally) is the largest spender in the economy. The sector
performance is expected to rise in response to expanding the government’s PSIP
(ECLAC, 2019).
36
The infrastructure stock for public investment is inadequate to support public
service delivery and facilitate private sector growth. The country’s transportation
infrastructure (roads, airports, and seaports) requires substantial improvements to help the
private sector's growth linkages (World Bank, 2019). The energy sector also hinders the
other sectors’ development. According to the Bank's Doing Business Report, high energy
costs are significant obstacles to business operations, limiting the private sector's growth
(World Bank, 2019).
Public Sector Investment in Guyana
Guyana faces development challenges on several fronts, including the
government’s institutional capacity and weaknesses in infrastructure (World Bank,
2018). Several investment programs were weak in their linkages as the investments to
support national development priorities lacked strategic alignment to aid the country’s
development (ECLAC, 2019). Guyana’s public sector investment projects'
socioeconomic importance included facilities such as water and sewerage, health,
education, transportation (road, ferry, aviation, port), sea defenses, national security,
telecommunications, drainage, and irrigation. These social services amenities are
valuable and necessary to sustain economies and support the citizens' social service
activities (Lübbe, 2016).
Post-independence saw Guyana planning its strategy development, the 1972 -76
developmental plans. Since then, several strategy policies have ensued, the national
development strategy (NDS), the low carbon development strategy (LCDS), and the
green state development strategy as of 2020. The green state development strategy
37
represents the country's long-term vision. It provides a comprehensive development
policy that guides public investment to 2040. Unlike the previously developed strategies,
the green state strategy is broader in its outlook. It captured a more holistic view of
Guyana’s socioeconomic and environmental challenges, a perspective more in line with
the United Nations’ sustainable development goals (SDGs) (World Bank, 2018).
The green state development strategy is transformational for Guyana, and the
approach combines all the critical components of the previously composed strategies in
fostering sustained economic growth that is low-carbon and climate-resilient, which is
consistent with that of the LCDs. However, as promised in the new government's 2020
manifesto, it reinstituted an expanded low carbon development strategy (LCDS):
Broadened to include more comprehensive environmental services, water resources
management, climate resilience, biodiversity, renewable energy, and marine prosperity.
The expanded LCDS will also establish an international center of excellence for
biological diversity to encourage cutting-edge research and develop and export
educational services (News Room, 2021).
Researchers have argued that project owners need to develop and incorporate
resilient, socially, and environmentally sustainable infrastructure and adapts to climate
change (European Commission, 2018). Guyana’s green state development strategy
promoted social cohesion, good governance and carefully managed the country’s finite
natural resources following the green economy principles. According to Lübbe (2016),
the public and private project owners in developing countries should upgrade
infrastructure development and ensure sustainable and long-term economic growth.
38
Researchers studied public project governance. They found that government introduces
its project governance frameworks - consistent with the recommendations from the
project management literature and the cabinet’s overall requirements (Volden &
Andersen, 2018).
In principle, the Guyana government has a project cycle management division
(PCMD) within the Finance Ministry, responsible for coordinating all aspects of PSIPs.
However, in practice, the institutional weakness has precluded the unit's proper
functioning. Each government sector deals directly with external agencies to identify the
needs for specific projects (NDS, 1996). Although, implementing infrastructure projects
can enhance economic growth and brings significant benefits to local communities. The
overall macroeconomic impact, especially on the balance of payment and financing of
public-funded projects, is not adequately reviewed. The supporting information is often
not readily available (Lübbe, 2016). The duplication of donor partners' efforts has been
burdensome to many developing countries. Unfortunately, the foreign-funded projects
created macroeconomic consequences way beyond those countries' capacities (World
Bank, 2017). The issue of pressing financial repayment commitments was of concern for
Guyana. The lack of project analysis and forecasts of resource availabilities may
ultimately exacerbate the problematic shortages. The government must spend its
resources to reduce poverty and social inequalities (Lübbe, 2016). In addition to the
short-term benefits, public investment can increase aggregate demand as a fiscal measure
in the long term. Those benefits have highlighted the need for developing countries to
39
invest in infrastructure projects that can improve the economy irrespective of its
developmental stage (Gurara et al., 2018).
Infrastructure development brings positive social change from two distinctive
approaches - economic infrastructure and social infrastructure. Economic infrastructure
generates income earned from the infrastructure via the end-users, according to Sillah
(2018). Guyana Water Incorporation. (GWI) is an excellent example because citizens, as
water consumers, pay for the water produced by GWI. The infrastructure from that social
service benefits the public in the form of a public good. Sillah (2018) also found that the
government pays for the social infrastructure's construction and operations. Police
stations, schools, hospitals, roads, and sea defenses are examples of social infrastructure
where beneficiaries do not pay directly to provide those services. Those huge investments
come under growing public scrutiny as the state is under pressure to deliver such services
efficiently. Lübbe (2016) opined that social incentives in developing countries boost the
economy of human capital.
The relationship between infrastructure development and growth and
development in an economy is the benefit obtained that surpasses the capital costs
associated with building the infrastructure, according to Lübbe (2016). The state
planning secretariat, a finance ministry unit responsible for overlooking infrastructure
projects' economic importance and underscored the direct contribution of infrastructure
development to Guyana's growth and development (World Bank, 2018). Besides, the
governments also invest in infrastructure maintenance and will need to upgrade those
40
deteriorating infrastructures to meet economic and social objectives. Lübbe (2016) found
that economic growth has a positive correlation with the citizens' social wellbeing.
Project Goals, Ethics and Communication Management
Project management aims to plan and manage each component of the project life
cycle to complete the listed goals and deliverables. The project management lifecycle
includes initiating, planning, executing, and project closure. The process also involves
identifying and managing risks, careful resource management, smart budgeting, and clear
communication across multiple teams and stakeholders. According to the Project
Management Institute, organizations that underestimate project management practice
reported an average of 50% more of their projects failing outright (PMI, 2018).
The changing business environments have forced organizational leadership
changes, rendering inefficient those “armchair managers” who only design and
communicate strategy, leaving project execution to others. The complexity
accompanying globalization has rendered armchair management obsolete. The failed
policies created frustration and the feeling that strategic directives were ignored.
However, crowdsourcing and outsourcing, which are tenants of globalization, have
caused project practitioners to tailor project management methodologies (PMI, 2017a).
A PMI study found that a lack of clear goals was the most common reason for
project failure in 2017. PMI recommends that organizations home on their priorities and
adequately define their project objectives (PMI, 2017a). These models should reflect the
organization's position, goals, and priorities as much as possible to achieve this goal.
Studies have proposed a multi-objective model for selecting the project portfolio that
41
maximizes efficiency and quality while minimizing the risks involved in project
execution (Zaim et al., 2019).
Public-funded projects have distinctive characteristics, namely, regulatory and
accountability. Those characteristics have improved public-funded projects' quality and
effectiveness; they have also created different challenges for the existing competence
models (Meirelles et al., 2019). The public sector modernization is a solution for
achieving a social purpose that drives improved performance, transparency, and
eliminating corruption while improving public services' value (PricewaterhouseCoopers,
2017). With taxpayers frequently demanding cuts in what they perceive as wasteful
spending, significant public sector investments now have greater public scrutiny.
Unfortunately, as the literature shows, and even in government statistics, many of these
initiatives fail or at least undergo substantial difficulties and problems - often
spectacularly and amid public criticism and ridicule (PricewaterhouseCoopers, 2017).
To achieve project success, the project manager must anticipate the difficulties of
avoiding project delays. Those problems may be resolved by competencies in knowledge
management to facilitate complex issues, according to Bakhshi et al. (2016). Typically,
no two projects are the same. In one sitting, the solution (often a concern for project
management methodology) is rarely successful for another situation. Although public-
funded project teams strive to achieve project goals, there are still several competence
gaps in elementary project management practices, according to Meirelles et al. (2019).
Another concept that captures this idea is project governance and portfolio
management in uncertainties. Project governance is a multi-level phenomenon that
42
encompasses the control of the parent organization, contractors, suppliers, and the project
combining the relationship among them in achieving the objectives (Turner and Müller,
2017). Müller et al. (2016) illustrated how project governance could affect project
participants' synergies and how the adopted mechanisms can heavily influence
stakeholder engagement and trust in the project. Both theorists have underscored the
established relevance that exists between government and stakeholders. Project
governance represents a new approach to the development of project management -
strategic project management. Project governance aligns with the organization's strategic
goals during project implementation by establishing and achieving optimal results in
fulfilling each project and optimized effects at the organization level (Geyer et al., 2017).
Identifying and managing projects from a selected portfolio with complexity
involves many factors and considerations, starting from the proposal stage until the
project portfolio is finally selected. Organizations should pay particular attention to
knowledge utilization to improve organizational performance (Zaim et al., 2019). Given
the portfolio's project selection, the organization must prioritize those projects that align
with objectives. Since projects and portfolio management include processes to collect,
identify, classify, evaluate, select, prioritize, balance, and authorize as measuring success.
Assessments and management tools help project managers identify the tools to enable the
success factors (PMI, 2017a).
According to De Vasconcelos Gomes et al. (2019), project and portfolio managers
can evaluate success by identifying or creating a research instrument (questionnaire) to
gauge the processes' success. Management tools are available to collect, identify, classify,
43
assess, and prioritize data. While the project management field has continued to build its
procedures, it still maintains its philosophical stance. Much of the mathematical modeling
has advanced its trajectory, creating ever more complex solutions to more complex
models. De Vasconcelos Gomes et al. (2019) stated that there should be a more
systematic and empirical approach to managing uncertainties in project portfolio
management. Generally, project management begins with a well-defined problem; after
that, it becomes vital to grasp the issues associated with offering solutions during the
growing phase. Since selecting a suitable project is significant, it is necessary to
appreciate mathematical models to lead the organization towards its final goal (Wysocki,
2019).
Traditional project management starts with the assumption that each proposed
project aligns with the organization's strategic goals and contributes to the organization's
positive results (Cristóbal et al., 2018). Some projects entirely support the organization's
strategic goals, while some only support some parts, and some generally do not support
the organization's strategy. When the project outcomes are not aligned to the
organization’s goals, the organization will fail to tie its projects to its business strategy
and portfolio (Volden & Samset, 2017). Such occurrences are evident when managers do
not accurately understand the strategy because there are not communicated (Erceg &
Gulam, 2018). The importance of establishing a secure connection between clearly set
strategies will aid in the correctly chosen projects, strengthening and maintaining the
relationship during project implementation, according to Volden and Samset (2017).
44
Objectives, project culture, and organizational leadership positively affect project
management performance and help establish a precise reference for leadership qualities.
Project managers use the maturity of organization project management, culture, and
organizational leadership to help organizations determine a roadmap to a higher maturity
level, according to Khan, Waris et al. (2019). The PMI’s (2017a) study found that project
management efficiency and effectiveness are critical to successful project management,
whether the maturity assessment involves (a) project management risk maturity, (b)
organizational project management maturity, (c) project management office maturity, or
(d) a simplified project management maturity, all of the assessments help project
managers to evaluate the level of best practices to employed in managing projects.
While public infrastructure projects may be challenging, managers with
knowledge and competencies in the requisite skill set are essential to managing the
process. PMBOK’s support to project managers in accomplishing project objectives
aligns the projects with the organization’s strategic plans (PMI, 2017a). They assumed
that project managers could identify trends and generalizations that arise throughout the
project (Wang et al., 2018). Public infrastructure projects have interwoven interest groups
with government policies, regulatory bodies, investors' goals, and general expectations.
Their success is defined by conflicting ideas coming from the various stakeholders
involved.
A smart city project study done by Sandulli et al. (2017) discussed the selection
process for the right public partner by considering three attributes - complementarity,
commitment, and compatibility as a selection criterion and their importance for public
45
projects' success. Levin and Wyzalek (2015) described how project managers must
manage stakeholders to deliver organizational value in uncertain times. The process
involves a five-step - "stakeholder circle," applied in the project portfolio management in
situations of uncertainty: (a) to identify all the stakeholders, (b) then rank them by
prioritizing their relevance, (c) developing an understanding for all the stakeholders, (d)
engaging them through effective communications, and (e) monitoring the engagement's
effect. Every project should involve some form of stakeholder engagement, which assists
in stakeholder identification, stakeholder influence, and stakeholder impact, according to
Patanakul et al. (2016). The primary stakeholder engagement goal is to fully support the
various project stakeholders while managing the stakeholders’ agenda. The agenda is
driven primarily by political, social, or financial gain (Müller et al., 2016).
Project Management Leadership
Daniel and Ugochuku (2020) defined leadership as the improvement of personnel
and equipment. The leadership roles include developing quality standards, ensuring
substantial delivery, and creating pride in staff's artistry. Daniel and Ugochuku found
leadership characteristics such as being influential, persistent, and engaging. Therefore,
project managers must possess such qualities and managerial skills for business
effectiveness and project results. Dubrin (2016) describes leadership as inspiring support
and confidence among the people needed to achieve organizational goals. The
involvement speaks to the use of the four I’s: intentions (objectives of the project),
influence (people, organization, society), impact (the outcome of the project), and
integrity (fair dealings in the project), ideals that leaders should model. While there is no
46
magical method for effective management, some required skill sets would aid the
process. Skills that contribute to developing a continuous learning process that facilitates
management with best practices, according to Sabrokro et al. (2018). Positive results are
the outcomes from effective management skills, and the opposite is true for ineffective
management.
Project managers must have the ability to make decisions, emphasizing that there
is no single model for project management leadership. Project managers should adopt
characteristics from different leadership styles, according to Daniel and Ugochuku
(2020). In contrast, organizations may experience challenges due to the uncertainty from
the fast-changing environment - the effects of globalization aid the increasingly complex
project activities. Adaptation may be challenging, but a shift in leadership style may help.
The lack of employees' adaptability to the process will adversely impact the project
(Abdelouahab & Bouchra, 2020). The project lifecycle can serve as the basic structure
for the management of projects. The different project leadership styles are available in
their application at various stages of the project life cycle (Pretorius et al., 2018).
The traditional leadership of vertical relations (top-down management) was
practiced for several decades and the leadership field's first practice. Shared and balanced
leadership have gained prominence from the project management literature. It
highlighted the differences between ‘leadership’ and ‘management’ that explain the
current leadership literature trends (Pretorius et al., 2018). The expectation is that leaders
must provide guidance and define the goals to their followers. Howell (2018) opined that
leaders are the ones to introduce directional changes for the organization’s success,
47
enhanced by competitiveness to achieve the goals and objectives. From the onset, the
leadership position should promote a consistent and fully integrated business unit that
results in the organization's teams' aptitude to self-manage. Doing so requires team
orientation, which bonds members to each other and the project’s mission. Good
leadership is an essentials skill for active management in decision making, staff
motivation, and a lead by example method that determines organizational behavior
(Northouse, 2016).
From establishing a thriving project environment, two leadership functions can
emerge - performance management and team development. The project manager's
leadership style can be guided towards directive and task-orientation without neglecting
subordinates' relationships because it can be crucial for project success (Zhao et al.,
2016). Iyer and Banerjee (2016) conducted a case study of India's infrastructure projects
to determine if managerial efficiency was the key driver for completing projects. The
researchers used 630 infrastructure projects between 2009 and 2013, with an average of
USD 25 million per project. Projects were either classified as mechanical or civil. They
evaluated the managerial efficiency using various descriptive statistics from the data
source - interviewees, reviewed project documents, weekly reports, and job site visits.
Additional data came from senior officials of each project to determine their level of
satisfaction. Iyer and Banerjee (2016) concluded that benchmarking managerial
efficiency in large-scale projects could improve efficiency. The success can be measured
by including targeted dates in the project schedule and using external groups instead of
peer reviews to determine the success.
48
Hoxha and McMahan (2019) found that the project success rate might improve
leadership qualities and referenced two studies that supported their contention. First,
Buengeler et al. (2016) surveyed 113 German customer service organizations and 121
leaders and found that age impacted leadership effectiveness, owing to experience. Amin
and Kamal (2016) provided an exciting observation from older team members' extensive
practice and work experience; they were more influential in leadership. Their
membership in the team provided a commitment to the projects that is important for
knowledge sharing (social capital).
Factors such as leadership, corporate processes, and culture can influence project
success. However, the findings are neither tangible nor concrete to benefit project
managers (Horning, 2018). The conflicting decisions give credence to the notion that
environmental and situational factors influence project management effectiveness (Teller
et al., 2014). All of which lends credence to the contingency theory, which suggested no
single “best fit” in the style of leadership practice. The leader's effectiveness is a function
of the prevailing circumstances resulting in two factors, leadership style and situational
favorableness - later referred to as situational control (Saunders et al., 2015).
Managing projects has complications, especially when the moving parts cannot be
quickly grasped; it becomes difficult to understand and navigate such complex
environments. Cristóbal et al. (2018) provided a general overview of project management
amid project complexities and argued that the traditional project management tools and
techniques were wholly inadequate when managing such projects’ time, cost, and
resources. For achieving project success, Levin and Wyzalek (2015) found a relationship
49
between project management methodology (PMM) and its impact on project governance
relationships. The new complex and dynamic environments now require a new public
administration approach for its management. Public project managers must rethink the
traditional approach to projects - the new public administration's dispensation requires a
willingness to change leadership style. The input-outcome cycle explains how the
organization counteracts entropy, assuring its survival by offering an integrative and
potentially systemic approach. The conventional organization theories exaggerate internal
functioning while failing to understand the adaptation process, according to Ackermann
and Alexander (2016).
Under the new model public administration program, the emphasis is on KPIs,
with an infused private sector philosophy that supports effective public sector
government deliverability. The new public management (NPM) is a significant
development in public administration, with varied political and technical objectives. The
model shifted public organizations away from the old rule-bound Weberian style to a
scalable public sector. The NPM reform narrative includes management empowerment
and active performance measurement, which draws its intellectual impulse from the
public choice theory and agency theory (Ferlie, 2017). The public sector functions to
satisfy the citizens' needs rather than theirs. The social goals should balance the
economic ones.
Importance of Project Management
PMI defines project management as “ the application of knowledge, skills, tools,
and techniques to project activities to meet the project requirements.” (PMI, 2017a). The
50
primary project management lifecycle covers initiation, planning, execution, and closure.
Project management aims to plan and manage each phase of the project’s lifecycle to
achieve the identified goals and deliverables. It involves identifying and managing risks,
careful resource management, smart budgeting, and clear communication across multiple
teams and stakeholders. Jacobs and Chase (2017) found that process integration increases
the enterprise's efficiency and ability to compete in its agility, cost, and service
capabilities. The integration process is primarily for a collaborative involvement of the
enterprise systems with resources improving performance and quick reaction to demands
(Kim & Chai, 2016).
Failed projects can quickly derail and delay initiatives and even prevent business
growth because unclear focus can lead to scope creep, missed deadlines, and
overspending. In recent years, Elton (2018) reported a dramatic rise in scope creep due to
stakeholder expectations and shorter delivery schedules. For example, in 2017, 52% of
projects completed reported scope creep at some point during the project’s completion.
The figures represent a notable jump of 9% from 2012, which recorded a 43% scope
creep (PMI, 2017a). The strategy that organizations expect to follow can be very
different from the strategy that gets realized. Regular project success appears to be
challenging because of volatility, uncertainty, complexity, and ambiguity (VUCA) (Pace,
2019).
The primary goal of stakeholder engagement is to fully support the various project
stakeholders while mitigating the stakeholders’ agenda, which is primarily driven by
political, social, or financial gain (Müller et al., 2016). Different stakeholders are
accountable for varying project perspectives with a vested interest in aligning their
51
objectives to form a uniform approach for delivering solutions to the end-users. Without
a unified approach from each stakeholder to achieve project goals, the organization may
risk misalignment between organizational and project objectives. Erkul et al. (2019)
highlighted stakeholders' engagement within the project's strategic intents with public
needs and expectations. What becomes pronounced is an effectual effort in implementing
an eventual project management methodology. Emphasizing organizations that utilized a
standardized project management methodology, the PMI study found that only 26% of
the participating organizations use a method throughout the organization's project
management practice (PMI, 2019).
Having an interactive approach to project management can help to mitigate
project risk. Project risk management is a practice that manages current and potential
challenges emanating from the project stakeholders' relationships. The risk factors
include ethics, supplier (monopoly behavior), methodologies, and techniques that may
affect the project's goals and objectives, factors influenced by project complexity.
Crispim et al. (2019) conduct a two-phase study to identify project risk management
(PRM) knowledge level and project managers' current practices. They investigated the
connection between critical attributes of organizational PRM maturity, risk-related
methods, and project performance, with complexity as a moderating factor. In the first
phase, they interviewed five project managers. They generated data through a
questionnaire distributed globally to various project managers in the second phase.
Crispim et al. (2019) found that PRM maturity and project complexity influence the
practices employed by project managers.
52
Further, PRM maturity also changes the usage of risk practices moderated by
project complexity. The more complex the problem, the more risk mitigation measures
are needed by project management practice. Crispim et al. (2019) provide insight into
PRM maturity and PRM practices; the authors used moderating factors to improve
project performance. The maturity of PRM reflects the level of development of formal
methods and processes. Researchers examined the factors that have impacted enterprise
risk management and recommended a framework for identifying and describing
enterprise risk management (Mishra et al., 2019). Resources included all assets,
capabilities, organizational processes, firm attributes, and information knowledge that
allow the organization to implement strategies that improve efficiency and effectiveness.
External resources should be integrated into the firm's resource base, internal resources,
personnel, facilities, processes and customers, suppliers, and other critical outside
entities, like government entities, control bodies, and geography (Mishra et al., 2019).
Those factors offer organizations opportunities they may have failed to recognize because
of inefficient risk management strategies.
Further, with the responsibility of aligning projects and programs to business
strategy, the enterprise project management office (EPMO) establishes and oversees the
projects and programs' appropriate management governance. The EPMO is responsible
for mitigating the issues of risk amid complexity. The considerations and advice help
when choosing the project management (PM) maturity modeling, as the model structure
can influence the assessment’s focus, according to Backlund et al. (2015). Further, the
53
growing complexity and uncertainty of the project managers will require them to predict
and repeat their project management methodology.
According to Cristóbal et al. (2018), tailoring the established project management
methodology to a specific project and organizational characteristics will allow the
organization to standardize the tools, techniques, processes, and procedures used to
manage the organization’s project. Samiei and Habibi (2019) explain how project culture
and organizational leadership can affect project management performance by establishing
a precise reference as a basis for enterprise resource planning. Project management
professionals will improve their project management approach's efficacy. It explains how
a tailored project management methodology functions and how well the method is
understood and implemented (Joslin & Müller, 2015). Organizational challenges exist not
only in the selection and tailoring of a methodology but also in the manner of deployment
(PMI, 2018)
Crispim et al. (2019) conducted a quantitative cluster analysis and identified six
patterns in project risk management (PRM), risk identification, risk evaluation, planned
actions against risks, risk monitoring, communication, and managing support tasks. The
researchers found that the six patterns are helpful for organizations to determine the
project maturity model and its overall success effectively. Organizations that have
completed over 80% of their projects (within time and budget), and had met their
business intent (outcomes), are those that have benefited highly from realization maturity
(PMI, 2017a). The levels range from none or minimal best practice utilization to the
highest standard of best practices utilization with continuous improvement. The higher
54
the level of maturity, the more effective project management becomes. Despite the
benefits of maturity modeling, only 7% of the organizations surveyed in 2017 had such a
practice (PMI, 2017a).
Project Management Processes
The concept of project management success and project success is utterly
different in the relationship. Measuring the distinction between the two concepts explains
that project management success delivers the project’s scope and budget within the time
constraint (Joslin & Müller, 2016). In contrast, project success involves realizing the
project goals and objectives after project fulfillment (Hoxha, 2017). From the literature
research and practice, three prevailing streams for project success were evident. The first
was the dominant stream - a prescriptive list of critical success factors, failure factors, or
risk factors that should be considered to ensure a positive project outcome (Joslin &
Müller, 2016). While the risk assessment is subjected to (a) opportunism, (b) bounded
rationality, and (c) subjectivity, the project manager’s involvement in planning from the
onset has the best potential to improve risk assessment (Firmenich, 2017). The research
stream's value identifies essential preconditions and drivers of project success; however,
it offers no explicit definition.
The second stream identifies other contingency variables that might impact
project outcomes or require specific management intervention to mitigate potential
adverse effects. Firmenich (2017) found that each project is unique. Risk should be
estimated using individual assessments, including project size, project type, life cycle
stage, project management complexity, and strategic versus operational mindsets. The
55
three streams relationship explains how the first two streams achieve project success. The
third stream is concerned with the measures against which success can be judged. Joslin
and Müller (2016) opined that the established criterion from project practice provides an
immediate fulfillment of a project, measured against its design parameters. The
parameters include schedule (time), budget (cost), scope, and quality. The literature sees
this as a measurement for project management success. Gaddis (1959) determined a
project to be an organization unit devoted to attaining a goal-generally the successful
fulfillment of a product on time, within budget, and in conformity with deliberate review
blueprints.
The best-delivered projects are those with the best-applied methodology coupled
with experience and knowledgeable project managers. Managers use key performance
indicators and earned value management tools to monitor the project contingencies
during the project’s life cycle (Eshghi et al., 2019). Implementing the project
management process is an endeavor that requires commitment for strategy alignment
from the top of the organization. Project management has operational tools and
techniques that allow for planning and controlling project delivery. Joslin and Müller
(2015) found that 22.3% of project success results from applying the relevant PMM
elements throughout the project life cycle. Wali and Othman (2019) observed that project
management tools' relevance has increased in construction project management because
of the number of interacting elements in the environment. As management tools aid the
critical path method, it helps support project managers in planning, scheduling tasks, and
completing activities. Gantt charts are projections phased as activities in the project's
56
work breakdown structure. Wali and Othman (2019) considered the complex
environment and found that tools and their impact on managing public sector projects
provide a better assessment for project success. The tools also involve mathematical
modeling techniques to optimize projects' duration at the level of the project’s scope,
time, and cost factors (Joslin & Müller, 2016). Another seemingly popular method to
measure success is the balanced scorecard, a framework to measure performance from a
financial and non-financial standpoint and provides a balanced view of the internal
business processes, financial, learning, and customer satisfaction and growth (Singh &
Sethi, 2017). When an organization's project management method is misaligned, that
project has a high probability of poor quality from the inefficient operation.
Each project has five phases. Together, they represent the path a project takes
from beginning to the end, generally referred to as the project’s life cycle: initiating,
planning, executing, controlling, and closing. Each project phase uses procedures, tools,
and techniques for constant monitoring and reporting (Joslin & Müller, 2016). In the five
stages of the project management life cycle, each phase will create the work breakdown
structure of every activity and milestone. The KPI analysis procedure compares each sub-
activity or work breakdown structure (WBS) achievements with a projected outcome
(Wysocki, 2019). The use of unsuitable factors will lead organizations to mismanaged
projects. The distinction between methodology elements and success factors becomes
critical because the WBS methodology will identify a comprehensive and detailed WBS
as the success factor measured by five functional elements: processes, tools, techniques,
capability profiles, and knowledge areas (Joslin & Müller, 2015).
57
The traditional project management has a three-dimensional life cycle approach
that provides cost, quality, and design, optimized by the project manager. Large
infrastructure projects manifest high complexity, unlike contemporary project
management, such as task, structural and directional, technical, and organizational
complexity. Floricel et al. (2016) found a direct correlation between project complexity
and project completion time. From a canonical analysis, the researchers found that
complexity will reduce completion performance and increases innovation performance.
Although the issues of risk and time are impacted by complex projects characterized by
uncertainty, some large-scale and long-term projects experienced some delay in cost
overruns (Safaei, 2020). Qazi et al. (2016) found that project completion time and cost
can be affected by uncertainty issues, and the sophistication is a function of the project
size, creating cost overruns.
Researchers found six elements of uncertainty that may affect both new and
maintenance projects; the most common of the six are complexity, environment,
capability, and information (Saunder et al., 2016). Project managers must exercise
knowledge about the elements and how to manage project risks and uncertainties
effectively. A helpful way is for managers to plan ahead of time and ensure the projects
start early enough to identify and resolve all impediments as soon as possible (Qazi et
al., 2016). The project's units can make continuous adjustments to their plans to reduce
the problems (Khan, Waris, et al., 2019). Complexity affects the modeling, evaluation,
and control of projects and the objectives concerning time, cost, quality, and safety
(Floricel et al., 2016). They also identified specific knowledge management strategies
that project
58
planners can use to address any complexity-concerning uncertainties (Floricel et al.,
2016). For Arbabi et al. (2020), knowledge management (KM) is regarded as an
essential factor in project-based organizations (PBOs), leading to organizational learning
across projects. Most PBOs have recently inserted project management offices (PMOs)
into their hierarchical charts to manage their projects coherently.
Rivera and Kashiwagi (2016) observed that project management is the mechanism
for delivering professional services; managers are responsible for managing, directing,
and controlling those projects. No one design method cures all challenges, as
contingencies are inevitable. Managing risk in project portfolios requires adopting a
broader outlook than the unique/individual project risk. A strong relationship between
strict supervision of the dangers at each project level and the integration of risk statistics
at the portfolio level allows both to enjoy a positive correlation with the overall project
portfolio success (Teller et al., 2014). Risk management in projects requires
understanding risk evidence, which is critical during high turbulence and portfolio
dynamics. The significance is that the researchers provided functional clarifications for
project risk management to reduce the likelihood of project failure (Teller et al., 2014).
Government agencies that initiate project management methodology (PMM)
control budgets plan activities and ensure stringent quality. The contingency theory offers
project management insights into how best to adapt a project management approach
within a given environment and aids in fulfilling and satisfactory project management
practice (Joslin & Müller, 2015). Project culture and organizational leadership positively
59
affect project management performance and help establish a precise reference as a basis
for leadership qualities.
The maturity of corporate project management, culture, and organizational
leadership allow project organizations to determine a roadmap to a higher maturity level
(Khan, Waris, et al., 2019). Organizations that move up the project management maturity
levels may have better chances of concluding their project successfully than those that do
not move in the same direction (PMI, 2017a). Climbing the project management maturity
levels improves project success rates in complex environmental projects. The degree of
the projects' complexity determines the “ideal” level of maturity (Christoph & Spang,
2014). Climbing the project management maturity ladder may contribute to positive
social change by improving the projects' environment.
The project portfolio manager's role revolves around the two most fundamental
competencies (a) the portfolio strategy mapping – the management of portfolios through
portfolio value, customer, process excellence, and future orientation capabilities (Levin
& Wyzalek, 2015). The second competency involves working with different algorithms
and financial models. The analytical ability and numerical intelligence are the balanced
scorecard outcome, the tool to align projects to the organization’s strategic objectives
(Levin & Wyzalek, 2015). For example, some organizations struggle with finding the
right mix of products to shape the relative investment based on their preferred risk
profile. Tools help solve those problems by enabling the organization to derive the
desired allocation mix based on existing portfolio analysis.
60
Business Management Strategies in Project Management
Project management is different from the general management of business
because of its mission-oriented objective. There are terminated upon mission
accomplishment and described as the art of directing and coordinating human and
material resources throughout a project's life by using modern management techniques
to achieve predetermined objectives of scope, cost, time, quality, and participation
satisfaction (PMI, 2018). The general management of the business and organizations
assumes a broader outlook with more excellent continuity of operations. Given the
underlying similarities between project and business management, adapting modern
management techniques in either realm is now the challenge (Dyer et al., 2016).
Organizations today seek to “do more with less,” they now integrate IT systems to
eliminate redundancy while improving efficiency. Integration tools are different from
integration strategies because the foundation of an effective integration strategy is to
standardize operations. If not given the various divisional components, the organization
will find itself awash with duplicated functionality (Jacobs & Chase, 2017). Modern
management practices and unique knowledge domains have absorbed many techniques
and tools identified only for business management practice. For example, computer-based
information systems and decision support systems are now standard tools for general
management. Computer-based systems and subsystems are intended to help decision-
makers use communications technologies, data, documents, knowledge, and models to
complete decision-making tasks (Ölçer & Akyol, 2014).
61
The internet of things (IoT) is essentially a global network of devices that can
communicate with one another and end-users through the internet. The IoT intersects
with project management on team collaboration to data collection, presenting challenges
at several levels (Sanchez, 2018). PPM practitioners slowly implement emerging
technologies like artificial intelligence (AI) or virtual reality (VR). The lack of urgency is
directly associated with the lack of digital-friendly solutions offered by PPM technology
providers. Still, the expectation is that the newer generation of PPM end-users will begin
applying pressure based on today’s PPM tools' limitations. The following changes in the
external project environment, the power structures, capabilities, skills, and standard
practices may eventually cause many traditional project portfolio management practices
to become obsolete. Poorly implemented changes may result in strategy misalignment
within the project life cycle (Zolfaghari et al., 2017).
Project management specific to construction encompasses objectives by
implementing a series of operations subject to resource constraints. Many operations
research techniques, such as linear programming and network analysis, are now popularly
used in the general knowledge application domains. They help resolve challenges and
potential conflicts between the project's stated goals concerning scope, cost, time, quality,
the limitations imposed on human material, and financial resources (Lübbe, 2016).
Conflict resolution should be at the project's onset by making the necessary
tradeoffs or creating new alternatives (Wysocki, 2019). Business management
emphasizes management's systematic study by distinguishing management functions in
an organization, measuring each detail. A principal tenet in analyzing management along
62
functional lines explains how all new management activities are practiced. The manager's
role is to coordinate a process of interrelated functions, which are not arbitrary nor rigidly
calculated but becomes dynamic as the process unfolds. Understanding the changing
dynamics of organizational structure will create the directional path for construction
project management and better preparation (Uddin & Lynn, 2016).
Another tenet is that management principles are derived from an intellectual
analysis of management functions. Even leaders with higher emotional intelligence
quotients were more productive and experienced a higher project success rate (Maqbool
et al., 2017). Creating smaller operative components for managers' jobs allows for
organized management functions to improve operational efficiency. The primary
management functions are performed by all managers, regardless of enterprise, activity,
or hierarchical levels. The development of a management philosophy helps the manager
establish relationships between human and material resources. The outcome follows an
established philosophy of operation that helps managers win the subordinates' support in
achieving organizational objectives (Melé, 2016). Project managers should be aware of
their organization's strategic position and the other organizations involved in the project.
The project manager faces the difficult task of aligning various organizations' goals and
strategies to accomplish project goals.
Project Success Factors
The iron triangle’s cost, time, and scope concepts are still considered fundamental
objective measurement tools for project success. Despite not being the only contributory
factor, the triangle only accounts for 60% of project success, according to Serrador and
63
Turner (2015). Project success is a multidimensional construct that includes short-term
project management success (efficiency) and long-term goals (effectiveness). The
regarded distinction between the concept of project management success and project
success is distinctly significant. While project management success refers to delivering
the project's scope on time and within the budget, project success means accomplishing
the project’s objectives after the project conclusion (Hoxha, 2017). Project success is
understood as achieving targets and objectives as planned but measured when the project
is closed.
The project success literature centered around three fields, to identify project
objectives' attainment (Waheed, 2016); evaluation of projects in terms of cost, time, and
quality (Khan, Memon, & Ahmad, 2019); and strategic alignment projects to
organizational objectives (Joslin & Müller, 2016). While researchers often use project
success and project management success interchangeably, there are different, even
though there are found to be interconnected (Radujkovic & Sjekavica, 2017). A logical
deduction implies that project management generally involves controlling cost, time, and
progress to assess project success criteria.
A project might still be successful because, for stakeholders, the process of
finishing the project within time, scope, and budget, is critical, but other considerations
can also be helpful. The end-users experience might be most effective, especially with
infrastructure projects, as the benefit obtained can surpass the capital costs associated
with building the infrastructure (Lübbe, 2016). In contrast, a project can be defined as an
enterprise's activity to benefit the long-term (Radujkovic & Sjekavica, 2017).
64
Several factors can influence project success, many outside the project manager’s
control (Akade, (2017). As such, the sole responsibility for project success should not
necessarily rest ultimately on the project manager alone. Wysocki (2018) opined that
projects are subject to changing conditions, creating difficulties in scoping the project,
even from the onset. The mechanistic management system offers a better perception of
project requirements through the work breakdown structure (WBS), according to
Wysocki (2019). Waheed (2016) contended that the perspective for recognition in project
management practice comes from the regulatory body, the PMI, a guide to the project
management body of knowledge (PMBOK). The purpose is to help project managers
achieve project objectives and align projects with the organization’s strategic plan. The
PMBOK assumption is that project managers can identify patterns and generalizations
throughout the project (Wang et al., 2018).
Notwithstanding PMI's contributions and authoritative influence, project
sustainability is not well addressed in the popular texts containing the best practices for
project management. Such observation raises the need for a more holistic and coherent
view of projects in terms of the degree of fitness, given the operating environment of
those projects and the general society they operate (Armenia et al., 2019). The
researchers identified five dimensions as the principal research domains. They
considered critical factors for integrating a sustainable approach for project management
practices (Armenia et al., 2019). There are as follows, (a) corporate policies and
practices, (b) resource management, (c) life cycle orientation, (d) stakeholders’
engagement, and (e) organizational learning. The researchers found positive trends
towards integrated project
65
management processes using sustainable management in the project’s process life cycle.
Sustainability influenced all of the standard practices of project management knowledge
concerning time, cost, quality, and project risk (Armenia et al., 2019).
Joslin and Müller (2016) examined the link between project management
methodology (PMM), project success, and its impact on project governance
relationships. Joslin and Müller's (2016) sampling method provided a balance among the
continents, and they targeted professionals who work in professional organizations
worldwide. The sampled approach resulted in better responses because they were more
interested in their profession than their employers. This sampling approach also has its
limitation; PMI professionals' limited respondents' choice to only members of
professional project management bodies, creating a bias. Nevertheless, the researchers
found that PMM was initiated by government agencies, in an effort at controlling
budgets, for the planning of activities, and to ensure stringent quality. Joslin and Müller
(2016) found that methodologies should evolve to provide the best application within the
project environment, using new tools and planning techniques, including ICT.
Best Practices in Project Management
Patanakul et al. (2016) found six essential characteristics as critical success
factors for governmental projects to succeed. They achieve specific and attainable
outcomes, effective product design, stakeholder engagement, integrated project schedule,
legislative alignment, and project standards. Being excellent at managing projects is
usually a matter of grasping project management best practices. The “best practices” are
generally obtained from project management methodologies, international standards,
66
industry standards from conventions, and the organizations’ guidelines from past project
lessons learned. Research tells us that skilled, trained, and experienced project managers
increase the likelihood of project success, meeting original goals, and delivering on
business intent (PMI, 2018). Often, these “best practices” may vary from organization to
organization. Some, however, are applicable across organizations and can fundamentally
enhance project performance.
Researchers have adopted a practice-based approach to study project and project
portfolio management and encourage researchers to follow this call (Clegg et al., 2018).
Practice-based research has three views: Phenomenon, perspective, and philosophy. The
phenomenon view encompasses what happens as opposed to what to expect. The
perspective view includes a unique way of observing the participant. The philosophy
view provides for the misconception of social reality’s perception of observing the
participant (Clegg et al., 2018). The phenomenon practice is used by seasoned and skilled
project practitioners to combat project complexity challenges. They demonstrated the
alignment of project processes with a business management strategy using tools,
techniques, and procedures for successful alignment (Floricel et al., 2016).
A best practice is to maximize human resources to gain efficiency by creating a
“product team” - experts trained in specific repetitive tasks. Leaders need to select and
communicate the strategy to make the most efficient use of the resources (Samáková et
al., 2018). The product team should not be affiliated with any particular project or
organization. Instead, they would move from project to project, performing just the target
task for product management. In another project, best practice involves a risk
67
management response team. Four options are available, mitigation, acceptance, transfer,
or do nothing. The team should comprise experienced members with wide-ranging access
to plan, monitor, and control the project's risks by thinking of worst-case scenarios and
develop contingency plans (Crispim et al., 2019).
Leadership capabilities are significant when dealing with sophisticated resources -
as in an agency setting. While a schedule cannot continually develop creative work to
realize 100% perfection every time, leadership traits, motivation, and empathy can create
teams' talent for efficiency (Northouse, 2019). Portfolio management allows
organizations to make the most efficient use of resources to understand their investments'
benefits. It helps ensure credibility and increased accountability to stakeholders and
enhances the ability to make timely and strategic changes. Amongst the more popular
form of project management methodologies in practice is agile; however, the waterfall,
hybrid, critical path method, and critical chain project management are also considered.
The agile methodology is the most utilized in short development cycles focusing on
continuous improvement in developing a product or service (Loiro et al., 2019). The
benefit from constant improvement requires a narrow focus on one primary goal
achievement, and to stay on schedule while keeping costs low is now practice with the
use of technology (Berggren, 2019). The process of aligning project and program
activities with ICT strategy helps with being agile, whose application is primarily within
the software development industry (Loiro et al., 2019). Today, the process has become
useful across most industries; being agile is more comfortable to manage change when
obstacles arise.
68
A common factor in failed projects is a lack of collective understanding of
stakeholders' requirements. Both the project team and client have differing views of the
project's scope. The identified characteristics of stakeholder engagement and project
complexity are similar to the concept of governance of project portfolio management that
deals with multiple programs involving a multi-project environment (Levin, & Wyzalek,
2015). Stakeholders' involvement is critical; the project can easily slip into a pattern of
reduced communication when dealing with the client, especially when perceived as
"happy." However, unless the meetings are not regular, one cannot know the client’s
satisfaction. The dominant driver of projects meeting their original goals is an actively
engaged sponsor (PMI, 2018). From the project manager's perspective, frequent
stakeholder engagement gives the feeling of open communication and that their best
interests are served (Loiro et al., 2019). To process is formalized with regular client status
meetings - at least weekly, it will keep everyone engaged and on the same page. The
project momentum will stay steady, and success is more likely (PMI, 2018).
Organizations can focus heavily on their project managers' technical
competencies (e.g., relying on formal PM knowledge and certifications). Although
skilled, trained, and experienced project managers increase the likelihood of project
success, meet original goals, and deliver on business intent (PMI, 2018). In effect, the
"softer" side of project management - leadership, empathy, people skills will suffer.
Given how heavily project managers interface with clients and internal stakeholders, they
strain their leadership competencies beside their technical ones. The most successful
change management approaches reflect leaders' experiences who apply a deeper
69
understanding of people and systems supported with an organization’s culture,
comparable to the McKinsey 7-S Model (Morgan, 2015).
The project management office develops and implements a process that ensures
everything works as planned to succeed with project portfolio management. The
alignment needs to be within the formulated strategic implementation in large projects,
including the project managers and executive management (Erceg & Gukam, 2018).
Those large projects have project management offices or enterprise project management
offices which can (a) identify all existing and potential projects, (b) determine how each
project will impact organization-wide strategy, (c) prioritize each project, (d) allocate
resources, and (e) adjust project strategy as required. The realization of the
organization’s objectives allows for the programs and projects to be further arranged
under a portfolio strategy undertaken by the project management office (PMO). PMOs
are used to improve the communication and interactions between the organization and
customers (PMI, 2018). Besides, PMO may consolidate projects with similarities for
operational planning, allowing for alignment with business strategy (Dyer et al., 2016).
Portfolio management is a way to operationalize strategy by aligning project policies and
procedures with the organization's goals.
Alignment of Project Management with Organizational Strategies
According to Zolfaghari et al. (2017), alignment is an effort that supports
organizational success; it involves the collective alliance of strategies from three levels,
corporate, business, and functional, to maximize outcomes. In general, alignment is the
effort to agree on the main goal by directing all parts and functions of an organization
70
towards the same objectives. Understanding business strategy at all levels of an
organization becomes a significant task of an effective project management process in
alignment (Erceg & Gukam, 2018). When the alignment is substantial, both the
organization and project team's effectiveness will increase. Still, when the alignment is
weak, the challenge is misalignment when the teams cannot focus on the main goal and
objectives (PMI, 2016). The researcher found that organizational strategies represent
approximately 37% of the common factor associated with project failure (PMI, 2017a).
The contention is that successful organizations are those organizations that achieve
proper alignment between these elements. Their mission should translate into the
business and the strategic plan to include workers, departments, strategies, and business
processes.
The critical issue in the process-driven strategy alignment model is that the flow
from the inception point from the business process to the project management process is
linear. When the strategic objectives change due to changes in the project's internal and
external environment, misalignment from business to project strategy could occur.
Project effectiveness can be achieved by aligning project management priorities with
organizational strategy (Zolfaghari et al., 2017). The creation of alignment between
projects and organizational strategy starts from the project selection phase continuing
throughout the project lifecycle up to the project implementation. Zolfaghari et al. (2019)
categorized the efforts into three stages: allocation, cascading, and autonomy; the
researchers focused on the last stage. Zolfaghari et al. aligned the construct between
project strategy and business strategy had posed a limitation because they could only
71
assign three discrete states to the alignment (low, medium, and high). Zolfaghari et al.
suggested that further study can measure the alignment construct for more reliable
results. While Zolfaghari et al. (2019) established significant quantitative research
alignment, my qualitative approach differs. From the project selection phase and
throughout the project’s lifecycle, right through to the project completion stage.
The traditional literature on aligning project management with business strategy is
vague. Most studies linked the business strategy with project management through a
project selection process, seen as part of the alignment process (e.g., Baker, 1974). The
more common approach is project portfolio management (PPM), another concept
suggested in the literature to ensure project management and strategic alignment. Volden
and Samset (2017) presented their findings on public investment governance on
megaprojects and found a pathway to sustainable development for developing countries.
They found that most megaprojects were successful because project managers performed
quality assurance at the project's onset. Sustainability can manage the project life cycle to
positively impact cost, time, and project risk (Armenia et al., 2019).
Pinto and Winch (2016) discussed designing the projects' front-end to suit the
business environment. From the findings, the pointed conclusion is how dynamic project
portfolio management has grown. The progression has become a dynamic decision-
making process through which an organization can update and revise its active projects
list (Pinto & Winch, 2016). The organization’s choice of business strategy drives their
PPM’s method, the significant purposes of selecting and prioritizing projects. The study
by Berggren (2019) introduces another idea of innovation through the sequential learning
72
of project managers, who can deploy ambidextrous leadership skills in achieving project
innovation. The front-end project design was critical for managing the business
environment as an innovation measure in a challenging environment.
The organizational project management models discussed above are now well
mature in their applications. Nevertheless, the criticisms were ineffective as many firms
continued to face obstacles in improving their project management practices. An
alternative methodology was developed from the literature review, and the proposal's
arguments were analyzed. Mossalam and Arafa (2016) determined the awareness and
level of implementing project-level benefits management versus other organizational
governance practices across different organizations. Aubry et al. (2019) investigated
how benefits management evolved in organizations by considering project actors'
experience based on five large-scale organizations as they engage in the activity. Aubry
et al. (2019) provided valuable consideration for understanding the “good practice
approach” to benefit project management. They suggested a strong relationship between
projects and their benefits to be measured throughout the projects' execution.
Similarly, in a unique approach, researchers used a case study of an infrastructure
megaproject that concerns the construction management of a 50-year-old American
bridge. Eskerod et al. (2018) found that exploiting all project opportunities will increase
project benefits. Such a requirement involves all categories of stakeholders. While some
project-related opportunities may take a while before enjoying the related benefits,
celebrating the successes stimulates the project and creates opportunities to further
project benefits. Eskerod et al. (2018) contributed to the gap within the literature on the
73
phenomenon “project opportunity exploitation,” even though the case study was a “rare
species.”
The recognition of strategic importance in project management is rapidly
accelerating. A strong reason for the acceleration is that aligning project management
with business strategy can significantly enhance goal achievements (PMI, 2017). What is
now emerging is the project management office's role and the enterprise project
management office (EPMO), which offers a broader business-wide responsibility. The
EPMO and PMO benefits were highlighted in the survey, as 27% more projects were
completed successfully, and 42% fewer projects were without scope creep (PMI, 2017).
The strategic alignment concept stresses project management goals and implementation
plans with the business's goals and organizational strategic goals in a dynamic and
uncertain environment. Project managers with competencies in the knowledge and
process areas are critical to successfully managing a project (PMI, 2017).
The research field concerning the idea of strategic alignment in various fields of
management is growing. Zolfaghari et al. (2017) established alignment between the
project life cycle stages - allocation, cascading, and autonomy. Other researchers found a
correlative relationship between the organizational business and function (e.g., Erceg &
Gukam, 2018). Since project management is similar to these functional strategies, the
logical deduction is for project management alignment with the business strategy because
of the critical role in project success in organizations. Projects aligned to the
organization’s strategy are completed more often than the misaligned projects (PMI,
2016). Aggressive project sponsors also use their influence within an organization to
74
actively overcome challenges by communicating the project’s alignment to strategy,
removing the bottleneck, and driving organizational change. Project momentum will stay
steady with this consistent engagement and support, and success is more likely (PMI,
2018).
While many organizations, including governments, suffer from misaligned
projects, the lack of a systematic approach to align project management with the business
strategy is evident. The empirical literature that offers advice on how to achieve
alignment is scanty. The planning strategy points should represent the changes in an
organization’s long-term direction. Researchers found that less than 50% of the studied
organizations have enterprise project management offices (EPMO). However, only 44%
of those EPMOs have aligned organizational strategies (PMI, 2016). While projects are
viewed as building blocks for organizational strategy, they are not recognized
functionally. However, they are rather perceived as a business process, achieving a
project management /business strategy alignment even more complicated, according to
Wang et al. (2018).
Wang et al. (2018) stated that the PMBOK’s purpose is to help project managers
achieve their project objectives by aligning them with the organization’s strategic plans.
PMBOK assumes that project managers can identify patterns and generalizations that
occur throughout the project. The literature suggested that PMO professionals hold
significant knowledge to ensure alignment and focus on achieving their vision, similar to
the EPMO. While PMO’s original purpose was to manage programs and project
specified deliverables, they did not necessarily have a secure link with the high-level
business
75
objectives. Their effectiveness is increasingly measured by mapping a direct line back to
the overall business performance's success (PMI, 2018). A centralized function should be
operable at the strategic level with the executives.
Organizations are now using the project stage-gates approach to adapt and
maintain the alignment during the project's execution phase (Volden & Andersen, 2018).
The mediating process level provides strategic feedback resulting from environmental
changes, leading to an “emergent strategy” (Mintzberg, 1994). The strategy was never
envisaged in the plans but rather emerged from a stream of managerial decisions over
time. Volden and Andersen’s (2018) approach is the first step toward a better
understanding of public project governance as a hierarchical system and the relationship
between project owners on three levels, the cabinet, the sectoral ministry, and the
government agency- project execution unit (PEU). Considering the varying government
roles becomes quite helpful in understanding the stage-gate within a country’s public
sector project management. Volden and Andersen (2018) studied public project
governance in various ministries and agencies in Norway. Following the introduction of
a structure that seeks support at the highest government level, the cabinet approves the
most significant projects. The study methodology was designed to assess the project
governance frameworks and applied to state-funded investment projects in selected
sectors. The researchers found that all agencies introduced their project governance
frameworks, consistent with the project management literature recommendations and the
cabinet’s overall requirements. By contrast, only one ministry has taken a formalized role
76
as the project owner. After the cabinet's no-objections, governance tasks get delegated to
the subordinate agencies (Volden & Andersen, 2018).
Project, Programs, and Portfolio Management
Project portfolio management (PPM) illustrates how best to accomplish those
interrelations and dependencies that connect projects. PPM offers a pictorial view of all
grouped projects -past, present, and future, and provides an analysis that optimizes the
prioritization and sequencing of projects to maximize the organization’s return rate
(Armenia et al., 2019). Portfolios of programs, projects, and operations, when created,
are used to achieve strategic goals and objectives. Project portfolio managers require
different skills to project managers. According to Levin and Wyzalek (2015), project
portfolio practice revolves around two crucial competencies. They allow for strategy
mapping when managing portfolios through portfolio value, customer, process
excellence, and future orientation capabilities.
Projects and programs within a portfolio generate value in an organization's
production capability, and when completed, the projects become operational (Berzisa &
Rasnacis, 2017). An organization can then translate its vision and mission into a strategic
plan with strategic goals and objectives. The organizations’ departments also have their
strategic plan that supports the organization’s initiatives. These initiatives are grouped
into portfolios and create portfolios of programs, projects, and operations executed over a
pre-determined period (Zolfaghari et al., 2017). A portfolio will link projects and
programs to the organization’s strategic plan. Some organizations struggle with finding
the appropriate mix of products for their investment based on the risk profile. Moreover,
77
tools are available to help solve the problems and enable the organization to derive the
desired allocation mix based on existing portfolio analysis (Zolfaghari et al., 2017).
Berzisa and Rasnacis (2017) presented a new source that successfully
implemented a tailored agile PMM based on a project's specific elements and the
organization. The method included people, training, customers, team size, team
capability, team motivation, company culture, planning, and scheduling. The process
included the best practices from change management, methodology adaptation, and
execution while using sociometric and motivation research methods that analyzed the
project team's role in implementing the PMM. The researchers presented a case study
where the procedure was employed and analyzed in a real-world scenario. The
researchers found that the team experienced greater cohesion, improved risk
management, and increased communications due to the implemented agile PMM.
Within programs and portfolios, projects are a means of achieving organizational
strategy and objectives. In turn, projects will have deliverables with control accounts,
including work packages with work activities throughout the project (work breakdown
structure). Their assumed risk groups them; for example, at the level of the executive, the
risk responsibilities range from (a) the steering committee-level presentations, (b) the
portfolio management milestone plans, (c) resource allocation, and (d) accepting
responsibility for deliverables and timeline engagements. Levin and Wyzalek's (2015)
model helps organizations view strategy in an integrated and systematic way. Generally,
portfolio managers usually develop management standards to guide the portfolio and
keep a high-level overview of everything. The projects with their deliverables
(outcomes)
78
provide the day-to-day goals and execute the strategic objectives. Projects are undertaken
to accomplish an organization’s strategic plan's business objectives, albeit directly or
indirectly. The PMBOK guide also regards projects as an authorized activity derived
from multiple sets of strategic considerations (Project Management Institute, 2017b).
Ng (2018) reviewed several widely used project management frameworks and
selected three (PMBOK, PRINCE2, and ITIL). The objectives of the review were
twofold. First, it allows for a quick understanding of the widely used project management
frameworks. Second, it considered varying frameworks for complementary applications,
each at different phases of a project life cycle to address the specific needs. The
researcher provided an example of how the methodologies could be combined and further
tailored to determine similarities, differences, and gaps within each method. Using a real-
life case study of an organization with 2,000 employees, the researcher described
organizational PMM that comprises stages and varying management involvement levels.
Once the business case is justified, the project team then moves to the acquisition and
development phase of the PMM, leveraging PMI’s PMBOK processes and techniques.
As the project moves to operations and support, the PMM will include the ITIL
components to build a management plan. The components provide specific configuration
and asset management, incident management, and change management. Ng (2018)
concludes that one methodology rarely sufficed because of each project's uniqueness, the
comparative analysis, the real-life case study, and the feedback obtained from project
management practitioners. Instead, the researcher opined that tailoring and combining
relevant elements of the traditional PMMs be reworked to improve project success.
79
Besides, adding the most up-to-date tools, technologies, skills, and knowledge areas to
leverage in increasingly complex project environments.
Projects can enjoy successful completion in numerous ways. However, to think of
the most successful project management methodologies, methods, and frameworks
requires an open mind because there are always changes. A relationship between project
management methodology (PMM) results in project success and impacts project
governance relationships (Levin & Wyzalek, 2015). New concepts appear all the time,
and an entire sequence of methods, tools, and techniques lies behind each successful
project. Bakhshi et al. (2016) found that the project benefits can map to the strategic
objectives, especially for complex problems, as competencies in the knowledge facilitate
complex issue resolutions. Investigations have determined the awareness and level of
project-level benefits management versus other organizational governance practices
across different organizations (Mossalam & Arafa, 2016). The researchers proposed roles
for the project manager to realize benefits management. To add confidence, a real-life
scenario of implementation for challenges illustrated a successful implementation
benefited from the realization concept (Mossalam & Arafa, 2016). The benefits
realization management process is compatible with the process groups of PMBOK. They
enable the organization to cascade the responsibilities of delivering values at the project
manager level (Project Management Institute, 2017b).
As a practice tool for implementation, benefits measures play an active role in
monitoring the potential project benefits. Mossalam and Arafa (2016) showed a
superficial implementation level of benefits management practices at the project level
80
compared to benefits at higher levels (programs & portfolios) and among other
organizational practices and systems (quality management, excellence, risks,
performance, among others). In the current methods, 40% of surveyed organizations
possess benefits management practices versus 70% of the organization for project
management practices, which indicated the relatively low performance of benefits
management (PMI, 2017). The findings help enlarge the project manager's
responsibilities to realize benefits, suggesting a mechanism for managing these benefits
through benefits register, benefits realization plan, measures, KPIs, and closure.
Therefore, a portfolio manager needs to be less focused on individual projects and more
on the big picture approach: Identify opportunities for success by mitigating risks to
achieve the objectives.
Summary and Transition
Section 1 discussed the study's background, the problem statement, the purpose of
the study, the research question, and the study's conceptual framework. I also presented
the study's nature, defined terms, assumptions, limitations, delimitations, and the study's
significance. The literature review discussed the strategic management concepts
concerning public sector project managers and the factors that align project outcomes
with government strategies to maximize project success. Section 2 includes the purpose
statement, the researcher's role, participants, research method and design, population and
sampling, ethical research, data collection technique, data organization techniques, data
analysis, and reliability and validity. In section 3, I presented the findings, application to
81
professional practice, implications for social change, recommendations for action and
future research, reflections, and a conclusion.
82
Section 2: The Project
In this section, I reiterate the research's purpose statement, present the researcher's
role in the qualitative study, and identify the participants. Further, I explain the
methodology and the research design and define the population and the sampling size. In
addition to offering the highlights for ethical research consideration, I explain the data
collection method. Finally, I present the study's technique to ensure the research's
reliability and validity.
Purpose Statement
The purpose of this qualitative multiple case study was to explore effective
strategies that public sector project managers used to align the project outcomes with
government strategies that maximized project performance. The specific population
group comprised public sector investment project managers who successfully aligned the
project outcomes with government strategies and worked for four project-based units
within the geographic administrative region of Demerara/ Mahaica (Region 4), Guyana.
They participated in semistructured interviews that provided their perspectives and
experiences in project management, which formed the source of the data collection. A
project is determined aligned if 80% of its expected outcomes are aligned with the
organizational strategy (PMI, 2017). The examined project reports verified successful
alignment from three constructs; (a) identification of the set goals from the baseline
studies and how they were captured within the project goals on a percentage basis; (b)
exploration of each of the alignment factors of cost, time, and budget; and (c)
examination of the end user's satisfaction from stated goals of both the project and
83
organization, all from a compliance rate of at least 80%. The study may contribute to
positive social change if public sector project managers can use the study findings to
create a community of successful project practitioners to implement projects better.
Role of the Researcher
Unlike quantitative research, in which the participants function autonomously,
and the researcher’s role is distant from the studied population, qualitative research
necessitates that the researcher determines accuracy and trustworthiness while serving as
the primary data collection instrument (Alpi & Evans, 2019). The process entails a
researcher’s thorough understanding of the research phenomenon to aid a meaningful
research inquiry while making a conscious effort not to influence the participants
(Marshall & Rossman, 2014). The researcher’s role is to understand social
constructivism's principles. The intention was to create a collaborative nature of learning
by linking the literature with the interviewees' self-discovery from the collected data —a
belief that social processes are sustainable and that people construct knowledge in their
daily social interactions (Merriam & Tisdell, 2015).
Researchers should be objective in their approach because subjectivity negatively
affects the quality of the research. For example, Karagiozis (2018) stipulated that
researchers should avoid forced opinions or thrusting their views on the participants’
answers. Such meddling could invalidate the study. Researchers should actively listen to
the participants and build trust and rapport while demonstrating empathy (Kenno et al.,
2017). Researchers have a social responsibility to conduct the study ethically, preserve
the research, fully comply with the code of ethics and avert biases (Karagiozis, 2018).
84
As the researcher, I follow the protocols of the Belmont Report (National
Commission for the Protection of Human Subjects of Biomedical and Behavioral
Research, 1979). The report presented three fundamentally ethical principles, autonomy,
beneficence, and justice (Miracle, 2016). Autonomy explains “the respect of person” as
the first moral principle that speaks to an individual's fundamental right to choose
whether to participate (Yin, 2018). Autonomy allows for a detailed comprehension of the
requested engagement and reasonable judgments about making a noncoerced decision
(Roth et al., 2018). Regarding the individuals' natural ability to do what they choose—
the respect of person—Yin (2018) found in human research that not every individual can
intentionally apply independence and control. Diligence and due care must be practiced
to ensure no influence, coercion, or exogenous influences are placed on the participants
in their responses (Glenna et al., 2019).
Researchers should not find themselves in any conflicting situations; in fact, they
must show due diligence in mitigating personal bias in data collection and verification
(Karagiozis, 2018). A generalized idea in qualitative research is to ascertain a
relationship between (a) the research question, (b) the observed data, and (c) the
conclusions (Green & Salkind, 2017). Therefore, the researcher should try to mitigate
bias as much as possible. Such efforts will ensure that the study overcomes design
scrutiny with a repeatable method that produces the same results using different samples
(Walden University, 2019).
I used interview protocols, member checking and review, data saturation, and
triangulation, in addition to the carefully constructed interview questions. I ensured that
85
the analyzed data was primarily inductive, allotting meaning developed from the data
rather than the more hypothetical-deductive quantitative research approach. Researchers
create an interactive dialogue with the participants to enhance the perspective and derive
more into a social context (Merriam & Tisdell, 2015). Each participant’s uniqueness was
maintained to ensure each participant realized an independent and unique case study that
allowed for case comparison (see Yin, 2018). In qualitative research, researchers should
build sufficient trust with participants so that their data set can describe strictly authentic
and rich meanings, experiences, and perceptions (Anderson, 2017).
An interactive dialogue helps develop an intensive response and add a more
insightful approach to the social context (Merriam & Tisdell, 2015). Furthermore, given
the uniqueness of the participants, a sustainable method was required to ensure each
participant represented an independent and unique case that provided the opportunity for
case comparison, following Yin (2018). Finally, I conducted diligent and careful
verification of interview questions and data analysis methods to ensure comprehensive
data collection and analysis. The interview protocols, member checking and review, data
saturation, and triangulation ensured that the data analysis was primarily inductive,
allowing meaning to develop from the data.
Participants
Sanjari et al. (2014) opined that the participants must best fit the qualitative
researcher's criterion under investigation. The selected participants for this study were
project practitioners who experienced the phenomena and articulated their knowledge in
successful project outcomes alignment. My role was to select those appropriate
86
participants who had the expertise and competence to answer the interview questions and
ensure access to those participants (see Saunders et al., 2016). I interviewed the
participants with the requisite competence to answer the overreaching research question.
To gain admittance to participants, I first identified those organizations whose
affiliation to public sector investment projects were known to have a pool of experienced
project practitioners. According to Yin (2018), the participants can come from ministries,
agencies, and at the local government levels in such circumstances. Given the nature of
the study, I found the participating pool to be public officials. Participants with positions
of power in those organizations are often the gatekeepers of valuable information and a
potential source of rich data for researchers (Adhabi & Anozie, 2017). Therefore, I
contacted the agencies' principles to gain approval and an agreement for cooperation.
This process promised access to the project leaders in the agencies with the sought-after
information and permission to interview them. I had anticipated challenges with
accessing participants, and I sought a high level of engagement with the organization’s
leadership. In the process, I had expected some leaders to exercise elite behavior under
their positions of authority—politicians, heads of agencies, chief executives’ officers,
permanent secretaries, and senior civil servants—making this group challenging to
access.
Often elites are more inaccessible and surrounded by gatekeepers, and I managed
to gain access because I exercised much patience, planned carefully, and allotted plenty
of time for the process, as suggested by Mikecz (2012). The strategy for gaining access
to these government officials had involved developing a rapport for a working
relationship
87
with the participants (see Prior, 2019). I was thoroughly prepared to anticipate a
challenge on my research topic, its relevance, and other questions. Sometimes elites will
inadvertently or deliberately avoid answering a problem, especially if they are media
savvy. An excellent strategy I applied was the proper interview techniques that allowed
for elite personality control. It allowed for a better assessment with qualitative
interviews and greater credibility. It kept the respondent from telling partial or
imaginative narratives (Harvey, 2011).
An acceptable interviewee response is a sign of relaxation, indicating that the
respondent may open up networking opportunities. Prior (2018) concluded that
developing a good rapport provides networking opportunities before attempting
complicated or awkward questions. The rapport consists of a healthy process of giving
and receiving information between participant and researcher, noting that the researcher
can connect with participants to share their experiences. The aim is to demonstrate a
skilled researcher's attributes by asking the right questions while staying adaptive, being a
good listener, having a firm grasp on the issues under consideration, and conducting the
research ethically (Yin, 2018). I endeavored to such a practice.
Obtaining the appropriate participants for interview-based research is a critical
element of successful research (Kenno et al., 2017). To ensure my conduct was of the
highest ethical standard for the study, I provided the participant with a comprehensive
overview of the research. Each received an informed consent form that invited them to
confirm their participation. Whether or not a participant wishes to partake in the research,
informed consent is a process to communicate honestly and thoroughly about the
88
investigation (Simon et al., 2018). The consent form featured the following details: the
eligibility criteria, the purpose of the study, the data collection procedures, the voluntary
nature of the study, the risks and benefits of participating in the survey, compensation for
taking part in the study, measures to protect the privacy of the participants and the
confidentiality of the collected dataset, a declaration on conflicts of interest, and contact
details for further information. All help cultivate a rapport with participants in qualitative
interviews and enhance the researcher’s access to the interviewees’ stories, according to
Prior (2018).
The data was collected after receiving approval from Walden University’s
institutional review board (IRB; approval number 07-08-21-0984939). Gaining the IRB
approval expedited the primary data collection process because the IRB protects
participants' welfare and ensures the research's ethical conduct (Henry et al., 2016). In
addition, the IRB approval assures the prospective participants of the study's
appropriateness in its design. Participation in this study involved minimal personal risks
while offering benefits to stakeholders.
The purposive sampling method explained how the four eligible organizations'
participant was identified. Each was chosen from a different organization with success in
managing a public infrastructure/construction project. The purposive sampling technique
is appropriate for case studies. Purposive sampling follows a unique line of questioning;
for example, do participants share the researcher's phenomenon of interest? (Englander,
2016; Patton, 2015). Purposive sampling requires examining the population's specific
characteristics - an investigation of participants based on their judgment. Researchers
89
then handpick participants based on their knowledge and experience (Kandola et al.,
2014).
For my study, because my population comes from state agencies, I used two
approaches. First, peruse the project documents to identify which projects satisfy the
selection criterion, with an 80% compliance rate. The verification of successful alignment
met from three constructs, (a) identification of the set goals from the baseline studies and
how they were captured within the project goals on a percentage basis; (b) exploration of
each of the alignment factors of cost, time, and budget; and (c) examination of the end
user's satisfaction from stated goals of both the project and organization. Second, the first
criteria' fulfillment easily allowed for identifying successful managers. The request was
made to the agency's executive for a list of those practitioners to form the sample.
Researchers who use snowball sampling allow one or more participants to identify other
participants (Saunders et al., 2016).
Qualitative researchers select a sample of participants who generally provide rich
information about a phenomenon that positively affects others' lives (Rossetto, 2014).
The eligibility criteria for selection as a participant were projects managers who
successfully aligned project outcomes with government’s strategies and those who
satisfy the requirements of (a) serving as the project manager, (b) serving as the program
or portfolio manager, (c) serving as a functional manager, and (d) work in a public
infrastructure unit for a minimum of 5 years. In addition, I interviewed those who agreed
to participate voluntarily, from which I achieved data saturation.
90
Considering the COVID-19 circumstances, researchers may conduct electronic
interviews in real-time using computer-aided technologies via the internet (Saunders et
al., 2016). Skype and Zoom are easily accessible and are of free service. The researcher
interacted audiovisually and held live conversations via the internet, which provided
convenience across time and space in any physically remote location. Skype and Zoom
are convenient and safe alternatives because the interviewer and the respondent can
interact at their choice (Archibald et al., 2019). I conducted the interviews via Skype and
Zoom, convenient to the participants in line with the interview protocol.
Research Method and Design
Three methodologies are available in scholarly research. Researchers use them to
investigate problems and determine the method's appropriateness and design suitable for
any research, qualitative, quantitative, and mixed methods (Queiros et al., 2017). This
section will include a discussion on the research method and research design.
Research Method
In qualitative research, the participants for consideration must best fit the
criterion under investigation (Sanjari et al., 2014). For example, selecting those
participants who have experienced the phenomena can articulate their experiences and
knowledge. The researcher’s role was to select those appropriate participants who have
the expertise and competence to answer the interview questions and ensure they gain
access to the substantive details (Saunders et al., 2016). The participants in the study
have the competence to provide answers to the overreaching research question.
91
The strategy used to gain admittance to participants requires identifying the
organizations affiliated with public sector investment projects and having a pool of
experienced and successful project practitioners. In such circumstances, the participants
can come from agencies and state and local levels of government, according to Yin
(2018). Given my study's nature, I interviewed public officials whose participants are of
power positions within the organizations. They are often the gatekeepers of valuable
information, a potential source of rich data for researchers (Adhabi & Anozie, 2017). I
anticipated challenges with accessing some participants; those in a privileged position-
usually professionals or elected politicians concerning a particular activity or area of
policies- often directly influence their domain. With such expectation, a certain level of
professionalism is anticipated in their work-related interactions, including the researcher.
The central argument for preparedness remains that no matter how sound is the
methodology concerning elite interviews, the success still depends on the researcher’s
ability to undertake them effectively.
The strategy for gaining access to government officials involves developing a
rapport for a working relationship with the participants, according to Prior (2018). Trust
is also crucial to the process, especially when some questions might be controversial or
ask participants to think critically about their organization or activity. Building trust and
rapport can take time; therefore, building a collegial position early in the interview is
necessary. I did not open up any controversial questions that might unsettle the
participants, resulting in the interview termination. Instead, I started by asking the
participants to outline their background and experience in government projects briefly. It
92
allowed the participants to speak broadly on “their terms” while getting used to the
interview situation and my presence. Then, I provided the participant with a
comprehensive overview of the study. I selected the qualitative method because of my
interest in business strategy alignment for project management fulfillment.
Qualitative research offers four robust methods, (a) ethnography, (b) focus
groups, (c) phenomenology, and (d) case study, explained in their best application.
Researchers use ethnography to observed phenomenon solely from the participant’s
perspective, through the submersion in the participant’s environment (Queiros et al.,
2017). Immersion was not my aim, and neither was understanding cultural phenomena
from the participant’s perspective. Therefore, ethnography did not meet the research
requirements. Focus groups can be a valuable source of knowledge but problematic for
novice researchers who can find the participating group challenging to motivate and
manage (Queiros et al., 2017). Given the complexities of group dynamics and being a
novice researcher, focus groups were not a suitable design option.
Phenomenological researchers are concerned with individual research
participants' lived experiences versus abstract knowledge or reflection (Berglund, 2015).
Researchers use the phenomenological perspective to study individuals’ perceptions and
give meaningful human experiences concerning the events (Neubauer et al., 2019). I did
not aim to explore what appears in consciousness or pursue ordinary insights into human
experiences; therefore, phenomenology did not meet the requirements. Researchers use
the case study to understand the intricate complexity and peculiarities of a distinct case
investigation of an organization considered worthy of analysis (Park & Park, 2016). A
93
case study helps understand a complex issue or object involving an up-close, in-depth,
and detailed investigation of a study subject and its contextual position. It can extend
experience or add strength to the existing knowledge through previous research. The case
study was my choice to explore in-depth activities of the phenomenon from a process that
project practitioners successfully used within a specific system or context for projects and
government strategy alignment.
Research Design
Case studies are ideal for understanding organizational and business processes.
Because the procedures vary across institutional contexts, such an inquiry would require
specific approaches. While the research design links the data to the research question,
qualitative research could improve value through rigorous from a well-structured
research design. The research context or boundary is well defined by the researcher,
according to Van den Berg Struwig (2017). Case study research approach could either be
a single case study or a multiple case study. Researchers have applied a single case study
to explore and understand a phenomenon using a unique or extreme interest case; the
research question should guide the design (Morse, 2015). The researcher's choice of
study involves using the multiple case study because of its appropriateness in exploring
the contemporary phenomenon in a real-life setting, as Yin (2018) stated. Further, Yin
observed the usefulness where the boundaries between the event and context setting are
not established and are unknown.
The multiple-case design is skewed to provide replication logic; each case could
produce similar or different data and perhaps predictable findings. Researchers use
94
multiple case studies to explore and understand the similarities or dissimilarities of the
phenomenon in various places (Gaikwad, 2017). The multiple case study is more robust
and helps better understand the phenomenon under investigation than a single case study
(VanWynsberghe & Khan, 2007). According to Yin (2018), the appropriateness of the
multiple case methodology captures the associated perspectives concerning business
strategy alignment for project management.
My interest in exploring government strategy alignment with project outcomes to
maximize public project success was best applied using multiple cases. Multiple cases
offer the best accessible potential for triangulation and a thorough understanding of the
complexities that may arise both in projects and government strategies. Besides, the
multiple case study design is appropriate to ascertain whether the first case findings
occurred in the other cases and, thus, the need to compare outcomes for all the situations.
For example, in research with similar characteristics, justification using multiple
qualitative case studies to explore factors that led to misalignment between project
management and the business strategy in the telecommunication industry in Saudi Arabia
(Alsudiri et al., 2013). Similarly, I explored those helpful strategies for project
management alignment of outcomes with government strategies for an improved public
investment project climate in Guyana, all within the contingency theory conceptual
frameworks.
Qualitative researchers are concerned with understanding an issue versus
representative numbers that indicate statistical significance. Queiros et al. (2017) found
that some questions are better answered with numbers, while others are easier with
95
words. In the considered case for my study, remarks and comments will help me
understand the study phenomenon. I relied on stories as against numbers to achieve the
study objective. Qualitative research includes qualitative data and inductive approaches
to answer the "why" questions. For example, researchers may want to understand the
"why" of a particular phenomenon or why strategies have varying effects. Researchers
use the qualitative methodology to explore the principal theories and reveal new ones
(Yin, 2018). They use the case study to embrace repetitious cases to ensure data
saturation (Bansal et al., 2017).
Data saturation comes when no more new information or themes emerge after
interviews and the reviewed case document. While it is nearly impossible to reach total
saturation, considering that there is always the potential to discover new things in data,
though not the objective of saturation (Saunders et al., 2017). Saturation is not just to
reach a particularly critical point, but rather where no more discoveries emerged to add
further insights. Such a point must represent a ‘diminishing returns’ position in
developing a sufficiently robust understanding of the phenomenon.
The saturation point is a function of the sample size, which should range between
5-50 participants in qualitative research, according to Martino et al. (2017). The
administration of nonprobability sampling through an in-depth semistructured interview
will require a sample size ranging between 5-25 participants (Saunders et al., 2015). An
appropriate sample size is fundamental for researchers to achieve data saturation (Sim et
al., 2018). Careful consideration is for the sample size not to be too small nor too large to
make data analysis difficult (Saunders & Townsend, 2016).
96
I interviewed five participants and reached data saturation, for which I stopped at
that point. Yin (2018) suggested a sample size of five as often sufficient for a case study
research. The sample size of five proved sufficient to reach data saturation. There was no
reason to extend the interview by adding additional participants for data saturation to
understand the participants’ perspectives. It is essential to recognize the data saturation
point, where continuous research does not yield new information (Fusch & Ness, 2015).
Population and Sampling
For my qualitative case study, the population comprised those project managers
who best aligned with the research question and those with hands-on participation as
practitioners concerning the investigated subject matter and proclaimed to be subject
matter experts. Researchers use a homogenous group of participants who meet the
selection criteria. The intended group has the opportunity to gain relevant information
while improving data quality and saturation (Tavor & Spiegel, 2016). Originated from the
identified and selected individuals or groups of exceptionally knowledgeable individuals
or experienced with the phenomenon of interest. I chose a specific population of those
public-sector project managers who align their project outcomes with government
strategies. Moreover, those who work for four PSIP project-based units within the
geographic administrative region of Demerara/ Mahaica (Region 4) Guyana.
Sampling in case study research involves decisions that the researchers make
concerning sampling strategies, influenced by the number of case studies and the
description of the unit of analysis. Central to case study theory-building and testing,
purposeful sampling is a more acceptable sampling procedure for qualitative research,
97
particularly when selecting participants for special situations (Marshall & Rossman,
2016). The technique is a ‘statistically non-representative stratified sampling,’ while
similar to its quantitative counterpart. Its difference is in the sampling strategy. Even
though case studies offer detailed and in-depth evidence about a particular phenomenon,
the information gained is challenging to generalize because of the single focus
phenomenon (Akers & Amos, 2017).
In identifying and justifying the sampling method, researchers find an acceptable
way that ensures the sample type provides information richness and quality data.
Purposeful sampling is widely used in qualitative research to identify and select
information-rich cases related to the phenomenon of interest (Guetterman, 2015). The
purposeful sampling method helps identify and select participants based on their
knowledge and experience of the business phenomenon (Awiagah et al., 2016). Besides,
researchers use the purposeful sampling technique to control the targeted population's
scope and narrow down the participants (Coleman, 2018).
Researchers used the purposive sampling technique to maximize the chances of
seeking information on a specific case concerning the phenomena under investigation
(Coleman, 2018). Purposive sampling provides an informed selection for optimizing the
chances of observing the phenomena associated with the research. Besides, researchers
use the purposeful sampling technique to control the targeted population's scope and
narrow down the participants (Coleman, 2018). I employed the purposeful sampling
strategy to select the study participants to provide information about the study
phenomenon. The interviews were free from distractions and held in the comfort of
98
tranquility, in a quiet location for quality audio recording, in keeping with Marshall and
Rossman's (2016) requirements.
Ethical Research
Considering a qualitative studies' nature, researchers' and participants' interaction
can be ethically challenging because of their involvement. Saunders et al. (2016)
described research ethics as the standards of behavior that guide the research conduct and
explain the participants' rights and those impacted by the study as critical for a research
project's success. Researchers face ethical challenges in all stages of the research, from
design to reporting. Moral flaws pose a severe danger to scholarly research (Honig et al.,
2017). The formulation of specific ethical guidelines is, therefore, essential. The
adherence to the Belmont Report of ethical principles is a helpful solution to combat
ethical issues. The Belmont Report identifies fundamental ethical principles for
conducting research that involves human subjects and sets forth guidelines to ensure the
regulations are throughout the research process. The ethical principles of autonomy,
beneficence, and justice guide researchers in balancing the research's needs and goals and
the participants' rights.
The term autonomy explains that a person is free to decide whether to participate;
researchers must respect that individual's rights. Steele et al. (2016) suggested that
researchers must get permission from the participants. These principles are
considered universal and do not have national, cultural, legal, or economic boundaries.
Respect for persons is one of the fundamental principles in research. It recognizes a
person as an autonomous, unique, and free individual. While Sanjari et al. (2014) noted
99
that ethical issues mainly occur during the interaction between the researcher and
participants, each person has the right to make their own decisions. It gives the
participant a dignified belief that they are valued.
The beneficence ethical principle appeals to the researcher’s responsibility to
maximize participants' and society's benefit while mitigating associated risk (Honig et al.,
2017). The policy of ethics assures both participants and the broader community of their
well-being concerning the study. It guides participants against physical and psychological
harm; thus, the researcher must also ensure that the research benefit exceeds the assumed
risk. Researchers must be fair to the participants, and the needs of research participants
should always come before the study's objectives (see Glenna et al., 2019).
The justice ethical principle necessitates an impartial selection of research
participants (Roth & von Unger, 2018). Ethical issues in qualitative research may arise
from the researcher's effect on the participants and maybe subtler than quantitative
analysis problems. Justice, at its core, seeks to avoid participants whose participation may
have been unduly coerced - justice requires that participants must equally want to benefit
from the research (Yin, 2018).
Qualitative research seeks to (a) uncover meanings, (b) understand the intent, (c)
explain behavior, and (d) increase awareness of decision-making factors; the concept
pertains to the notion of "doing good and avoiding harm." Universities typically develop
a code of ethics in promoting ethical research, listing the principles and standards
applicable to research (Frechtling & Boo, 2012). Considering the ethics for the research
100
includes the informed consent process ensures each participant is fully aware of all the
proposals (Knepp, 2014).
Embedded in qualitative research are the notions of relations and power
connecting researchers and participants. Researchers have a social responsibility to
conduct their study ethically and preserve the research (Cumyn et al., 2018). To ensure
the study had the maximum ethical consideration, I exercised due diligence and
awareness, which was paramount for the participants. The participant's willingness to
participate in a study depends on their enthusiasm to participate in their experience. Each
participant was provided with the informed consent form for this study, which they
reviewed before the interview. The content of the way included details of the study,
including the objectives of the study. The interview process's procedure, risks and
benefits of being a participant, withdrawal information, incentives, the security of
participants and organizational identities, retention and protection of documents, and the
participants' confidentiality were all found to be effective approaches (Korstjens &
Moser, 2017).
All participants completed the informed consent form before their participation;
the consent form explained all their involvement to what end, how, how long, and for
whom. Besides, the participants' confidentiality was considered sacrosanct. Its
preservation resulted in those remaining nameless, referred to as “P” for practical
purposes of sequential numbering of the representative interview sample (e.g., P1, P2, P3,
P4 & P5, with their affiliated organization as A, B, C, and D). All collected information
would also be kept confidential; proper coding from the researcher must ensure accurate
101
coding from the collected data. The final report will not disclose any names (personal or
organizational). The collected data will be stored for five years with encrypted password-
protected loaded to an external drive in a locked container to protect the participants'
rights. After the five years have elapsed, the researcher will destroy all the interview
notes by deleting all saved data.
Data Organization Technique
The data gathering process in academic research demands that the researcher
securely and adequately manages the data. The most common qualitative data sources
include interviews, observations, and documents, none of which can be “crunched” easily
by statistical software. For Alase (2017), the story of people’s lived experiences, events,
or situations may describe as “thick,” suggesting the attention to the rich detail,
meaningful social and historical contexts, and experiences. Besides, the emotional
content's significance is open to the spoken words, including whoever is under
consideration. While the research data is considered an asset, selecting the correct
research participants for the study was tedious and daunting and must be carefully
managed concerning its value. Qualitative interviewing ideally solicited the participant's
perspective while eschewing judgment; thus, researchers' efforts resulted in the selected
participants for the research. A careful selection provides the best chance of having rich
and accurate study data, according to Higman and Pinfield (2015). I directed my analytic
attention towards the participants’ attempts to make sense of their experiences in
gathering rich and thick data. A qualitative research interview is more like a 'conversation
with a purpose,’ which is implicitly informed by my research question.
102
I used a notebook to collect the participants' data during the interview to form a
reflective journal - an account of the work in progress and a chance for reflection on the
learning experience. I recorded all of the interview conversations with an audio recorder
and simultaneously with my smartphone as a backup. All interview materials, including
the hard copies with the recorded notes and the transcribe documentation of interviews,
are kept in their original format. All data files will be safely secured in their original data
format for five years, in full adherence to the university's data retention policy (Briney et
al., 2015). Accordingly, after five years, the researcher can further use or otherwise
destroy the data if no longer needed (Marshall & Rossman, 2016; Patton, 2015).
Walshe et al. (2016) suggested five-year data retention at a minimum to ensure
data security. All hard copies will be saved in a physical folder under locked storage,
including electronic files. The audio production will be for safekeeping in my personal
computer, password-protected, and reinforced protection storage, with USB flash drive,
encrypted. I used a framework approach supported by a qualitative software analysis
tool. Framework analysis is an approach to qualitative data analysis that researchers use
to manage, analyze, and identify themes (Hackett & Strickland, 2019). I considered the
NVivo 12 from Windows for qualitative data analysis (QDA). NVivo, as a computer
software package, is used by qualitative researchers to organize, analyze, and find
insights in unstructured or qualitative data. According to Bonello and Meehan (2019), the
outcome is consistent with the recommendation to analyze data for quality assurance.
Nvivo works best with interviews where a deep level of data analysis is required. Bonello
and Meehan (2019) offered an excellent illustration of how NVivo was used to produce
103
an audit trail. It tied in how the data findings, interpretations, and subsequent conclusions
were traced and grounded to the raw data.
I used the framework approach to collate and organize the data and then used
NVivo as the qualitative software analysis tool for coding and generate the themes.
Qualitative data analysis aims to uncover emerging themes, patterns, concepts, and
insights from the gathered information, coded through carefully double-checking the
audio interview recording. I used NVivo to record, manage, identify themes, collate, and
analyze data, thereby saving time. Increasing the efficiency of organizing the data will
enhance the study's findings (see Kim et al., 2018). The coding and organization of data
are critical components of the qualitative researcher. Yin (2018) discussed coding to
explain how one defines the data analyzed and what they represent. Coding is the process
of identifying a passage in the text or other data items, searching for, and identifying
concepts and relationships. Coding is not just labeling, but linking data to the research
idea and back to other data is considered most useful (Elliott, 2018). Concerning coding
and analyzing the participants' information, I used thematic analysis to code the data.
Saunders et al. (2015) opined that the thematic analysis helps identify themes or related
patterns for reviewing the related research question for further exploration.
Data Analysis
Data analysis is significant within qualitative research because its interpretation
may influence the investigation (see Mayer, 2015). Data analysis entails checking for the
similarities between participant descriptions and the conceptual framework used in the
study for meaningful analysis (Yin, 2018). Considering my research, which explores
104
business strategy alignment within project management, the case study technique is best
for such an application. Researchers use the case study as the most accessible potential
for triangulation and to gain a thorough understanding of the complexity and uncertainty
in both projects and businesses (Mayer, 2015).
A significant antecedent for qualitative data analysis is for the researcher to
organize the data using a systematic and methodical approach (Yin, 2018). The first
approach requires the researcher to get acquainted with the data, requiring the researchers
to review the recordings, transcribe files multiple times, gain familiarity with the data,
and keep with the thematic analysis (Fugard & Potts, 2015). I reviewed the following: (a)
transcribed files from the interviews, (b) member-checked interview notes, and (c)
perusal of project documents provided. Further, the DBA doctoral study handbook makes
provision for at least two data collection methods. However, characteristically,
researchers use multiple methods to address their research question (Joslin & Müller,
2016; Walden University, n.d.-d).
Triangulation helps curb personal and methodological biases, and the effect is
that it helps to boost the research findings (Abdalla et al., 2018). Researchers and
participants alike have preferences and prejudices, which create influencing errors that
affect qualitative case studies' quality and reliability. For Yin (2018), errors of perception
hinder the credibility of the study design execution and the data analysis. Researchers
should use open-ended questions that stare the personal bias and assumptions (Saunders
et al., 2015). The ability to repeat the study to obtain the same results undermines
reliability. For my research, interviews and data triangulation were the two valuable
105
means of developing the converging findings. Data triangulation explains the correlation
between participants' views, project time, and space across multiple data sources (Fusch
& Ness, 2015).
Besides the interview transcripts, there were also project documents from
participant observation during interviews. The two methodological triangulation
strategies are within or between methods (Hastings & Salkind 2013). I used within-
method triangulation from two data sources, the interviews and document review. Those
choices explain the rich and descriptive data sources from which I derived a meaningful
explanation of my qualitative research rigor. Lawlor et al. (2016) offered several criteria
that should be met for triangulation to be valid. Triangulation should result from at least
two different approaches, and that the principal sources of bias are explicitly
acknowledged.
Researchers found that making judgments from a personal lens is one of the most
challenging qualitative research features. They wrote that hearing and understanding
others' perspectives is a massive predicament that researchers today should seek to
combat (Fusch et al., 2017). During my research analysis phase, I practiced conscious
checking for personal bias and be open to new ideas. A meticulous approach to the
qualitative process helps a researcher minimize prejudice and adds to the data (Maher et
al., 2018).
Researchers may perform validity control measures such as triangulation,
consistency, and replication to overcome the probability of systematic bias and false
inferences (Zyphur & Pierides, 2017). Triangulation applies to multiple data sources or
106
numerous data analysis approaches to enhance the credibility of a research study.
Triangulation of methods that include investigating potential divergences within the
outcome will tremendously increase confidence in a study. Hussein (2015) affirmed that
method-type triangulation implies multiple integral methods used in the data collection
and analysis. It offered the most appropriate data analysis process to complete my study.
The triangulation may result in new insight and a deeper comprehension of the
phenomenon under investigation (see Joslin & Müller, 2016).
I triangulate the data by synthesizing codes from the reviewed literature, the
project documents, and interviews to augment the overall themes. My data organization
technique resulted in numerous codes, as mappings can help identify themes, summarize
interview transcripts, and identify interconnectedness among the collective ideas
(Conceicao et al., 2017). I used physical concept mapping by sorting piles of related
codes. In triangulating the data, I sought connections in the data's coded categories and
explored the key categories. I deciphered the themes coming from the coded data
categories. I established correlated themes from mapping the collected data, with current
studies from the literature review relating them to the conceptual framework. Vaismoradi
et al. (2016) found that connecting themes to ascertained knowledge is indispensable in
the research process.
Reliability and Validity
Building a suitable and harmonious methodology based on the research purpose is
essential to ascertain a comprehensive research design, objectivity procedure, and
reliability (Korstjens & Moser, 2017). No one evaluation method can speak to quality in a
107
qualitative research setting (Chowdhury, 2015). Reliability and validity refer to
replication and consistency and provides a guarantee on the following essentials (a) the
design, (b) rigor, and (c) data saturation (Saunders et al., 2016). In assessing the design,
the measurement of the phenomena (the construct) creates the cause and effect
connection (internal) and the means to apply the findings to other cases (external). All of
which explains the repeatability of the study (Yin, 2018).
The second issue of rigor relates to the data collection analysis and coding, which
account for the process credibility, the dependability of the method used, the ability to
validate the data, and being able to transfer the results to other populations (Houghton et
al., 2013). One method is to follow the TACT framework of (a) trustworthiness, (b)
auditability, (c) credibility, and (d) transferability (Daniel, 2019). Trustworthiness is
achieved through reflexivity, while suitability is through the full description of the data
collection and the research process. Credibility is through peer debriefing and data
triangulation. Transferability explains how the research findings can demonstrate their
applicability to another setting or group of people (Daniel, 2019).
The third consideration is data saturation, which involves gathering and analyzing
the data to determine where additional coding is impossible. Therefore, such explains that
incremental data is no longer possible, suggesting enough information to replicate the
study (Fusch, & Ness, 2015). Finally, the quality assurance for research is considered a
profoundly entrenched provision in research work's validity and reliability (Saunders et
al., 2015). I used dependability, credibility, confirmability, and transferability through the
measures that follow:
108
Reliability
The researchers' findings' reliability provides credence to the overarching research
and equates the research's reliability with the necessity for accuracy and appropriateness
of the data collected (Morse, 2015). Qualitative researchers are obligated to present
adequate information on research design and evaluate quality in academic studies, often
evaluated from reviewing the survey against specific dependability criteria.
Reflexivity, triangulation, and detailed descriptions of the research process are all
strategies to ensure dependability, according to Hays et al. (2016). Dependability in
qualitative research refers to the consistency of findings across time. Dependability lends
credence to the study and equates the research's reliability with the need for accuracy
from appropriate data collected (Morse, 2015). Qualitative researchers are obligated to
present adequate information on research design for quality evaluation in academic
studies. Usually, a complete description of the research process, including reflexivity and
triangulation, determines dependability, according to Hays et al. (2016). My study
incorporated the three dependability strategies, in addition to member checking
interviews.
Reflexivity monitors the researcher's assumptions and relationships throughout
the research process (Hays et al., 2016). I remained conscious of my role as a data
collection instrument: As the study proceeded, I kept awareness of my assumptions and
the need to guard against bias. Through openness and collaboration with the participants
will help build trust. Therefore, building trust is necessary, especially for methodological
triangulation. It allows for the use of multiple data collection instruments that adds to
109
conformity (see Heesen et al., 2016). I consolidated several data collection instruments,
including (a) interviews, (b) project reports, (c) baseline documents, and (d) reflective
journals for methodological triangulation.
I presented an accurate description of my doctoral study research process,
enhancing the findings' dependability. Besides demonstrating reliability, I used member
checking to review the final documents and seek alterations of any explicit descriptions
or themes. All were discussed with the participants to determine accuracy (see Birt et al.,
2016). The consideration of member checking a second interview with the participants
can also enhance the findings' credibility. In addition, member checking interviews serve
the purpose and process of obtaining consent to use specific components in the final
study report (Thomas, 2017).
Validity
In qualitative research, validity points to the accuracy of the findings (Darawsheh,
2014). The qualitative research results are credible when the findings represent an
accurate representation of the participants’ experiences. To ensure validity in a
qualitative study, a researcher must address credibility, transferability, and confirmability
(Yin, 2018). Credibility is a symbol of validity, and qualitative researchers aim to
demonstrate validity through triangulation (Yin, 2018). Because credibility is an
indicator of validity, I sought to incorporate methodological triangulation, which
explains the degree to which my research findings are accurate. Hays et al. (2016)
offered ways to increase credibility; there are not limited to triangulation but include
reflexivity, thick descriptions, and member checking interviews. All of which were
incorporated into my research.
110
Another indicator that demonstrates validity is transferability. Noble and Smith
(2015) found transferability to involve the study’s findings in different contexts. The
transferability of the research results is a crucial element I considered during the study. I
provided a complete description of the study objective and the findings to enable
participants, researchers, and readers to implement any recommendations in their work.
Korstjens and Moser (2017) explained transferability as the potential for extrapolating
results transferable into other respondents' settings. The findings were documented so
that the participants, researchers, and readers might adopt the recommendations.
Researchers found that thick descriptions and triangulation lead to transferability (Hays et
al., 2016). While I cannot create transferability from the research, my findings must yield
applicability to others based on the recommendations— a pillar of transferability
(Marshall & Rossman, 2016).
The third validity indicator is confirmability, referring to the accuracy of the
participants’ perspectives from the findings versus the researcher’s viewpoint (Hays et
al., 2016). Connecting data, its analysis, triangulation, and member checking are all used
to establish confirmability (Hays et al., 2016). Upon gathering the data, I quickly
organized the analysis data, which incorporated triangulation, reflexivity, thick
descriptions, and member checking interviews to ensure confirmability.
Transition and Summary
In this section, I restated the purpose of the case study, enunciated my role as the
researcher, described the participants, and provided selection criteria for the study
participants. In Section 2, I examined how ethical considerations fit into the data
111
collection process framework, the proposed data analysis technique, and the proposed
plan to ensure credibility, confirmability, dependability, and data saturation.
Section 3 described how my findings applied to professional practice and the
implications for change. Section 3 comprised a discussion on the overview of the study,
presentation of the findings, applications to professional practice, implications for social
change, recommendations for action, recommendations for further study, reflections, and
summary and study conclusions. I concluded the section with a final summary of key
study outcomes.
112
Section 3: Application to Professional Practice and Implications for Change
Introduction
The purpose of this qualitative multiple case study was to explore effective
strategies that public sector project managers used to align the project outcomes with
government strategies to maximize project performance. This multiple case study
participants comprised five project managers who successfully aligned their projects with
government strategies and worked for four project-based units within the administrative
region of Demerara/Mahaica (Region 4), Guyana. The study data were primarily
collected using a semistructured interview technique and review of project close-out
reports. The interview process was complemented by reviewing documentation of
successful projects completed by those who volunteered to help realize the study's
intended outcome. The chosen projects were those with which the managers
demonstrated successful alignment from three constructs with at least 80 % compliance;
(a) identification of the set goals from the baseline studies and how they were captured
within the project goals on a percentage basis; (b) exploration of each of the alignment
factors of cost, time, and budget; and (c) examination of the end user's satisfaction from
stated goals of both the project and organization. Successful realization of aligned
projects occurred when at least 80% is achieved within the iron triangle of budget, time,
and scope, where the original goals and business intent were met through higher benefit
realization, according to PMI guidelines (2017).
I conducted semistructured interviews with five project practitioners who
provided their perspectives and experiences in project management. The participants
113
answered nine open-ended interview questions and provided appropriate responses
concerning the research question. The interview questions inquired about public sector
managers' strategies to align project outcomes with government strategies to improve
project performance (see Appendix A: Interview Protocol). After reviewing and
transcribing participants' responses, I used NVivo 12 Plus from Windows to identify key
themes across the transcripts. NVivo's software application helps determine accuracy in
qualitative studies (Bonello & Meehan, 2019). This section discusses the applied design
process results, identifies the key themes and conclusions deduced from the analysis, and
offers recommendations for PSIP policymakers, project management practitioners, and
project management researchers.
Presentation of the Findings
The research objective was to find answers to the central research question, and
in answering the research question, I used a guided interview protocol for the interview
process. According to Castillo-Montoya (2016), the protocol enables researchers to
conduct the interview and ethically enhance the data collection process. The interview
protocol included introducing the study objective, reviewing the consent form, ensuring
the confidentiality of information provided, and obtaining approval for the interview
audio recordings. I also asked the nine prepared interview questions and follow-up
questions requested any necessary documents, and sought participation for member
checking. The interviews lasted an average of 45 minutes and occurred at convenient
locations chosen by the participant. I assured the participants of their privacy by
114
identifying the study data participants with pseudonyms PT1, PT2, PT3, PT4, PT5, and
their respective organizations with pseudonyms A, B, C, and D.
I shared the interview summary with the participants upon the interviews'
completion to confirm my interpretation for accuracy concerning the answers provided.
Yin (2011) provided a five-step approach, which was the overarching technique used to
guide the qualitative data analysis process.: (a) compiling and organizing, (b)
disassembling, (c) reassembling, (d) interpreting, and (e) concluding phases. At the initial
stages, I examined the organizations' project documents to confirm compliance and verify
that the data collected from the semistructured interview method involved projects with
successful alignment. Finally, I constructed a list of the initial codes that emerged from
the analyzed data and grouped them accordingly, creating their respective anchor code.
Then I tallied each code's frequency of occurrence to generate codes' categories and
examined them to create themes. The themes below address the research question that
explored the public organizations' practitioners' strategies when aligning government
strategies to their project outcomes to maximize project performance.
The major themes derived from the analysis were (a) government/executive
commitment and support for the project teams, (b) efficient project management skills,
(c) aligning national strategy with project processes, and (d) managing public project
processes with ICT tools. The documentation provided and a detailed description of the
step-by-step process of the evolved findings created an accessible path for critical readers
to understand the process. I offered clarity on the points of interpretation from the themes'
extensiveness and assessed the validity of the data mining process results. In addition, I
115
extracted raw data from the thematic analysis to augment the practitioners' stories with
direct quotes from the participants.
Theme 1: Government Executive Commitment for Project Team
The first theme from the analyzed data was the government's commitment to
maximizing project performance. According to PT2B, the government must assign
resources and enforce decisions regarding the project. According to PT1A, relationship
dynamics work best within a stakeholder engagement plan designed to outline
consultation and communication activities throughout the projects and present the
pathways to incorporate feedback into the project’s life cycle development. Similarly, for
PT2B, “it is their support that turns the project concepts into reality.” All participants
expressed the desire for project executives to involve project managers in the business
strategy development process. The five participants (PT1A, PT2B, PT3B, PT4C, and
PT5D) recognized the need for the government executives to clarify the strategies for
alignment as required by public investment projects that are purely out of the project
team's control but needed communication. According to PT1A, misalignment occurs
because project managers do not precisely get government strategies, reflecting poor
communication as opined in Erceg & Gulam (2018). For PT5D, the organization uses its
steering committee to understand the government’s thrust in fulfilling its election
manifesto promises. In further support, PT1A and PT2B observed that executives'
support strategically helps align the government's long-term vision for improved project
outcomes.
116
While business executives and stakeholders generally drive projects, they are
treated as solution providers while not involved in the project fulfillment phase. PT5D
described the National Procurement and Tender Administration Board as having a
political role in the project execution process for information requirements. Its current
evaluators display no contract engineering or project management skills. According to
PT1A, they can delay the solution implementation efforts due to a lack of appreciation.
PT3B opined, “I believe this challenge can be addressed by giving technical experts a
seat at the table,” referring to the upfront inclusion of technical support at the stage of
project conceptualization and the initial planning. For PT3B, such practice would add
technical value that drives the business case against following instructions and delivering
what was requested. On the flip side, PT3B discussed how some technical experts also
lack business knowledge because they are driven by technology and not the business
case. PT4C offered a solution that encompasses finding a middle ground to bridge the
divide; a nexus between infrastructure and business needs worked best in [named]
organization. PT2B stated that,
infrastructure projects generally follow the governing administration’s priority,
and their election manifesto promises… everything comes from the top when
initiating a project, or the project will never take off.
Consequently, for PT1A, the government must sell its ideas through clear
communications, enabling the project team to understand the strategic direction. In
return, the project lead/manager must achieve government strategic alignment once it is
distinctly communicated. PT2B's concern was how management executives made
117
decisions. "The challenges are with top management because they make decisions from
top to bottom," PT4C explained the value of top management commitment in aligning
project management outcomes with government strategies. PT5D and PT1A each
expressed the desire for executives to involve project managers in project governance
strategy development. PT5D posited that "alignment with projects to the government
strategic plan involves a collaborative strategic development of the project plan." PT2B
stated that after the top management's approval, the projects come to the executing unit
for rollout by the selected contractor, local or international. Outsourcing depends on the
environment and the project sponsor. International contractors with cross-country
experience are helpful for project leadership, according to PT2B and PT5D. Project
leadership skills are crucial in public sector investment because people in the
construction industry come from diverse backgrounds and professions. The collaboration
with the locals facilitates knowledge transfers, benefiting globalization. According to
Potter et al. (2018), cultures are intertwined to fulfill short-term project goals in a varied
and uncertain operating environment.
Participants PT4C and PT5D acknowledged the importance of executive
committees in overcoming project challenges, especially those involving financial,
environmental, political, and issues of project procurement. While the project executives
seek to address those challenges for the project teams, PT5D stated that "sometimes the
project budget is skewed for political expediency, and execution sometimes becomes
problematic. Still, with some tweaking to the objectives, the project gets implemented."
PT4C discussed adequate administrative support in providing training as a benefit of
118
stakeholder collaboration. "Expatriates usually provide knowledge transfer and develop
the local project team's skills," according to PT4C, PT5D concurred. All participants
expressed the desire for executives to involve project managers in its business strategy
development process. PT5D said that in "developing projects to align with government
strategy planning, one must at least be involved in developing the strategic plan at a
minimum." PT2B similarly held that "if you decide to go ahead with the project, then the
executives must involve project managers in the government strategy development."
Correlation With Recent Studies
The role of executive management in project management has been discussed
repeatedly in the literature and received more attention in this research project. According
to PMI's (2017) Pulse of the Profession report, engaged executives drive projects in
meeting their original goals and business intent. PT1A, PT4C, and PT5D's assertions
supported Alsudiri et al. (2013), who identified the importance of the executive and the
project managers in the organization’s strategy development. Still, project managers
continue to examine ways to enhance executive support, the lack of which is the second
most significant factor contributing to poor project performance, according to
PricewaterhouseCoopers (2012).
In principle, PT1A explained how empowering [their] organization executive
extends the sphere of the respondent's influence. Therefore, stretching beyond the
project boundaries and up into the organization, such influence may help executives act
and implement speedy action (PMI, 2018). For example, PT5D explains that some
projects are taken to the tender board in the interest of time, even before the national
budgetary
119
appropriation for the fiscal year. Similarly, when the project coordinating agency
involves the project managers, their involvement is to better understand the government's
business strategy processes, allowing project managers to implement. Similarly, by
adding practical inputs and feedback mechanisms to the strategy, the project manager in
the strategy development helps build an effective work environment, according to
Silvius et al. (2017).
Erceg and Gukam (2018) found that some public investment programs were beset
with poor communication and coordination among the critical stakeholders. Despite such,
PT2B, PT3B, and PT5D found the various government executive committees appreciate
effective communication, which realized the project management processes' alignment
with the implemented government strategies. However, executive support means that
executives must maintain a hands-off approach but must avail themselves when problems
arise (Khan, Waris, et al., 2019). A government's commitment through effective
communication better maximized project outcomes, according to Erceg and Gukam
(2018). PT2B remarked that the executives do involve some project managers in
government strategy development. The collaboration with government strategies
minimizes the scope of defining the problem, reduces design errors, and creates a
workable schedule for critical problems affecting project deliverables and milestones
(Badewi, 2016). The maximization of collaboration and coordination among stakeholders
drives positive results, according to PT1A. In contrast, the opposite is true - a traditional
contracting arrangement involving a lack of coordination among stakeholders, which
would yield a less desired outcome (Ling & Tan, 2015).
120
Chiarini (2016) argued that the prudent executive action of showing commitment
had a positive long-term effect on achieving significant project outcomes. The
participants' responses were in line with Chiarini’s findings. PT5D suggested that
executive management commitment is essential in strategy alignment with projects to
maximize project outcomes. Similarly, communication engagement was seen as a critical
activity for strategic alignment, according to Chiarini (2016). PT3B describes the
communication process as “weekly and monthly progress reporting and meeting,”
resulting in “effective consultations or scoping meetings to guide the infrastructure
projects.” A reconciliation of the different project teams and designs enables
sustainability for a fulfilled project when the communication and strategy alignment is of
utmost importance to any project deliverable and milestones (Zolfaghari et al., 2017).
While project success often depends on how well the executives communicate,
building relationships with the project manager during project life cycles allows for better
outcomes. For PT5D, “stakeholders add value to the design process and provide the
business analyst with the necessary information for systems engineering.” In some
situations, according to PT1A, the strategy misalignment occurs because no one explains
the responsibilities concerning the project outcomes, which is consistent with the findings
of Erceg and Gukam (2018). Project executives often do not understand their roles and
responsibilities of providing support to lend direction for strategy adoption, cited by
PT1A. However, PT3B underscored the importance of project reporting responsibility
and opined,
121
One must be clear: who their reporting officer is and what matter is being dealt
with by whom, which have always been a bottleneck to a project because persons
are unaware of who is dealing with what aspect of a contract and project.
Administrative support is needed to improve project success rates; environmental
issues can result in strategy changes or regulations that influence projects' progress and
outcomes. Empirical evidence described the relationship between executive support for
project success as commitments, beliefs, and rewards as the most significant variables
affecting project success (O’Brochta, 2018). PT1A found that stakeholder support is
enabled by embedding the requirements for an effective mechanism to address grievances
- a workable framework that projects could practice. In addition, they can provide
insights for senior managers regarding the executives’ roles in organizations to contribute
to project success.
Alignment of Findings to Contingency Theory
Applying Fiedler’s contingency theory, leadership preference plays a significant
role in project success in varying situations. The model establishes that leaders are either
task-focused or relationship-focused. Understanding one’s style of management is
required to facilitate the most effective match in a given situation. For example, those
leaders with a preference for the human orientation (High LPC) will do best within
favorable conditions. In contrast, task orientation leadership (Low LPC) will be most
effective in unfavorable situations (Fiedler, 1964). Besides leadership style, job design,
decision-making participation, and organizational structure are criteria for an excellent
overall managerial outcome. Davies et al. (2016) opined that the implications seek to
122
balance the importance of an individual’s preference and situational factors. The
analyzed data was centered around the organizations’ size, uncertainty, and complexity,
which is best understood using the contingency approach. It is a mechanism for better
performance when linking the front-end with the relatively late project cycle phases.
According to Qazi et al. (2020), when uncertainty increases, the appropriate structure
must be less formalized and more decentralized, with systems coordinating between
functional departments such as project teams. In comparison, the appropriate structure
will significantly raise the degree of bureaucratic structure. The more autonomous project
teams realize organizational strategic objectives, according to PT4D.
Three of the five participants impliedly suggested front-end collaboration as
critical because it allows obtaining better information from a flexible project portfolio.
Similarly, researchers found that the contingency theory provides the best uses for
strategic flexibility by extending the framework to organizational choice utilizing the
goodness of fit (Starkey et al., 1991). For PT2B, the main aim of the front-end
management style is to get the strategy anticipation right –a critical element for prudent
decisions at the initial stage of the project rather than during execution. Pinto and Winch
(2016) discussed supporting a positive link that connects successful front-end and overall
project fulfillment. PT4C depicted front-end practices as the period between the
proverbial “blank sheet of paper” up to the project proposal stage.
In contrast, PT2B saw it as “the concept notes that invaded the project that gave
rise to the project charter.” Still, the actual benefits of front-end success depend on the
environment and the government mindset—those additional measures taken by the
123
executives to support the exploitation of the promising project (Pinto & Winch, 2016).
PT5D describes the process as starting with a ‘Trip report’ containing all of the pre-
requirements. It later becomes a “memo,” containing all technical details, the soft skills,
socioeconomic issues of the community that will benefit from the project. Powerful
upfront collaboration connecting the project executive with the project design team and
the executing contractor effectively addresses risk and uncertainty by improving the
project participants' dynamic capabilities (Davies et al., 2016). Each of the four
organizations had different structural variability.
While both managerial and technical tasks have different degrees of complexity
depending on their purpose, the interdependencies required for completion allow for
contingency theory application. While complex projects need direction from the
executive, establishing executive directions requires effective communication of a
sharped aligned vision to benefit higher-performing project teams (PMI, 2018). A holistic
commitment by the executives to project management is vital in realizing more
sustainable project governance practices, according to Volden and Andersen (2018). The
commitment must allow for the empowerment of project managers to benefit from
aligned project outcomes. Executives who adopt sustainable principles in the decision-
making processes had better results than just relying on the constraint of time, cost, and
quality, according to Silvius et al. (2017). The use of objective information, track records,
communication between partners, and confidence in partners' competence constitutes the
commitment's trust.
124
Theme 2: Efficient Project Management Skills
Implementing efficient project management skills is the second theme that
emerged from the analyzed data. The participants expressed that considerable project
management skills (hard and soft skills) are prerequisites for successful projects. The
participants demonstrated the importance of soft skills for infrastructure project teams. A
likely suggestion because most public project managers are foremost engineers and need
professional project management training. PT2B explains how embracing new project
management practices can be helpful, "I must remain flexible, given the complex
environment in which megaprojects operate." PT3B introduced a communication
perspective that strongly encourages project teams to provide feedback instead of being
static in the mundane and routine work roles. PT2B used the feedback to focus on
information specific to individuals in determining the skills set to understand their
assigned roles. Similarly, PT5D uses peer review, which allows the team to critique each
other to release and remove any gaps. The process supports the empowerment of the
project team in general, as Tabassi et al. (2016) found empowerment helpful in managing
public projects.
In addition to technical competence, exceptional soft skills attributes are
necessary for success when managing engineering projects. Alias et al. (2014) specified
infrastructure projects and the use of knowledge management (KM), both the traditional
and modern management practices, with a broad application for the project’s design that
includes the construction process. PT5D acknowledged some of the challenges with
project failure but suggested: “effective and workable KPIs to guide the construction
125
implementation of these projects is what makes the difference.” Participants (PT4C &
PT3B) emphasized how knowledge management (KM) adds value to the project,
program, and portfolio success. They opined that public policymakers must have the
ability to review the arrangements of the project carefully. According to PT1A, one must
be able to “deduce the most realistic contract completion timeline.”
The project managers in organization ‘B’ had significant concerns about lacking
in-depth technical skills and experience to determine the project contract timeline
accuracy. Asked how effectively data is used in determining project timeline, PT2B noted
“the picture is mixed” but suggested that project software provided predictability. From
the pursued documents, it was observed that while some used the data effectively, there
are others where the potential for data use is encouraging but missing. PT2B offered this
example, “architects would generate the project designs, but may not have thought of
using the computed data to prepare the bill of quantity (BOQ).” The BOQ helps derive
the tender price, which becomes helpful in the administrative review in the approval
processes. Most of the used data revolved around solving critical problems that enhanced
the project management processes from the observed documents. PT1A said," the project
team analyzes the project’s scope, contract, and other information to define the
deliverables, after which the team will develop the milestone schedule."
Much of the data used historically lacked current performance indicators and
records from previous projects. Features of the reports included causes of delays, systems
planning, systems design, systems implementation, performance, and user involvement.
PT4C addressed how data use has evolved and drew reasoning from the benefits of
126
Oracle and its Oracle Aconex. “The platform provides dashboards that facilitate
identifying issues such as pending change requests with revised approvals,” PT4C
opined. Although not always adequate, PT2B found collaboration and cooperation
essential among all stakeholders to coordinate with the executive on effective project
timelines. While utilizing the project management tool enables practitioners to document
effectively, the derivation of analytical information remains problematic. Still, PT2B
illustrated the tactic used to measure performance and to determine contract time. The
balanced scorecard provided a comprehensive framework that translates strategic
objectives into an identified set of performance measures integral to the project
management process.
Similarly, PT3B found the work breakdown structure (WBS) a valuable tool for
collaboration and reasonable expectations for milestones and deliverables considered
from the SMART goal perspective – a guiding criterion for setting objectives (specific,
measurable, achievable, relevant, and time-bound) based on the government’s
expectations. For PT5D, after seeking buy-in from the project’s engineers and
technicians, the estimated timeline becomes an agreed schedule. PT1A opined that
prudent engineering and KM from experienced team members provided remarkable gains
during the planning and project implementation. PT4C similarly remarked that having
the needed project skill is essential when managing and evaluating complex engineering
designs. PT3B highlighted examples that determined the associated risks and showed
how the team developed workable timelines, assigned tasks, and set attainable
milestones. There were quite similar to that of the SMART approach adopted by PT5D.
127
Engagement through effective communication and empowerment are practical
management skills that directly influence infrastructure projects. PT3B emphasized that
project managers should avoid portraying the attitude that suggests only one way of
performing the project. While experience matters, as discussed by PT5D, knowledge
transfer is a feature of project communication, described as a “toolbox” meeting with the
staff. PT3B stressed that project managers need to listen attentively,' allowing members
to participate freely. For PT4C, "I get a better understanding of the project's issues by
hosting regular meetings. The feedback provides a collaborative team approach
concerning the project deliverables and milestones are the benefits described by PT1A.
Correlation With Recent Studies
Many failed projects showed poor management skills concerning the hard and
soft skills of the project manager. These skills contribute to continuous learning,
according to Sabrokro et al. (2018). Public project managers must be trained with the
required skills to implement successful project alignment to maximize outcomes (Cole,
2017). Consequently, the respondents suggested that novice project team members need
education and training to quickly learn to adopt the new knowledge required for project
management amid changing environments. According to Pretorius et al. (2018), the
required knowledge includes standard scope, cost, quality, customer management, and
the ability to recognize and implement other appropriate project management
methodologies at each stage of the project lifecycle. Carvalho (2015) describes those
requirements as relevant for improved project management skills.
128
Engagement through effective communication and empowering subordinates are
practical leadership skills that directly impact infrastructure projects, according to
Berggren (2019). Similarly, PT2B spoke of the benefits of effective communication by
encouraging project teams' feedback on issues that may change the mundane and
repetitive work roles in a dynamic environment. Communication may impact one way or
another on the project outcomes; as a result, PT5D opined that a cultural element of
empowerment supports open communication. According to Abou-Hafs et al. (2019),
applying broad-based blended skills approach greatly assisted project leaders. In contrast,
low participation in empowerment concerning planning and implementation at a housing
construction project led to the project's delivery (Lin, 2018). Still, communication
strategies may work best as critical success for project implementation when blended
appropriately with the relevant stakeholders (Zuofa & Ochieng, 2017). PT4C opined that
“there would undoubtedly be times when you have to collaborate with people in other
departments."
Researchers in behavioral competence learn how soft skills and technical
competence (hard skills) have impacted project outcomes (Abou-Hafs et al., 2019; Tian,
2020). While the participants exhibited hard skills from their engineering experience in
mapping project processes, three of the five participants emphasized soft skills to support
their project teams. Generally, studies concerning hard and soft skills have all come up
with similar conclusions concerning project practitioners, even though their methods
differ. In their designs, some were quantitative; others were through concepts and
available theories. Similarly, Balcar (2016) found that both hard and soft skills increased
129
productivity. For example, PT5 discussed that a smooth blend of interpersonal and social
skills among teams is an excellent mix to improve work efficiency. For Rao, a “judicious
blend of hard and soft skills is essential for achieving professional and leadership
success” (2018, p.215).
Interestingly, soft skills effectiveness facilitates hard skills' success, requiring
prudent communication for project management coordination (Ofori-Kuragu et al.,
2016). Therefore, cross-functional support during the project implementation process
with clearly communicated goals leads to project fulfillment. While soft skills increase
the project's potential to be on time and within budget, researchers discovered that the
positive impact was more pervasive in the on-time delivery of infrastructure projects
(Musembi et al., 2018). In addition to non-cognitive (soft skills) activity demonstrated
through effective communication, performance behavior is essential for project
management communication with non-technical folks (Smith et al., 2018).
Alignment of Findings to Contingency Theory
The second theme concerns the effectiveness of project management skills which
correlates with the seminal works of Fiedler's contingency theory. Fiedler established a
contingent relationship between the project environment, leadership style, and
organizational effectiveness - an approach contingent on the prevailing circumstance. The
participants demonstrated varying degrees of hard and soft skills at different stages in the
projects’ processes. PT1A and PT4C implemented strong technical skills for their
projects; planning, analysis, tracking, and problem-solving at the initial stages of the
projects, blended with softer skills within the project life cycle processes. “ I ensure that
130
all possible issues that can arise at the planning stages are dealt with upfront concerning
the processes in the project cycle,” PT4C opined. PT3B demonstrated more hard skills
throughout the project processes but showed empathy for collaborative influence in
leadership. Given the unique consideration required for each project lifecycle phase, a
flexible management solution was the participants' (PT3B and PT4C) answer. Their
effectiveness demonstrated softer skills application with benefits during project
fulfillment, mainly when applied to the project processes from the given task, as seen in
Cole (2017).
According to Mirza and Ehsan (2017), project managers must exercise two kinds
of hard skills. First, technical skills within the project’s domain include analysis,
planning, tracking, and problem-solving - usually numerical, logical, and data-oriented
skills. Second, to determine the behavioral approach towards incorporating decision
process support into project management, which has its roots in the Decision-based
system development paradigm. For example, PT2B and PT4C used the Gantt chart and
PERT to illustrate project progress and milestones with dependencies. Those tools
provide a quick project overview, enabling swift management decisions at a glance,
according to Mirza and Ehsan (2017). Approaches that incorporate decision process-
support into project management are rooted in project managers’ everyday work as the
primary source for understanding the competencies of relevance. While project
management methodologies often overlap with complex societal and political
dimensions, a design like the agile approach may provide a more inclusive management
approach. Policies of selective flexibility, learning, adequate authority, people first,
131
collaboration, in consideration of unstable conditions, may prove a complimentary
replacement for traditional project management practice.
Vidal et al.'s (2017) contingency approach to leadership found that effective
project management requires considering two approaches. The first is the traditional
leadership approach based on technical skill and know-how, which requires managers to
complement people skills in implementing specific tasks. The second involves processes
in complex project environments. DuBois et al. (2015) found that maintaining leadership
qualities aligned to the organizations' environment facilitates smooth and efficient project
management. The right strategic approach must decide what organizational culture and
leadership are needed to execute the strategy successfully (Reeves et al., 2018). The
process requires a match between the environmental characteristics and those of the
organization to yield high performance. This match is called the 'fit'; the better the fit, the
higher the performance.
Theme 3: Aligning National Strategy with Project Processes
The third theme that emerged from analyzed data was customizing project
implementation processes and procedures to suit each organization's specific project
implementation requirements. For PT1A, to benefit from a workable national strategic
approach means integrating practice entirely into all aspects of the system. It is not an
additional task or an ad hoc activity but a routine and integral part of the system itself.
PT1A opined, “a key function of a dedicated implementation strategy and approach is to
ensure sufficient flexibility to adjust strategy, objectives, and priorities in response to
changes in the broader political and operating environment.”
132
Government plays such a crucial role within the project concerning identification,
design, and decision-making process. Therefore, for PT1A, it is necessary to leverage
specific organizational characteristics during the project management process to ensure a
successful outcome. PT3B suggested that project appraisal embraces internal and external
variables using the public sector management approach. PT3B opined that the program
budgeting and value-for-money analysis help consider the risks to be borne by both the
public and private sector partners (project end-users). According to PT4C, “feasibility
studies determine whether the project is a feasible or viable investment; in its absence,
infrastructure projects will continue to fail.” In assessing viability, consideration must be
both internal and external. According to PT2B, internal, cost-benefit analysis, and
environmental impact assessment are the primary external considerations. Besides, the
analysis should also include private sector participation and projects' suitability to
develop the other sectors. According to PT3B, forward and backward linkages for
economic growth and development are encouraged.
According to PT5D, the methods and techniques specific to each project process
helped participants overcome past problematic issues, citing lessons learned from
monitoring and evaluation. Similarly, PT4C remarked that "with lessons from the past,
the project teams and contractors now have a clear understanding of the project manager's
expectations, especially those concerning the government's strategy.” Illustratively, PT3B
established a procedure that best helped track information that reduced the contractor and
project timeline. In contrast, PT4C observed a procedure involving a form template that
illustrates communication flow charts and verifications in a more precisely formulated
133
way. PT1A and PT3B discussed similar experiences adopted in their organization's
project procedures.
Correspondingly, PT4C used a standardized step-by-step project tool called a
work breakdown structure that presented the management details for the various project
execution phases. In organization ’C,’ the project team followed the formalized process
by inspecting the tasks and identified timelines. Although an independent supervising
consultant firm maintains quality assurance, according to PT4C, using the management
checklists is another tool for determining project quality management. For example,
PT3B's quality management checklist offers a condensed and effective road map. The
lists showed by PT4C and PT3B was operational during the design stages, with data
obtained as the project develops. When asked about the list's effectiveness, PT4C
explained that while the road map cannot show every quality measure, it aids decision-
making.
In addition to the process of checks and balances, communication, documentation
of bills of quantities, standards of delivery, and acceptance reporting are measurements to
support the standardized procedure seen in the observed reports. The success of those
activities triggers the contract acceptance criteria for the achieved milestones consistent
with the guide in PMBOK. PT1A explained that a fundamental input collaboration for the
management review processes involved the project consultant in realizing the process for
the change management. To increase operations input into the project design according to
PT1A involved sending the engineering blueprint for operational review and feedback at
134
the initial stage (foundation). After that, the change is agreed to and finalized, then
implemented and executed as an approved change plan, signed by the relevant parties.
PT1A's procedure worked well within the project management process in the
planning phase when supplemented by Agile-Scrum methodology. The hybrid
methodology allows for a flexible framework readily tailored to any project type or size,
associated with the work environment, and finalized within an agreed-on timeline,
according to PT1A. While Microsoft Project efficiently documented and monitored
projects (regardless of their size/scope), PT4C explained the need to break the project
into events and activities in a work breakdown structure. Described as a schedule that
monitors each activity's quality and effectiveness within a systematic procedure. PT4C
further illustrated,
We often get into problems with contractors when they turn up on schedule and
find they cannot work because of an earlier activity lagging in time. It is more of a
problem than the lagged task is their dependent activity.
The challenge suggests that timely communication and continuous collaboration
beyond the supply chain can make a big difference between success and failure in
infrastructure projects and improve productivity in delivery. PT2B observed that "while a
project is initiated and completed as a unit activity, it now involves the sum of the; supply
chain and general stakeholders’ support." PT3B found usefulness in project schedule
tracking by creating documents to track progress and monitoring risk. The use of Oracle
and its Oracle Aconex platform provides dashboards that facilitate identifying issues such
as pending change requests and review approvals. Similarly, PT1A prefers an integrated
135
delivery team that aligns around end-to-end solutions, not technologies. According to
PT1A, to realize the best result, the “project information should be updated within the
MS Project planning space, allowing the project to constantly be updated and
streamlined with the technical team’s tasks.”
Concerning risk management, the participants found the risk register helpful in
handling the risk management, i.e., mitigate, accept, transfer, or ignore the risk depending
on the circumstances through collaborative efforts. The participants concurred that there
is a need for solid leader-member relations for project success. These must extend off the
enablement tools that empower individuals to be productive without the need for hands-
on leadership, a tenant of the studies of both Fielder (1964) and Maqbool et al. (2017).
Still, PT3B and PT4C noted that leaders must present tasks clearly and with outlined
goals and procedures. Similarly, PT1A advocated using project charters and the five
stages of the project management life cycle reworked into a WBS - breaks down the
project into individual activities and assigns each activity with responsibilities, labor
intensity, and time demands.
Correlation With Recent Studies
Governments implement infrastructure projects and strategies to deliver projects,
despite their challenges. To be efficient in selecting projects, allocating efficient
resources, effective communication, and prudent leadership practices would be valuable
for delivering the desired project outcomes (Hyväri, 2016). The strategy employed by the
participants reinforced McAdam et al. (2019) study of the contingency theory and its
applicability for leaders to analyze management effectiveness to gain competitive
136
advantage. Communicating the objectives of the projects while maintaining controls for
the project requirements are roles of project managers (Dyer et al., 2016). Still,
infrastructure projects require organizational strategy, driven by the executives in a
centralized way through sustainability for competitive advantage (Hyväri, 2016). A
unified entity like the project management office (PMO) will drive resource allocation,
stakeholders, sustainable initiatives, and the realization of end users' satisfaction
completion - a unit responsible for the project portfolio management.
Regardless of the methodology, allocating the right amount of time for planning
increases project outcomes in the long run. A good project plan offers benefits as
reducing uncertainty, increasing understanding, and improving efficiency. While the
project practitioners view the end users' as the ultimate project stakeholders, they treat the
outcomes as the critical success factor. The plans executed through others provide a basis
for measuring work planned against work performed (Wysocki, 2019). Consolidating a
customized process with a standardized project methodology may allow a comprehensive
solution for project management success. Besides, techniques have enhanced projects'
effectiveness, which has achieved project success concerning end users’ satisfaction
based on the prevailing contingency of volatility, uncertainty, complexity, and ambiguity
(VUCA) (Pace, 2019).
Researchers found that the appropriate procedures and templates to selected
processes would enhance the process implementation to maximize the project's outcomes,
aligned with the organization's goals and objectives (Kononenko & Lutsenko, 2018). Not
all the participated organizations have standardized project management processes.
137
However, the successful practitioners found means to adopt new standardized strategies
into their project management process to improve effectiveness based on their project
training and experience. Kononenko and Lutsenko (2018) offered the benefits of
professional institutions and developing project practitioners' management of the
projects’ processes and procedures within various industries and project management
needs.
Culture drives the organization's commitment by establishing the underlying
behaviors and attitudes that push the day-to-day pursuits within the organization
(Hopkinson, 2017). While Reeves et al. (2018) found traits in the culture correlate with
success in each strategic approach, careful project development is essential for efficient
public investment in infrastructure. While all five participants shared the essential role of
risk management, organizations should build a culture that supports project risk
reporting. PT1A explained that project managers and team members are responsible for
developing effective risk plans and communicating the nature of the risk status with the
stakeholders. PT2B was very forceful in suggesting an alignment between the
organization's risk culture and risk management strategies, facilitating all stakeholders. A
robust risk management culture development positively impacts risk management when
used appropriately with project tools and techniques (Hillson & Murray-Webster, 2017;
PMI, 2017).
While proper implementation of project management processes is a critical
success factor, arguably, projects may find difficulties in achieving targets without
applying the PM tools and techniques (Hoxha, 2017). Similarly, observed from PT2B,
138
but better advocated by PT4C, "irrespective of how you start, each program should
inform the other.” Such practices allow the project team to track progress, minimize
project constraints, and deliver end user's satisfaction. For PT1A, a significant constraint
is the absence of a dedicated operational strategy and associated mechanisms to manage
and oversee projects.
Active management and investment ensure that they can serve as effective
frameworks to facilitate and channel coordinated and collective efforts against common
goals, according to PT1A. The implication from the analyzed data suggests the
applicability of the resource-based management (RBM) approach — a concept with its
origin in the 1950s, Peter Drucker's management by objectives (MBO). RBM focuses on
the outcome rather than the output, essential for project fulfillment. Like MBO, RBM
combines project goals with responsibilities to the organization's objectives, facilitating
strategic fit to maximize outcomes. Its adoption as a strategy allows for better results for
project governance, according to Otundo-Richard and Langat (2019). While public sector
project performance is successful with RBM in developed countries, it is comparatively a
novel concept (Olufemi, 2016). According to Otundo-Richard and Langat (2019), the
developed countries are better at public project service delivery; the reason identified was
the use of RBM. Still, PT2B opined that "project managers must focus on operational and
tactical issues within the project lifecycle stages.” In contrast, strategic planners,
including executives and project policymakers, must initiate forward-looking strategies.
Implicitly, it suggested that operational initiatives and goals are for project teams'
work plans. Similarly, Sharma (2016) found that the PBM approach to be a critical
139
integrative strategy. PT4C advocated a well-structured and adopted RBM strategy across
the project cycle to measure efficiencies. Unhindered globalization and its influence on
crowdsourcing and outsourcing, project practitioners are now required to tailor their
project management methodologies (PMI, 2017). Therefore, applying the best-
standardized processes will guide the project implementation and address the project's
parameters problems depending on the project outcomes, according to Kononenko and
Lutsenko (2018).
Alignment of Findings to Contingency Theory
Several researchers conformed to the central tenant of Fiedler's contingency
theory. Their ideas that open systems with external interactions (like construction
projects) can reach the same goal but from different initial positions that follow different
paths to fruition. The variabilities are because no one-size-fits-all approach would
provide a workable solution for project management (Maqbool et al., 2017; Miterev et
al., 2016). While Fiedler introduced the theory as a leadership effectiveness model, the
theory predicts higher management tools in organizations with goal clarity. Clear goals
with measured management processes and outcomes make it easier to apply the
management tools (George et al., 2019). Setting clear goals and managing each objective
is how PT4C explains project resource usage in each project phase, a workable approach
for managing by objective. In practice, the respondents were all comfortable with their
organization's management practice that supported the best fit for the project execution.
The government and the project executing team's management philosophy considered
the
140
challenges and risk perspectives. The contingency theory predicts higher management
tools in organizations with clear goals (George et al., 2019).
Maqbool et al., 2017 used the contingency theory to describe a class that indicates
outcomes contingent on factors' prevailing variabilities. A similar classification was also
affirmed from the analyzed data. While the participants explained the need for projects to
be adaptable based on the prevailing circumstances, contingency lends credence to their
project practices, the ‘best fit’ for leadership effectiveness. The observed flexibility by
the practitioners concerning their organization’s management practice is an essential
couture strategy aligned to incorporate with the contingency theory. The participants
shared stories of how open meetings received supportive feedback. For PT5D, the
flexible application works with a management practice that evaluates each situation as
unique to those conditions. Therefore, a leader's effectiveness may depend on the
prevailing circumstances resulting in two factors: leadership style and situational control,
as opined in Saunders et al. (2015). Leadership challenges remain those conditions that
require adjustments for external environmental factors. Again, PT5D opined, “I will
conduct regular meetings for feedback and reflect on working arrangements, the
performance of all implementors, and areas of improvement.” The contingency theory
advocates aligning external conditions to better assist leaders in increasing their overall
organizational performance (McAdam et al., 2019). The practitioners' PT4C and PT5D
justified project management experience, which adds value to a customized process with
better structure, flexibility, and a more inclusive approach for their projects' fulfillment.
The contingency theory provided alternatives that helped design the portfolio better and
141
better plan the information decision systems, especially for mega projects with
uncertainty and complexity. While projects' dynamism and required flexibility are based
on internal controllable variables (time scope and cost), the contingency approach
provides uncontrollable external environment variables.
Project success from the proposed business value is derived from the end-users
and measured from the process that created the benefit realized (Wysocki, 2019). The
analyzed data explains how project leaders need to exercise flexibility regarding project
leadership styles in their project management approaches. According to PT5D, flexibility
infers that project leaders must adopt management practices to accommodate the various
circumstances. Joslin and Müller (2016) describe them as project characteristics
consistent with the prevailing circumstances. Therefore, the challenges concerning the
project management plans and the choice of appropriate project management
methodology must be relative to the varying factors and circumstances that illustrate the
contingency theory's applicability.
Acknowledging the appropriate tools for managing construction and infrastructure
projects in complex environments, researchers explained the usefulness and how better
they are in assessing project success (Wali & Othman, 2019). To this end, numerous tools
were evident as proof of their use were cited by PT1A, PT2B, and PT3C. They displayed
several project dashboards with varying sensitivity analyses from anticipated external
variables, along with the associated risk probabilities. Matching charts with resource
allocation for project support were also perused, from which project continuity was
evident. The illustrations focused on maximizing project outcomes using those project
142
management tools. In practice, some questions are better answered pictorially; they
affirm how and why project practitioners used contingency planning to mitigate
challenges concerning uncertainties (Queiros et al., 2017). The contingency theory is
suitable for solving organizational choice differences, design megaproject management
strategies and processes regarding the differences in the project contexts, and changing
environmental conditions (Wysocki, 2019).
Theme 4: Managing Public Project Processes with Information Communication
Technology Tools
The use of ICT in project management allows for new management. Information
communication technology applications seek to replace the laborious and time-
consuming tasks associated with the traditional method. Information communication
technology offers substantial flexibility in organizing capital and resource facilitation to
rapidly transfer accurate information (Joslin & Müller, 2016). The flexibility allows for
faster decision-making for implementation, resulting in quality improvements and timely
project completion. One influential factor in achieving the project’s goals aligned with
project outcomes is technology. Balancing and integrating the relationships among these
elements can result in optimum project performance. Information communication
technology helps improve the ability to represent and analyze the increasing variety of
activities in projects. Everyday activities are increasingly carried out through digitally
mediated interactions of complex activities.
While ICT will work as an input factor, effective communication is a function of
the fed information (factor input); as such, there remains the potential for inaccurate
143
decision-making. Accordingly, PT2B established a strong communication plan in
collaboration with the aligned business strategies. Still, organization ‘B’ uses IT tools for
decision-making. PT3B from that organization opined, "I support business strategies with
enterprise resource planning (ERP) and electronic data interchange (EDI)." As more and
more organizations use technology to augment human skills, IT can help organizations
prioritize complex problem-solving procedures for continuous improvement (PMI 2021).
Technology is helpful in organizations' daily functions, and PT1A identified Microsoft
Project as applicable. In contrast, PT3B found useful ERP software programs that allow
data to communicate between the governments' departments and the project's internal
functions.
Organizations require clear communication with internal and external
stakeholders, so goals and objectives are understood among the parties (George et al.,
2019). Governments are now aligning their projects’ management with business strategy.
They have seen significant benefits concerning organizational goals, procedures, and
performance. While the new public service management model allows for business
management strategy application, its application in project management is growing.
According to Ferlie (2017), the new public service management model allows for
empowerment and active performance measurement, enticed by the contingency theory.
Those considered flexible organizations empower their people to make changes by
enabling them to master different working methods, becoming well-rounded
professionals with elevated power skills (PMI, 2021)
144
PT1A identified the stakeholders’ analysis and matrix as helpful tools in
designing and implementing solutions throughout the project management process
whenever conditions change. While plans may fail primarily because of inefficient stage
gate reviews, they lack the feedback necessary to detect significant threats. Accordingly,
P2B explained that public projects linked to business strategy might better accomplish
organizational goals. Shenhar's strategic project leadership (SPL) framework identifies
the project management elements that organizations should align with business strategy,
including (a) project strategy, (b) spirit, (c) organization, (d) project processes, and (e)
tools, all of which are synonymous with PT1A’s contention.
Contrastingly, PT3B advocated the balanced scorecard model, a performance
management system that balances the project's short and long-term business objectives. A
strategic management tool that evaluates financial and non-financial and internal and
external variables determine the organization's effectiveness and determine when
corrective actions are necessary. According to PT2B, the balanced scorecard was most
suitable because of its feedback mechanism concerning the internal business processes
and external outcomes and the continuous improvement of strategic performance and
results. ICT has provided projects with the tools and techniques to enhance mathematical
modeling for dashboard illustration of the Gantt chart, logic network, pert chart, product
breakdown structure (PBS). The critical path is an extension of the PRET approach of
algorithms for scheduling project activities. A project's required course represents the
most extended sequential project activities for completion. It determines the project's
145
total duration, milestones, deadlines, and necessary actions for timely completion as
practiced by PT1, PT3B, and PT4C.
Correlation With Recent Studies
ICT adoption has been considered from many different theoretical perspectives to
understand “why and how” organizations and people adopt ICT tools. One of the most
significant challenges in the traditional public sector is the time lag between inception,
implementation, and the possible outcomes. In consideration of the unpredictable nature
of today's complex environment, the contingency theory is applicable. According to
Joslin and Müller (2015), the contingency approach as a theoretical perspective was used
as a model to introduce a new project management methodology in project organizations
using ICT software. They were specifically for those organizations faced with
environmental contingency factors impacting the outcomes. Some organizations have
transitioned project management practice from traditional to Agile governance. PT1A
offered a practical example of applying changes aligned to the specific environmental
context that factored each software project organization similar to Joslin and Müller
(2015). Projects of various sizes and types must tailor their procedures to satisfy the
varying project sizes and types.
Although agile allows for a breakdown of risk into manageable chunks for rapid
iterative implementation, employees have found IT processes easily adaptable because of
the changing dynamism in the external environment (Haddad & Taleb, 2016). The
transitional process itself is affected by external and internal contingency factors. Their
analysis offered a more precise picture of the effects of changing project methodology
146
(Joslin & Müller 2015). Besides, a project's required course represents the most extended
sequential project activities for completion, determining the project's total duration,
milestones, deadlines, and necessary actions for timely completion. The critical path
analysis is an extension of the PERT approach of algorithms for scheduling project
activities.
Despite how the strategies are connected, the fundamental questions related to
“why and when” the strategies are needed. Besides, how to communicate through the IoT
technologies and “what” new values they can bring to enhance PM disciplines and
environments (Ghosh et al., 2018). The confluence of new technology such as the internet
of things (IoT), artificial intelligence (AI), and even disruptive technologies are tools for
adoption. Wu et al. (2018) considered the life cycle of mega infrastructure projects; they
emphasized the current developments and future directions of new models using
computational algorithms. While project challenges through globalization are akin to the
increasing role of complexity, AI and IoT advancement will provide new solutions, tools,
and support to project managers' implementation of PM disciplines within the changing
environments.
The re-engineering IT collaboration process aids in the transformation of project
outcomes (OECD, 2017b). Organizations must consider being flexible to empower their
people to make changes by enabling them to master different working methods and
become well-rounded professionals with elevated power skills (PMI, 2021). Chatman et
al. (2014) found that employees were generally willing to adapt to technological changes.
Similarly, PT4C opined that those specialized ICT tools had improved performance,
147
especially in stable and structured workplace culture. Participants PT4 C & PT2B
explained their project's smooth working processes and shared documentation supporting
their success. Culture shapes organizations' decisions and guides action, which drives
individual behavior. A lack of cultural awareness may restrict project managers' actions
based on their members' experiences, creating a unique organization's culture (PMI,
2017). PT2B spoke of team members being younger engineers who were very computer
savvy, illustrating their willingness to work with the new and emerging ICT changes.
Whatever the model, the emphasized focus must be on business problems and their
impact on success. According to PT4C, a typical mistake is to focus on the IT concepts
such as machine learning or linear regressions. Applying linear regression may predict
how the business will perform; such practice tools are acceptable technologies. The
focus, therefore, must remain on the underlying business challenges that need solving.
Similarly, PT2B advocated, like Waheed (2016), that project management recognition
comes from the authorized body- PMI, hence the need for PMBOK and its subsequent
editions.
The most ordinarily selected tool for the Waterfall model is the Gantt chart that
visualizes subtasks, dependencies, and project stages as it progresses through the project
life cycle. The participants underscored the application in practice from the interview,
and PT2B explained how agile project management technologies, e.g., Scrum, allow for
scope expansion as the project progresses. PT3B describes the agile approach as tailored
for the IT project environment. PT2B found applicable IT Infrastructure Library (ITIL) as
a practical framework for implementing project processes. For example, PT2B opined
148
that service requests and incident management provided data-driven decision-making that
efficiently operated with technology. In comparison, researchers found that seasoned
practitioners were effective with tools, techniques, and processes to align projects
successfully (Floricel et al., 2016): Rendering a timely and efficient project completion.
Early IT adoption presents agility for up-to-date feedback of what does as against
what does not. Throughout project implementation, the IT adoption is so that government
officials can quickly build upon successes and learn from the little challenges. PT1A
contended that documentation support must be accompanied by technical resources or
agile project management techniques with less comprehensive reporting requirements for
adoption. Employees with high self-efficacy perform better and are more persistent in
task completion, developed through information technology, a suitable tool for
adaptation amid complexities (OECD, 2017b). PT5D contended that IT provides sound
reinforcement through training. The training skills obtained are shown in employees with
high self-efficacy who perform better, are more persistent, and exert better task
completion, according to PT1A.
Alignment of Findings to Contingency Theory
The contingency theory explains organizational behavior based on contingent
factors – with the best potential fit connecting the organization, its environment, and the
diverse sub-systems. According to Joslin and Müller (2016), the best use of the
contingency approach is to correct low success rates by optimizing project planning and
control. Interestingly, a dated but seminal study found that some performance tools were
no longer entirely relevant. For example, in 25% of the examined projects, Khazanchi
149
(2005) found only three areas were held helpful throughout the project cycle:
communication, stakeholder management, and integration, all qualitative and behavioral.
Further, studies showed that organizations experience limitations in their PMMs,
whether in-house or off-the-shelf solutions. However, the organization’s business
strategy drives the PPM’s method, especially with innovation (Armenia et al., 2019;
Berggren, 2019). In applying the project management methodology (PPM), a partial
application can dictate the use of a subset of an already established PMM. While other
elements are not PPM-related, their application may suffice in achieving the desired
project outcomes amid uncertainty (Qazi et al., 2020). For PT1A, PRINCE2 and other
methodologies are regularly monitored by their respective governing mechanisms and
donor partners, supplemented by Agile-Scrum methodology when and where required.
According to PT1A, “The hybrid methodology allows for a flexible framework that can
readily be tailored to any project type or size, associated with the work environment, and
finalized within an agreed-on timeline.” Understanding the governance paradigm and
considering what may give rise to the evolution of the organization's PMM - may
provide insights to the program or project portfolio manager concerning the project
management skills, especially the experience required for a successful project outcome
(Joslin & Müller, 2016). Because projects are novel by definition, project managers must
tailor their project processes to accommodate the projects' outcomes for alignment with
organizational objectives.
The contingency approach advocates no single correct method of doing things;
instead, it decides the best solution, demanding a different approach for every exogenous
150
situation: Volatility, uncertainty, complexity, and ambiguity (VUCA) (Pace, 2019). Since
the best way to organize depends on the nature of the environment, the contingency
theory must demonstrate the management needs for project organizations. Standardized
and formalize management tools are considered more efficient, according to George et
al. (2019). Burns and Stalker (1961) brought attention to one crucial perspective of
standardization within organizations' need for clear goals. For PT3B, when goals are
clear in communication, they lead to calculable outcomes relative to those goals. In turn,
it presents easier use of the management tools geared toward goal formulation and
implementation. Accordingly, PT1A suggested developing a public website to map the
location and track the project progress, providing transparency and accountability in
promoting the results' visibility.
The contingency theory establishes an inherent linkage between projects (that are
unique and naturally unpredictable) and the contingency theory (advocates a unique
approach to conditions). While the participants' necessity of having a standardized
framework for projects arises, they agreed that the standard project structure requires the
deliverables to be well defined within the project cycle phase. For example, PT5 found
that having measurable outcomes in his project was related to a higher uptake of
performance measurement tools. According to Khazanchi (2005), the contingency
approach facilitates organizational performance through standardization and
formalization for efficiency and scale advantages using ICT tools. Besides, the chosen
framework should be flexible in sustaining the work with minimum bureaucracy. The
phrase “administrative delays” was used to illustrate the challenges of a bureaucratic
151
framework. PT2B opined that the process requires a match between the environmental
characteristics and those of the organization for project success. This match in the
contingency approach is called the “fit”; the better the fit, the higher the performance.
Therefore, a perfect and workable match is in the use of the contingency theory.
Applications to Professional Practice
Despite the adoption and application of modern project management
methodologies, techniques, and tools by public project leaders and practitioners for
project implementation, infrastructure and construction projects are still failing at an
alarming rate (Aljohani et al., 2017). The findings and recommendations conferred in this
study, berthed on the vast body of project management knowledge from experienced
practitioners, may become the strategic impetus for PSIP management. Public sector
practitioners, project executives, and policymakers can strengthen their project
management practices and policies, ultimately maximizing their project management
performance. Improved project management performance can also enable a higher level
of benefits realization through end users' satisfaction, measured against the improved
citizens' living standards. According to Kiehne et al. (2017), improved project
performance creates a competitive advantage that drives organizational business success.
Besides, successful project fulfillment may also lead to higher returns on investment -
measured in the end users' satisfaction for governments. The return on investment must
improve Calderon et al.'s 10% investment findings, which only yield one percentage on
the returned investment.
152
Trevor and Varcoe (2016) discussed a unique method for testing organizational
alignment. The researchers found two practical holistic perspectives - the strategic
support for the fulfillment of the organization's purpose, and the organization supports
the achievement of the business strategy. The plotted answers formed a matrix across the
four quadrants that posed a distinct leadership challenge—volatility, uncertainty,
complexity, and ambiguity (VUCA). In addition, the identified external variables have
been questionable in practice and rendered some of PMI's tools and techniques
problematic and, in some instances, inadequate, according to Cristóbal et al. (2018). The
focus is two-prong, managing the iron triangle deliverables and simultaneously aligning
the outcomes for societal benefits, representing a culture change for the government's
provision of public services. The strategy’s success may be achieved through effective
benefits identification, realization, and management by implementing or enhancing a
benefits realization program.
However, complementing the tools and techniques can blend the organization‘s
intent with the end users' maturing benefits realization (PMI, 2017). New technology and
advanced mathematical computation improved megaprojects construction, according to
Wu et al. (2018). As more devices, mathematical modeling, and information technology
become available, citizen satisfaction will improve from maturing benefit realization. In
addition, the appropriateness of the application will improve project fulfillment,
rendering a quick resolution to the anticipated problems concerning project alignment
with organizations' strategies (Joslin & Müller, 2016). While sufficient buy-in from
stakeholders, particularly the government, may maximize projects' outcomes. The buy-in
153
allows for preventative actions where necessary or remedial measures require
government executives to intervene and correct projects that stray from their intended
baselines during execution (Khan, Memon, & Ahmad, 2019).
In practice, a seemingly popular mapping tool is the balanced scorecard: A robust
control framework that measures performance from both a financial and non-financial
standpoint presenting a balanced view of the internal business processes, along with
financial and learning, coupled with customer satisfaction growth (Singh & Sethi, 2017).
The fundamental questions in project execution concern the projects' milestones and
deliverables and the expectation of their realization. What is needed is a management
system that can look backward and forward (with leading and lagging indicators). The
existing measurement indications of performance are not sufficient. Still, they must
predict tomorrow's performance by demonstrating how spending on strategic projects
today will improve future impact (Singh & Sethi, 2017). The Balanced Scorecard is the
closest management tool to suffice for that "crystal ball" approach.
Implications for Social Change
Organizational leaders can create positive social change from the shared value
that derives socio-economic benefits. While citizens generally do not thoroughly examine
their governments' fiscal expenditures, the result is that government gets a free pass on
their capital expenditure. Therefore, project misalignment will affect those other
businesses with strategies linked to completing the public project. A project may create
value when its satisfaction is derived socially and environmentally, bringing positive
social change by achieving allocative efficiency in a welfare sense to society (Santhosh
&
154
Baral, 2015). The community's influence will modify the project portfolio to enhance
living standards and cultural changes across those individuals' lives (Greenfield, 2018).
According to Stephan et al. (2016), positive social change is a transformational means of
developing society's well-being. The realization of its social impact is at the citizen user
experience of the public sector investment benefits. Information concerning the
government’s proposed investment with expected outcomes should be disclosed for
public scrutiny to improve transparency and accountability.
The positive social impact from effective strategy alignment can be attributed to
improved PSIP's organizational performance, hence, the communities' infrastructural
development and economic development. The enhanced project performance will
positively influence the growth in the country's GDP. The effect is that government
would see a reduction in wasteful expenditure of the taxpayers' money. In addition, the
success of public investments increases productivity in the other sectors with the
appropriate linked investments, supporting long-term economic growth with higher
benefit realization for citizens. The collective improvement in organizations contributes
to the national economy and enhances the country's GDP performance.
Given the unique challenges public investment faces, finding the balance for a
functional alignment relationship between government strategy and successful project
outcomes may provide new critical success factors for public sector investments. More
importantly, there are often competing interests with governments' strategy management
approach for resources at the national sectoral levels, hence the need to be prudent. The
social change may create a new project management model with implications through the
155
project management office. Such an office supports a unified project portfolio
management practice; attaining higher project maturity levels improve project success
rates in complex environments. According to Christoph and Spang (2014), the projects'
complexity determines the "ideal" level of maturity modeling.
Recommendations for Action
The findings of this study may serve well for those government ministries and
agencies whose project policymakers and project executives are involved in PSIPs. In
addition, project executives and managers encountering poor project infrastructure
execution would find these findings helpful in understanding likely gaps or deficiencies
in the system. The strategies to remedy challenges in public infrastructure project lies in
the governance mechanisms to gain project fulfillment. It requires the development of a
new and different project management path for improved project performance. From the
findings and conclusions, I propose the following recommendations.
An organized and phased approach will support linkages in significant
infrastructure investment through the government's quest for economic growth and
development. A scattergun approach to investment may result in expensive infrastructure
with few benefits. Holistically, the government should create an overall framework for its
capital investments, perhaps a national infrastructure strategy. The project cycle
management unit at the Ministry of Finance may become more active in coordinating
public investment in line with a national strategy. Besides, a national infrastructure
development (NDP) strategy will be helpful, which identifies the next stage in
infrastructure investment. A multi-year investment plan can form the primary tool for
156
determining the country's public investment. Monitoring the NDP's objectives will
require a dedicated information system that keeps track of the projects' lifecycle and
requires the use of performance-based budgeting (PBB). In comparison, PT3B suggested
the mechanism “aligning goals and subordinate objectives throughout the organization to
increase organizational performance.” Those initiatives will help the government’s
agencies identify and highlight policy changes required to encourage project fulfillment.
Projects’ success in the traditional sense is to achieve targets with planned
objectives, reviewed from the iron triangle (cost, time, and scope) and measured from the
project closeout report. However, those variables only account for 60% of a project's
success, according to Serrador and Turner (2015). The project's benefits are the
responsibility of the project managers. A recommendation is for managers to establish a
mechanism for managing these benefits through benefit registers, benefits realization
plans, KPIs, and lessons learned from the closeout reports. While PMI tools may pose
limitations, a helpful technique is to blend the tools with societal satisfaction, which helps
determine project maturity's benefits. In addition, practitioners must ensure adaptive
procedures for critical issues at the work breakdown structure level. The adaptive
procedures include reviewing the historical project data, lessons learned, and analysis of
the project environment using appropriate management analysis tools.
Public sector project managers should pay more attention to complexities,
especially those affecting megaprojects. As Böhle et al. found, a new way to deal with
uncertainty and complexity in projects. The researchers observed that it requires a
fundamental re-orientation of ICT tools in project management. A requirement that
157
allows project practitioners to adopt software tools that positively impact project
completion. While some of the projects' consultants and contractors might lack the scale
to invest in artificial intelligence (AI) or machine learning solutions, they can still sort
data by spreadsheets. The use of AI is an exciting prospect for megaprojects’
management, especially in the decision support management for "Big Data." Through
planning and delivery, project teams, quality, risk, and knowledge and resource
management, AI involvement in projects through planning and delivery may help predict
future outcomes (Ong & Uddin, 2020). As more devices and technologies become
available, the application's appropriateness will improve project fulfillment. Using project
management tools effectively offers ways to track progress and manage time for
successful projects. For example, project managers generally use a technique like the
PERT, whose method helps calculate the timeline throughout project scoping. The latest
tools and planning techniques, software, and risk management measures are excellent
recommendations.
The empirical literature on achieving alignment is developing; it can be described
in its current form as scanty (Zolfaghari et al., 2017). Therefore, organizations are
required to give more attention to strategically increasing these benefits from applying
ICT. While risk mitigation can significantly improve with ICT tools, technology-related
benefits have high driving power, with strategic benefits for the project team. According
to the respondents, the current approaches tend to be narrow. At the same time, the
general focus has been more technique as ICT has not always worked well in project
practice. The challenge suggests that the conventional system has done well for more
158
senior and seasoned practitioners, averse to formal project management methodology.
My recommendation is for the necessary application of IT training for project
practitioners using ICT tools.
Considering complexity and uncertainty with PMBOK techniques tailored to
public sector employers is instructive. The benefits of ICT adoption for infrastructure
project management requires a developed model to form an essential component of the
benefits management plan, leading to the strategic adoption of ICT. Boonstra and
Reezigt (2019) illustrated a practical use that derived benefits from a front-end
application. Their model allowed for identifying an objective approach that measures the
degree of complexity and predictability by assessing its internal and external context at
the front- end of operations. This recommended model may help project practitioners
understand and evaluate project designs based on a thorough pre-studied appraisal. The
recommendation is a practice that is more likely to succeed against a less systematic
analysis of reality. The general idea behind megaprojects implementations is geared
strategically towards sustainability and development, linking other sectors for citizens'
satisfaction. They must be successful in operational terms, achieved mostly when the
projects underwent up-front/ frontend external quality assurance (Volden & Samset,
2017).
An excellent recommendation for action is closing the project management
capacity gap for megaprojects before making such investment decisions. The level of
experience will ensure that the project practitioners possess the attitude that warrants
megaproject success. Again, training is helpful and mandatory. The prevailing view of
159
project management is morphing continually in response to the changing demands and
developing technology, which holds the future topography of project management.
Bridging the knowledge gap for the increasingly sophisticated applications of technology
will help to streamline current industry-standard procedures.
Business organizations tend to have more projects than program portfolios, and
projects are managed by an enterprise project management office (EPMO), according to
Hyväri (2016). In contrast, governments must recognize that they have a significant
number of programs. Therefore, like the business management model that uses EPMO,
governments can create program portfolios by establishing a program management office
(PMO). An organization's long-term directional changes should reflect the planning
strategy through a project planning office. Nevertheless, in a conducted PMI survey, less
than half of the organizations have EPMO's. Nevertheless, only 44% of those EPMOs
had aligned organizational strategies (PMI, 2016).
Even though projects are the basic building blocks of a country's infrastructural
development, they are often perceived as government processes and not functional. It
makes the project management/government strategy alignment even more difficult.
Effective strategic alignment provides checks and balances in each phase of the project
cycle. A recommendation is for the stage-gate approach similarly advocated by Volden
and Andersen (2018). A practical consideration is a hierarchical system that explains the
relationship between the PSIP using a three-stage model: The cabinet for policy direction,
the sectoral ministries to facilitate the policy, and the executing agency to deliver the
project, as per the findings of Volden and Andersen (2018).
160
The findings of Wang et al. (2018) provided practical recommendations for
strategic alignment. PMBOK aims to support project managers in their project objectives
by aligning them with the organization's strategic plans. PMBOK assumes that project
managers may identify patterns and generalizations throughout their projects (PMI,
2017). The assumption is not a stand-alone approach but one accompanied by a project
management office (PMO), as against what currently obtains - project execution units
(PEU) for individual projects. The PMO holds significant knowledge management that
may help align and focus on achieving its citizen's government vision. The PMO’s in
their centralized function operates at the strategic level as the intermediary between the
executive and the project management. By carefully considering its portfolio, the
effectiveness is measured by mapping a direct line back to the overall government
performance's success. Projects managed from a portfolio basis had 27% more successful
projects, while 42% fewer projects were without scope creep (PMI, 2017). While
portfolio management focuses on achieving organizational strategy objectives, measured
by the investment realization that benefits the end-users. Each project (component) of a
Portfolio must be viable, with clearly stated measurable benefits; they must be
quantifiable and linked to the government's objectives. With taxpayers frequently
demanding a reduction in wasteful spending, public investments expenditure is under
growing immense public scrutiny (PricewaterhouseCooper, 2017). It would help identify
and gather the projects that will yield the most valuable benefits for achieving project
outcomes according to the political objectives. The recommendation is to create a project
management office (PMO), the agency responsible for all programs and norms to develop
161
the project management principles for all public sector investments. The PMO will seek
to avoid an imbalance between all governmental programs, to establish a prioritization
system (strategic level) and the project management unit (strategic and tactical),
according to Hyväri (2016). Indeed, office development will help improve project
management maturity and project management culture in society.
In business practice, the consideration of international standardization is the ISO
standards, which support all businesses and their global coordination to avoid abuses.
Similarly, project management also has guidance in PMBOK 6th edition, among others,
for standardization in project management (Ferrell & Ferrell, 2016). The contingency
perspective helps achieve efficiency through formalization and standardization. It
efficiently maximizes projects ' outcomes when blended with the management tools
(George et al., 2019). While the more critical factor for the project's success is the
incompleteness of PMM concerning the project's efficiency and quality, project
managers would need to tailor project-specific methodologies (Joslin & Müller, 2015).
The strategic importance of resources and capacity for competitive advantages occurs
when the parties integrate into a structured approach. The recommendation, therefore, is
for the governments' project executing agencies to consider developing a full format or a
template for project scope development before project implementation. It starts with a
concept note that enables the creation of the project charter - a document that considers
the following details to include; (a) the justifications for the project, (b) the project
objectives, (c) time, cost, and schedule, (d) critical milestones with deliverables, (e)
acceptance criteria, (f) constraints, and assumptions, (g) potential issues or risks, and (h)
162
organizational requirements and resources. Project managers must continue seeking
personal development to maximize their project management skills and adapt alignment
strategies from the study findings'.
Over the years, professional institutions developed several project management
processes and procedures for application in various industries and project management
needs (Kononenko & Lutsenko, 2018). The recommendation would involve integrating
the project management processes into every stage of the project's process life cycle to
yield sustainable management practice. Such effort will allow the project life cycle's
efficiency to influence all the standard project management procedures concerning time,
cost, quality, and project risk against the external environment. Armenia et al. (2019)
identified five critical factors that help in the practice of project management
sustainability; an approach I will also recommend for project practitioners (a) corporate
policies and procedures, (b) resource management, (c) life cycle orientation, (d)
stakeholders' engagement, and (e) organizational learning.
Besides bilateral and multilateral financing, governments’ fiscal policy (taxation)
is the primary source of public investment. Empirically, the influence of quality and
efficiency in public investment spending concerning productivity and economic growth
was considered by Calderon et al. (2015). While the new public management model
forces public administrators to accept the responsibility of serving citizens by acting as
stewards of public resources embracing effective decision-making through
accountabilities enhances project success (Joslin & Müller, 2016). As a recommendation,
the anticipated increase in government revenue from the exploits of oil and gas should be
163
accompanied immediately by a comprehensive public investment plan aligned with the
other sectors' development. The uncertainty about COVID-19 has dampened private
investment; public investment can encourage investment plans that might otherwise be
postponed. Ascertaining linkages in the country’s development drive is the reason for the
recommendation.
Walden University's scholarly works will be the home for this study. It will
provide a mechanism that enables scholars and students interested in government
strategic alignment in project management practices to access the study findings.
Besides, I will share this study's results with the government (Ministries of Public Works
and Finance), the participants, project practitioners, and any other interested parties
through various means, including but not limited to publications, professional journals,
scholarly literature, seminars, conferences, and training programs.
Recommendations for Further Research
Advocates suggested reconsidering the research streams considering Morris'
management for project framework to adapt and maintain better alignment (Pinto &
Winch (2016). Researchers are now promoting the stage-gates approach to understand
better public project governance and strategy alignment (Volden & Andersen, 2018).
Further strides concerning alignment were evident in the autonomy phase of the project
lifecycle to the exclusion of the other two, cascading and autonomy (Zolfaghari et al.,
2019). Therefore, considering governments’ upfront roles in determining project
portfolios, the allocation phase is worthy of future research since it seeks to mitigate the
challenges of complexity and uncertainty. While my study provides a contemporary
164
approach to the alignment of government strategy with project outcomes, the findings,
along with Volden and Andersen's stage-gate practice, can be integrated to determine
higher benefits realization maturity in future research.
According to Khan, Memon, and Ahmad (2019), organizations with greater
maturity modeling could provide a roadmap to a higher maturity level. While the study
only accounted for four organizations, the lack of random selection in the chosen
participants may potentially pose validity issues due to possible selection bias. Future
researchers must consider a more countrywide comprehensive array of successful
projects delivered by broader perspectives and experienced project managers coupled
with varying and incremental government strategies. They will better explain public
investment projects' outcome alignment with government strategies.
Reflections
Although dated, I found exciting the seminal works of Adeyemi and Idoko
(2008). The researchers offered a perspective that accurately explains the dilemma faced
by developing countries concerning public infrastructure projects. The challenges were
all rooted within the iron triangle concept of time, scope, and budgetary allocation. To
date, those challenges have not subsided but instead compounded with external variables
of complexity and uncertainty, which continues the misalignments in stakeholders'
expectations (Khan, Memon, & Ahmad, 2019). While my study offers a fresh and
contemporary perspective of how strategic alignment can maximize project outcomes.
The realization is that project practitioners find tools and techniques used in management
to maximize project success, especially in complexity and uncertainty. The external
165
organizational environment has become more complex and needs other considerations
besides the "iron triangle" concept for project success. Those reflections are based on the
notion that governments generally take on multiple mega projects whenever they have
more fiscal space (GDP). The advent of Guyana's newfound oil and gas-energy sector has
created a more significant consideration for my curiosity, given its effect on an increasing
GDP.
While revenue growth positively correlates with citizens' pressure to improve
government services, those projects must also create linkages in the private sector. A
developed and supported private sector is quite impactful for a country's socio-economic
and environmental sustainability. I also realized that most project management
participants are foremost engineers, with some project management training (PMI
certified). The conducted study environment allowed the respondents to express
themselves freely, which enabled me to understand the strategies project managers use to
gain alignment. The study findings changed my personal biases and preconceived
thoughts and values of public project managers' approaches to aligning project outcomes
with governments' strategies to maximized project performance. I have gained knowledge
and understanding from the expert practitioners, and the interactions improved my
communication and interpersonal skills.
For those reasons, strategic alignment of projects and their evaluation and
selection process becomes more complicated, requiring more updated analytical and
managerial skills and models than those previously used. The findings provided an in-
depth understanding of the research question in developing multiple methods to align
166
project outcomes with government strategies to maximize project performance. On
reflection, the experience provided me a better understanding and appreciation of the
research process, which positively changed my personal biases and preconceived
opinions.
Conducting the doctoral pursuit, particularly the literature review, has improved
my understanding and knowledge of academic research work, critical thinking, problem-
solving approaches. Initially, I learned that students tend to overthink the APA style of
writing, leading to mental blocks (Van Note Chism & Weerakoon, 2012). Instead of
focusing on the style that can create a phobia, I found that early adoption provided
success. Besides, the APA publication manual spells out the requirements, which I
habitually followed to instill guidelines for scholarly writing.
Conclusion
The qualitative multiple case study explored effective strategies that public sector
project managers used to align the project outcomes with government strategies to
maximized project performance. The research method employed was a semistructured
interview. The five participants came from a specified population group of public sector
project managers who successfully aligned their projects' outcomes with government
strategies and worked for four project-based units within the geographic administrative
region of Demerara/Mahaica (Region 4) Guyana. Member checking, a qualitative
researcher's technique, enhanced data collection evidence that determined the study's data
validity and saturation (Saunders et al., 2015; Yin, 2018). Research has established that
167
an aligned project is one in which at least 80% of its expected outcomes were aligned
with the organization's strategy (PMI, 2017).
In addition to the contingency theory as the conceptual framework which helped
in understanding the context of the research and through the research question; four
themes emerged from the analyzed data on public project governance, concerning their
aligned outcomes with government strategies to maximized project performance: (a)
Government/ executive commitment and support for the project teams, (b) efficient
project management skills, (c) aligning national strategy with project processes, (d)
managing public project processes with ICT tools.
Additionally, using government strategies will incorporate feasibility analysis,
design, appraisal, approval, organization, operation, control, evaluation, and follow-up.
Throughout a project cycle, skilled managerial functions become the project managers'
thrust to realize the projects' outcomes align with government strategies to maximize
project success. Project managers may consider a register for risk lessons learned after
closing each risk management process phase. By doing so, future project managers would
gain more knowledge on what was successful or not.
The study's findings could conceivably add to public sector project practice and
may undoubtedly inspire social change. As government sectors compete for fiscal
expenditure, project management alignment can ensure purposefully measured public
spending- the gains from the investment return. Faced with continuous public scrutiny
enabled by digital technology- the government needs a clear mission to analyze their
portfolios to ensure aligned with their strategies. The PMOs pursue alignment and
168
maximized project success performance, creating end users’ benefits while improving
other citizen's support services that may boost governance.