Chapter 1: Introduction
1.1. General Introduction
To monitor the project is to compare the current with the planned situation, determining if the
costs and the schedule are progressing according to plan, in order to take corrective action when
needed. Any project with a considerable cost overrun and schedule delay typically gets in
trouble at its beginning as indicated by Alvarado (2004). In addition, project managers do not
realize this problem until late in the project when their ability to recover the project to achieve
its planned objectives diminishes.
EVM is the most used multi-dimensional project control method, as it integrates time
and cost (Rozeneset al., 2006). The Project Management Body of Knowledge (PMBOK)
defines control as “comparing actual performance with planned performance, analyzing
variances, assessing trends to effect process improvements, evaluating possible alternatives,
and recommending appropriate corrective action as needed.” (PMI, 2004, p. 355). In another
study evaluating the reliability of EVM conducted by Mahdi et al. in 2016, it was discovered
that among the EVMs assessed in the sample cluster, time schedules were identified as the
most influential. Additionally, the study noted that while quality also played a role, its impact
was not as substantial as the time schedule, yet still considered significant. Keeping under
budget and ahead of time schedule are key measures for project success. The executed work
compared with planned work is considered a work performance indicator, also the cost spent
compared with the cost remaining can be taken into consideration as a work performance
indicator. DE Marco et Timur, (2013) stated that indicators are essential management tools in
monitoring and evaluating project activities, as they allow the achievement of goals to be
monitored as well as advances and improvements in quality to be identified.
The EVM method has been used for numerous projects during the past 40 years (Lipke,
2008). This method had a favorable impact on various aspects associated with project
outcomes, including but not limited to enhanced planning, risk evaluation, monitoring,
reporting, and controlling. Nevertheless, few researchers have shown some studies regarding
the analysis and evaluation of time and cost performance stability while taking into account the
quality of work. Despite the fact that EVM has been employed by numerous companies for
over 35 years as a means to forecast time and cost outcomes, numerous studies, including
(Lipke et al, 2009), have identified weaknesses in its effectiveness.
The evaluation of project performance involves analysing earned value indicators
related to cost, schedule, and scope. These aspects, are known as the iron triangle as recognized
by the Project Management Institute (PMI), are crucial for ensuring project efficiency (Project
Management Institute, 2017). To derive the earned value indicator, it is imperative to quantify
activities in terms of cost and establish completion dates for each task. As highlighted by
Vargas (2003), the EVM technique intricately links cost, schedule, and scope in project
management.
1.2. Problem Statement
Since the development of EVM, the implementation of this approach is yet questioned in the
construction industry in Egypt and potential improvements are yet on the verge. There are
various studies in the literature review that discussed the potential limitations of EVM and the
urgency of further investigation to enhance the process and outcomes of using EVM in the
project (Mahdi et al., 2018). Some of the limitations were the complexity of the process, lack
of sufficient accuracy, and the process is classified to be time-consuming (CanCandido et al.,
2014). Therefore, with the current advancement in the tools and technology used in the
construction sector, there is a prospective opportunity to invent well controlled EVM approach
that can improve the overall management of the project regardless of its circumstances and
challenges.
Luis Felipe Cândido et al. (2014) investigated conceptual problems and implementation
difficulties associated with EVM. Through a case study on a construction project utilizing
EVM for planning and control, they identified four major issues. The EVM approach, they
found, falls short in supporting lean construction applications. Two notable problems include
the neglect of the mobilization of resources phase and the absence of consideration for
construction indirect costs. In their conclusion, the researchers asserted that EVM merely
extends the traditional approach of measuring physical and financial progress over time. This
narrow approach is insufficient to provide a comprehensive managerial tool, as became clear
through the analyses of the building project under consideration. The main advantage of this
technique is its relative simplicity and that it only requires the kind of information (activity
percentages of completion and actual costs mostly) that is gathered for other purposes during
the project execution. The biggest disadvantage, which has apparently remained out-of-sight
for most practitioners and researchers alike is that EVM is a technique that measures ‘amount
of work performed’, not time deviations.
Put it in simple words, EVM measures the differences between earned value (EV) and
planned value (PV) (for time deviations) or between EV and actual cost (AC) (for cost
deviations). If EV is greater that either PV or AC, the project is doing well in time or cost,
respectively. But EV increases as more activities are finished, irrespective of whether the order
of execution was the most appropriate. The reasonable question then is: are the activities being
finished so far, the ones that will lead to achieving the project duration we planned originally?
EVM cannot tell. Indeed, if we deviate significantly from the project schedule, complementary
indices like the p-factor (Lipke 2004), which measure schedule adherence, inform us about the
risk of rework but they still fail to anticipate what (negative) time deviations can be expected.
EVM is therefore, a technique that works perfectly in the cost dimension (Ballesteros-
Pérez et al. 2015, Ballesteros-Pérez et al. 2016), as all activities contribute to the total project
cost according to their respective budgets. But that is not the case for time deviations. Activities
need to happen in specific order to achieve a particular duration. According to Fleming and
Koppelman (2010), EVM techniques are difficult to be applied to dynamic construction
projects and do not add much value to project execution, especially when: 1) There is absence
of adequate project planning and documentation, 2). The construction schedule is compounded
by considering the resource constraints such as resource availability limits and multiple
calendars, iii. Activity and project delays encountered during project executions, iv. There is
no EVM analyst or specialist within the project team. Some problems that may impede the
implementation of EVM as specified by Kim et al. (2003) such as: - High cost, complicated
and burdensome paperwork - Poor understanding of EVM - Distrust and conflict between
project managers, project consulting and government -Pressures to report only good news.
The critical need for effective earned value techniques in the construction industry,
specifically focusing on project forecasting accuracy across diverse construction projects in
Egypt Furthermore, the variation in the most accurate technique based on project type and
duration introduces complexity in selecting the optimal method. Renovation and residential
projects favor the Earned Schedule method, while industrial, commercial, and educational
projects consistently lean towards the Earned Duration method. This inconsistency prompts the
need to identify a systematic approach for method selection tailored to specific project
characteristics.
In essence, the problem revolves around reconciling the overall effectiveness of the
Earned Duration method with the nuanced performance variations under different performance
factors and project types. The challenge is to provide a comprehensive and applicable
framework that assists project managers in selecting the most efficient earned value technique
for precise project forecasting, considering the unique characteristics of each construction
project in the Egyptian context.
1.3. Research Goal and Objectives
The goal of this research is to enhance the application and accuracy of earned value techniques
in Egyptian construction projects through a comprehensive evaluation of Earned Duration,
Earned Schedule, and Planned Value methods. The research seeks to understand variations in
technique accuracy based on project type, particularly focusing on preferences for specific
methods in different project categories. Key goals include developing a systematic approach
for selecting the most accurate technique, assessing and refining practical guidelines for
decision-making, and exploring the impact of performance factors like SPI and CPI.
Ultimately, this will promote the adoption of earned value techniques for improved project
forecasting in the Egyptian construction sector.
The objectives of this research are the following:
1. Evaluate the effectiveness of earned value techniques in forecasting project completion dates
across diverse construction projects in Egypt.
2. Investigate the variations in the accuracy of earned value techniques based on project type
and duration, specifically examining the preference for the Earned Schedule method in
renovation and residential projects and the consistent preference for the Earned Duration
method in industrial, commercial, and educational projects.
3. Develop a systematic approach for selecting the most accurate earned value technique
tailored to specific project characteristics, aiming to address the complexity introduced by the
varying preferences for techniques across different project types.
4. Assess the practical guidelines introduced in the thesis for choosing the most efficient
technique based on project duration percentages.
5. Examine the interplay of performance factors, including Schedule Performance Index (SPI)
and Cost Performance Index (CPI) for different project types, to gain a more nuanced
understanding of their impact on the accuracy of earned value techniques.
6. Develop a comprehensive and applicable framework that reconciles the overall effectiveness
of the Earned Duration method with nuanced performance variations under different
performance factors and project types, aiming to provide practical guidance for project
managers in the Egyptian construction context.
1.4. Research methodology
The proposed methodology of this research will rely on a methodology that involves
quantitative data analysis. The first step involves reviewing different techniques to measure
earned value management. These different techniques will be reviewed comprehensively in the
literature part. A comparison between the different techniques will take place in order to
differentiate between each of these techniques in addition to highlighting their major
differences. These techniques will be applied on numerous construction projects in Egypt in
order to evaluate their efficiency based on different factors such as project type, total price,
project duration and deviations between planned and actual cost and time. Analysis of the
accuracy of these techniques will take place to determine which of these techniques fits and
give more accurate results. In order to define the accuracy of each method, a numerical analysis
will be conducted as a quantitative approach. Finally, based on the findings of the analysis, a
model will be established to estimate the forecasted finish date. Details of the research
methodology are described in Chapter 3, in addition figure one below illustrates the sequence
of the research methodology.
Figure 1 Research Methodology steps
1.5. Expected significance of the research
The research is anticipated to significantly contribute to the construction industry by enhancing
project forecasting accuracy. The identification of the most effective earned value techniques
for different project types and durations, as highlighted in the thesis, is expected to provide
project managers with valuable insights to improve the precision of their forecasts.
The research's emphasis on tailoring the choice of earned value techniques to specific
project characteristics is expected to be a valuable contribution. This tailored approach is
anticipated to empower project managers to make informed decisions based on the unique
requirements and dynamics of each construction project, fostering more efficient project
management practices.
The practical guidelines introduced in the thesis for choosing the most efficient technique based
on project duration percentages are expected to provide clarity in decision-making. Moreover,
the research's nuanced understanding of the interplay of performance factors, including SPI
and SCI, is anticipated to offer practical insights, enabling project managers to navigate
complexities and optimize forecasting accuracy, with a special focus within the Egyptian
market.
1.6. Thesis Organization
This document is organized into six chapters, each serving a distinct purpose in the
exploration and analysis of EVM in construction projects.
Chapter 1 provides a comprehensive overview, starting with a general introduction to
the research topic. It includes a clear statement of the problem, articulation of the research goals
and objectives, an explanation of the chosen research methodology, and an overview of the
expected significance of the study.
The second chapter is dedicated to the literature review, offering a thorough
examination of background information on the subject, an exploration of various EVM
methods, and a review of relevant previous studies. This chapter serves to establish the context
for the current research and identify gaps in existing knowledge.
Chapter three details the research methodology employed in this study. It outlines the
chosen data collection methods and elucidates the data analysis techniques applied to scrutinize
the collected information. This chapter serves as a roadmap for the systematic execution of the
research.
The fourth chapter delves into the specifics of data collection, providing detailed
information about the projects selected for analysis. This section offers insights into the
variables, parameters, and scope of the data collected for the study.
Chapter five is dedicated to the analysis of the collected data. It presents the outcomes
of the analysis, providing a comprehensive understanding of the research findings.
The chapter six concludes with a summarization of the key insights and implications
drawn from the analysis, marking the end of the research journey.
Chapter 2: Literature Review
2.1. Background
The failure of construction projects in meeting cost and schedule requirement has forced project
managers to find any opportunity to invoke their learning and understand the causes of failure
for future projects (Hughes et al, 2017). In an effort to enhance project management success
rates, EVM has been developed as a tool that managers can utilize to aid in the attainment of
desired client deliverables. EVM has been in existence for some time, and its effective
implementation in projects remains a persistent challenge.
EVM is a project management technique used for improving the rate of success of
construction projects (Aramali et al, 2022). EVM stands as the most extensive approach for
overseeing and managing a project's cost and schedule performance by unifying the project's
scope, budget, and timeframe (Dube, 2018). There are many other sectors that are using the
methodology of EVM such as software industry, space industry, military applications, and
energy sector, and this application still improving and developing widely. Company managers
continually strive to minimize costs in the manufacturing and production processes, a task that
significantly influences their financial management (Villafanez et al., 2020).
The history of EVM dates back to many decades ago and after the second world war.
The critical path method (CPM) was introduced in the 1950s as a technique for assessing and
enhancing performance. The US navy then invented the idea of using project evaluation review
known as (PERT). PERT was established in a manner akin to CPM, and it served as a precursor
to the development of EVM. After that, in 1960’s the US government invented the idea of
EVM to be used in their projects and measure their performance (Nevison and Chichakly,
2021). The establishment of the Project Management Institute in 1969 marked the initial
significant milestone in the evolution of project management into a recognized profession
(Kabeyi, 2019). The inception of project management functions enabled managers to discover
practical solutions to project limitations.
EVM does not exclusively concentrate on the critical tasks of the project. It can involve
all types of tasks (i.e., non-critical tasks, and critical tasks), whilst the critical path of the project
is still considered essential to estimate the total time required to complete the project. The
critical path comprises a continuous sequence of activities with no slack, and these activities
are referred to as critical tasks. This indicates that controlling and monitoring the schedule of
work in the project can concentrate on these main tasks as no delay can be allowed because
any delay in these critical tasks can lead to the overall project delay (Corovic, 2022). Many
tasks are allowed to finish late during the execution of the project. Nonetheless, the traditional
earned value method would fail to detect these delays, and the schedule management indicators
would indicate an ideal value even following the postponed task (Schedule performance index
of one, or schedule variance of), which might not be the case (Corovic, 2022). EVM is helpful
in accurately estimating savings and cost overruns in the execution of construction projects.
Nevertheless, employing this approach for overseeing and managing schedule deviations is
insufficient.
The utilization of EVM across all project levels enhances the likelihood of success by
granting project managers the flexibility to make necessary adjustments for achieving success.
EVM can be a short-term method that helps the project manager to measure and control the
performance of the project after the inception stage and report anything related to the time and
cost of the project (Mogaji, 2019). Earned Value Management Systems (EVMS) equip the
project management team with software, procedures, instruments, and project templates to
enhance project success rates. EVMS is an EVMS that aligns with the EIA-748 EVMS
guidelines.
EVM tries to combine three correlated element of project performance, these are the
cost, schedule, and scope (Geneste, 2019). The assessment method known as earned value
analysis (EVA) empowers the project manager to employ a quantitative approach to gain a
deeper insight into project performance. This is achieved by calculating schedule and cost
variances throughout the project's duration. When the project manager finishes around 20% of
the project, the rest of the performance may result in an estimation of around 10% plus or minus
any variation. Project managers can utilize the information provided by EVM for trend analysis
and forecasting, making it a valuable tool for cost control measures. With its robust predictive
capabilities, EVM offers project managers an effective approach to project management.
Project managers can gain many benefits and advantages of utilizing EVM in their
project management methods and to be used for measuring and evaluating the performance of
their projects. EVM can provide stakeholders with transparent metrics, visibility, and clearly
defined accountability. This technique can be excellent for managers in offering an
unobstructed understanding of the project with an overall view of its performance starting from
the inception stage and can still be effective and efficient with many project stages and at all
levels. The procedure enables the project manager to take action proactively, making
adjustments to the project scope and budgets, seeking additional resources, and managing
customer expectations, all before a crisis arises. A database can be developed by project
managers to help in taking many actions and assist in various aspects in the project including
proper decision making for projects in the future and align their progress and work with
unknown risks to be reduced in future projects and ensure the prevention of any cost overrun
especially from risks that were considered critical in the past and had severe impact.
Furthermore, and of utmost significance, managers can employ the tool to conduct a
comparison and establish benchmarks for the current project status when compared to the
project's initial baseline. Additionally, they can pinpoint the critical path. Mogaji (2019)
indicated that a basic technique of EVM in a construction project can help project managers
with an adequate and accurate estimation and forecasting of around 20% of completed works
in the project. There are many quantitative equations and formulas that are currently available
to improve the performance of construction projects.
2.3. Earned Value Management
The traditional approach of managing changes in the project involves comparing the gap
between the actual variable value and the planned value. As an illustration, it is possible to
analyze the real accumulated project costs in comparison to the initial projected project costs
to identify variances in the project's expenditure (Buestan et al, 2018). Nonetheless, this
examination is partial because it's possible to have expended 90% of the budget while only
completing 50% of the project. The traditional cost analysis techniques do not determine the
status of the project and whether it is being performed properly, since the information about
the execution of the project is not available (Buestan et al, 2018).
In the traditional approach, a couple of variables are compared with each other; the
budgeted cost of the planned activities, known as the planned value (PV), and the actual real
cost of the performed activities known as (AC) (Aramali et al, 2021). The planned value (PV)
is linked to and symbolizes the project schedule in monetary terms, while the actual value (AC)
is tied to the actual cost of the project in monetary units. This comparison neglects completely
the scope of work which can be the third variable in the equation and a major constraint in
construction projects (Aramali et al, 2021). This is accomplished by means of the earned value
(EV) or the cost of work performed as budgeted, both of which are related to the project's scope
variable in terms of monetary units (Aramali et al, 2021).
The concept of earned value is generated from the idea that every delivered project has
a budgeted cost known as the value. When the cost of the project is well delivered, it indicates
that the value is well earned. EVM integrates the three pertinent project baseline factors: scope,
timetable, and financial plan (Zahoor et al, 2022). It is important to calculate many factors
such as the earned value correlated with the scope of work in monetary units, the planned value
correlated with schedule of work in monetary units, and lastly the actual cost of work in the
project again in monetary units (Zahoor et al, 2022).
The budget cost at completion indicates the baseline cost for the project and the initial
budget required in order to plan the performed work on site. It can be represented on the S
curve of the project accumulating the expected cost of each task during the whole life cycle of
the project. It signifies the anticipated value of all tasks and activities that are scheduled to be
finished (Mayo-Alvarez et al, 2022). The budget cost at completion (BAC) can be calculated
through the planned value as shown in equation 1:
𝑃𝑉 = 𝐵𝐴𝐶 ∗ 𝑃𝑊
Equation 1 planned value (Mayo-Alvarez et al, 2022).
Where:
PV: Planned value
BAC: budget cost at completion
PW: planned work percentage
The other major variable in the EVM is the earned value (EV), which refers to the budgeted
cost for the performed work It represents the projected cost, based on the budget, to complete
the work that has been executed within the specified timeframe, rather than the actual cost. It
helps in understanding the work performed until a specific date and the budgeted value, it can
be calculated through equation two.
EV = BAC × WD
Equation 2 Earned Value (Mayo-Alvarez et al, 2022).
Where:
EV: Earned value
BAC: budget cost at completion
WD: work done percentage.
The actual cost is the incurred budget that was used for the performed work until a certain
date (Mayo-Alvarez et al, 2022). This is the real-time cost of the work, encompassing both
direct and indirect expenses. It provides insight into the total cost incurred for the work
completed thus far. Its value is calculated as the sum of (quantities completed multiplied by the
actual purchase price) (Mayo-Alvarez et al, 2022).
EVM is very valuable when used to compare the cost gaps of the project using cost
performance index and cost variance indicators. These indicators can demonstrate if the project
is suffering from cost overrun or achieving cost savings. The standard variance can be used to
estimate the measurement of deviations in the schedule of work in the project and help in
indicating the delay or project overruns (PMI, 2011). Figure 1 depicts the three curves related
to PV (Planned Value), EV (Earned Value), and AC (Actual Cost), along with the cost and
schedule variances measured in monetary units. Employing this method to monitor project
schedule deviations may not effectively handle various project scenarios and does not utilize
time units to report project progress or delays (PMI, 2011).
Figure 2: Earned Value Management: The three curves and cost and schedule variations (Mayo-
Alvarez et al, 2022)
2.3.1. Earned Schedule
The earned schedule is basically the actual progress of work in the project valued or represented
in time units (Lipke, 2012). The commonality between earned schedule and earned value is
that they both utilize actual progress as their initial reference point (Kapuganti et al, 2019). The
major variation between them lies in how expressing and showing the actual progress on site.
Nevertheless, earned programming demonstrates the actual progress of work in the project in
time unites, while the earned value demonstrates the actual progress in monetary figures
(Henderson, 2005). The earned schedule method produces metrics that accurately gauge the
project schedule's status throughout its entire life cycle. This approach enables the assessment
of project progress or delays in terms of "time" units and effectively identifies and quantifies
delays in activities that have been completed behind schedule (Henderson, 2005). Therefore,
earned schedule helps to reduce two major limitations faced when using EVM as a method of
project control (Henderson, 2005). The next figure indicates the earned schedule basic
definition, where the earned schedule value is accomplished when the earned value on the
control date is the same as the planned value in 9 months.
Figure 3: Basic illustration of the idea of earned schedule (Mayo-Alvarez et al, 2022)
The earned schedule is similar to the EVM in the case of plotting S curve as a
representation and a reference for the schedule variation, but it does not differentiate between
the non-critical activities and the critical ones (Capone and Narbaev, 2021). This particular
aspect renders the accuracy of schedule variance measurement questionable because it suggests
that only critical path tasks should be taken into account when overseeing the project's timeline
(Capone and Narbaev, 2021). Therefore, the critical path earned scheduling (ESRC) was
developed to integrate the idea of earned schedule and critical path of the project and overcome
the limitation of the original concept. To achieve this, it is essential to establish and utilize the
S curve specifically for critical tasks as a benchmark to estimate schedule deviations (Capone
and Narbaev, 2021).
2.4. Previous Studies
Bhosekar and Vyas (2012) studied the cost control of construction projects using EVM. The
study concentrated more on the real estate sector. The study delved into the significance of the
EVM tool, explored its fundamental formula along with performance indicators, and applied it
to a case study involving a residential building covering an area of 120 square meters. This
case study was used to conduct EVM analysis, tracking both time and cost indicators. To
compare EVM analysis with software like MSP, P6, and SQL, the author compared multiple
project management tools. Additionally, the paper concludes with a comparative analysis of
EVM Analysis in contrast to various other management tools.
Virle et al (2013) discussed the implementation of both EVM and Earned Schedule
(ES) in construction projects. In this study, the researcher explored the utilization of EVM in
the construction sector, discussed the elements of EVM, and outlined the various parameters
impacting the significance of ES and EVM.
Gaddam and Landage (2022) reviewed the utilization of earned schedule and EVM for
construction projects. Project success is heavily reliant on achieving the anticipated cost and
time of construction projects. Public and private sectors have a long history regarding the
inability of completing projects on time and cost. Earned schedule and value management are
two methodologies used in project management for organizing and monitoring the progress of
work in the project. These methods are extremely useful in comparing the actual cost of work
and the budgeted one while considering the analysis of schedule delays. EVM is quite efficient
method for controlling and evaluating construction projects. It can be used by stakeholders,
project managers, and most parties to visualize the progress of the project during its entire life
cycle and allow the team to properly manage the project. On the other hand, earned schedule
is more about the practical knowledge that builds the idea of EVM. It is now considered the
newer extension to the concept of EVM. To enhance the control and evaluation of schedule of
work and performance during the life cycle of the project, earned schedule allows EVM to
convert its outcomes into time metrices. Project manger’s performance can be comprehensively
improved with earned schedule by forecasting and making better decisions in the project. The
aim of this research was to apply the concepts of earned schedule management and EVM to a
flyover infrastructure construction project in India to evaluate cost overrun and time delay. The
results were then compared with the outcomes of using MSP software predictions. Study’s
findings demonstrated the ability to use ES and EVM to monitor and control the time and cost
of infrastructure projects efficiently and accurately. It can aid in predicting early warning of
variances in the time and cost using ESM and EVM parameters during the whole life cycle of
the project.
Suresh and Ganapathy (2015) showed a study regarding the implementation of earned
value analysis for evaluating project performance. The study addressed earned value analysis
for examining the performance of construction projects. EVM offers the ability to understand
the cost of construction projects and the impact of the performance, risks, and scope of work
on the cost of projects. It motivates the management team to maintain a keen focus on cost,
time, and progress, thereby facilitating smoother project execution. On the other hand, Chavan
and Bhamre (2015) studied the ability to efficiently plan and schedule residential projects while
conducting a delay analysis. The research focused on many aspects including manpower
organizing, project planning, manpower management, project scheduling, project scheduling
steps, delay analysis, manpower planning, introduction to scheduling, planning steps,
introduction to planning, and other related information. Furthermore, a case study of a
residential unit project was illustrated through the use of MS Project and MS Excel software.
The study concluded with main points regarding the master schedule, planning of activities,
and other topics. The main causes of delay in the project were weather conditions, lack of
skilled labours, improper planning, poor organization, shortage of materials, and shortage of
labours. Therefore, this study indicated the importance of proper planning for the success of
construction projects and avoiding any time spent waiting.
Yvas (2016) tracked the progress of construction projects using EVM. The goal evolved
around demonstrating the efficiency and role of EVM for project tracking and its superiority
over the traditional approaches. EVM can be crucial for cost and delay analysis of construction
projects as proven in this study and agreed by many studies in the literature. Hence, it concluded
with the main benefits of using EVM in the construction industry and project management.
Mayo-Alvarez et al (2022) conducted an AHP systematic analysis of EVM techniques
that are used to control and monitor the performance of construction projects. Successful
management of projects relies on accomplishing the expected objectives. In these goals,
technical achievement is linked to meeting the project's baseline expectations. The project’s
baseline defines lots of information about the project such as the total cost on the S curve, time
of activities, and the work breakdown structure. In simple terms, the project is considered
technically successful when it can deliver its entire scope according to the established schedule
and without incurring additional costs. The baseline performance management helps project
managers to control and monitor the process of activities, costs, durations, and deliverables in
the project. In a conventional method, for projects following a waterfall approach and utilizing
the critical path concept, the primary tool for managing baseline performance effectively is
EVM (EVM). In practice, EVM is well effective for controlling the cost of construction
projects, nevertheless, implementing this technique to estimate the schedule status is usually
inconsistent and not effective. During the past few decades, various changes of the original
concept of EVM have been introduced to overcome this inconsistency when it is applied to
determine and measure the status of project’s schedule and timeline. There are many variations
under the original concept of EVM such as critical path earned schedule, critical path earned
value, the earned schedule, the work in progress earned value, and the critical path earned value
and the work progress combined. Every one of these suggestions aims to rectify certain
shortcomings in the conventional approach of EVM when it comes to time tracking and control.
For instance, they emphasize the importance of focusing on critical tasks for monitoring
schedule progress, addressing the issue of delayed task recognition, reporting schedule
variances in terms of time units, and measuring compliance with the project's schedule (referred
to as the "P factor"). Given the challenging circumstances, it's imperative to identify the most
suitable alternative from various versions of the original earned value method for effective
project schedule management. This selection process involves considering multiple evaluation
criteria. In this research, we conduct a systematic review and comparison of EVM (EVM) and
its variants as tools for assessing project baseline schedule performance. To determine the most
appropriate methods for schedule monitoring and control, we employ the Analytic Hierarchy
Process (AHP) and evaluate five key criteria: focus on schedule variation in critical tasks, the
ability to recognize and measure task delays, reporting schedule variances in time units,
measuring schedule adherence (P factor), and the presence of software support and
development. The outcome of the AHP analysis, when comparing these methods, reveals that
the critical path earned schedule method is the most effective for monitoring and controlling
project baseline schedules. It consistently performs well across all evaluated categories when
compared to other methods.
Araszkiewicz and Bochenek (2019) presented a study about the use of earned value
method for controlling construction projects through a case study. Effective execution of
construction projects relies on essential management functions, which include planning,
control, and progress monitoring. Scheduling and budgeting in the form of cost estimation are
two functions and instruments that are used to control the performance of construction projects.
These are established during the initial planning phase to oversee and manage deviations in
both cost and time. Furthermore, common monitoring methods include milestone observation
and comparative analysis of actual costs against the planned costs. This study presented the use
of EVM as a progress control method to demonstrate its usage in the construction industry and
its major benefits although its not commonly used by many projects. The study examines how
the outcomes achieved during the monitoring and control phase are influenced by the planning
phase when employing EVM. This case study offers real-world illustrations of EVM
application in construction project execution, including the utilization of computer software.
The novelty of the study was about introducing an extra sensitivity analysis showing the
influence of other factors such as delay in delivery of materials or increase in projects costs
while illustrating the impact on deviation curves. Employing sensitivity analysis in conjunction
with the outcomes of CPI and SPI calculations allows for the integration of cost and time
control with the monitoring of project risks. The results demonstrate notable advantages
associated with the adoption of EVM for the execution of construction projects, while also
underscoring certain noteworthy limitations.
Otuyemi (2017) discussed the potential use of EVM in the construction sector in the
UK as a trend tool. In this paper, the application of EVM as an analytical instrument in the
construction industry was examined. The primary goal was to demonstrate how EVM is
implemented in previous projects and measure its influence on the success rate of construction
projects. In this paper, we aimed to assess the utilization of this project management method
through the examination of three case studies that demonstrate its practical implementation.
These case studies are supported by reports, graphs, analyses, and commentary. EVM's role in
contributing to the success of these case studies is evident through its ability to identify key
issues and provide solutions that ultimately lead to on-time and on-budget project completion.
In summary, the paper outlines how EVM has demonstrated its value to the construction sector
by providing a clearer project perspective. It accomplishes this by presenting the project's status
in terms of cost and time and by offering forecasts for project completion.
In conclusion, the studies presented provide valuable insights into the application and
effectiveness of EVM in the construction industry and underscore the importance of EVM as
a valuable tool for project management in the construction industry, offering insights into cost
control, progress monitoring, and efficient decision-making.
The subsequent chapter is research methodology which will delve into the approaches,
tools, and techniques employed to gather, analyze, and interpret data, providing a
methodological framework to further enhance our understanding of the dynamics of EVM
implementation in construction contexts. As we move forward, the research methodology
chapter aims to bridge theoretical knowledge with practical application, contributing to a
holistic comprehension of the role of EVM in optimizing project outcomes.
Chapter 3: Research Methodology
This chapter outlines design and approach used to answer all research questions and achieve
the research objective. Selecting the right form of a methodology is extremely important to
ensure the reliability, validity, and rigor of data collection and analysis to achieve all research
objectives. The major goal of this chapter is to thoroughly present the methodological approach
that helped the researcher in understanding the research methods of data collection and
evaluation.
3.1. Research Design
There are many approaches that are used in scientific studies for data collection. The most
commonly used ones are qualitative approach, quantitative approach, and mixed methods
approach. Quantitative methods are used to gather statistical data that measures broad figures
using numerical information. On the other hand, qualitative methods are more suitable in
gathering the broad perspective of individuals and to be able to investigate deep thoughts and
ideas which cannot be done through a survey. There are many studies that combine both
qualitative and quantitative methods to form an approach known as mixed methods. Selecting
the best design relies heavily on the context of the study, research aims and objectives, and the
questions that are expected to be answered in the study. This study considered the adoption of
a quantitative approach. This approach was selected due to its ability to comprehensively
collect and analyse the required data for the context and phenomenon of this research. The
quantitative aspects are useful for providing a broad understanding and perspective, which is
different than the qualitative approach that only considers the theoretical explanation of
complex contexts that requires deeper understanding of the problem. The goal of the study
seeks to offer a holistic and nuanced viewpoint of the context that is being investigated in this
research. EVM can be applied in many ways in the project and this study aimed at exploring
the various methods under EVM which can be used in the scheduling of construction projects.
3.2. Data Collection Methodology
There are multiple techniques and methods that can be used by researchers in order to collect
the required data for the research. All the data in this research was gathered using a range of
multiple methods, each one of them was precisely chosen to align with the questions proposed
in this research. These common methods of data collection include document analysis,
literature review, descriptive analysis, questionnaire surveys, and in-depth interviews with
respondents. The decision to choose a certain technique was mainly based on the research
context, research questions, and the objectives that are expected to be accomplished at the end.
The literature review aided in obtaining the equations that can be used to apply the
various types and methods of EVM. The other method of data collection was document analysis
which involved many previous construction projects. The process of document analysis was
concerned mainly with evaluating the descriptive information of previous construction projects
to obtain any data regarding the time and cost of each project. This data was vital for the
following steps in this research including the ability to use EVM methods and equations and
estimate the total duration of construction projects. The next parts of the methodology
discussed the data analysis and the implementation of EVM techniques and equations.
Document analysis is used to offer previous insight and historical context, interviews
are useful for exploring the perspective of individuals, while surveys are preferred to obtain
quantitative data that is broad and from multiple perspectives. This study opted to use
quantitative methods to analyse the implementation of EVM techniques in the construction
sector and use many equations that can estimate the time and schedule of work in the project.
The initial method of data collection that was used in this study was a literature review. This
method helped in gathering extensive data and information about the concept of EVM and its
application in the construction sector. Following the methods used for data collection.
3.2.1 Online Interviews:
Online interviews were conducted with relevant stakeholders, including project managers,
contractors, cost engineers and planning engineers. These interviews helped in obtaining
valuable insights into the project details, including planned schedules, budgets, and actual
performance data.
3.2.2 Site Visits:
Site visits were an integral part of the data collection process. They provided an opportunity to
observe the progress of the projects firsthand, collect visual evidence, and verify the accuracy
of the information provided during online interviews.
3.2.3 Face-to-Face Interviews:
Face-to-face interviews with project team members and site personnel allowed to gather more
specific details about the projects, such as any unexpected challenges faced during construction
and deviations from the original plans.
3.2.4 Document Analysis:
Various project documents were analyzed to extract critical data. These documents included
baseline schedules, monthly cost reports, and monthly progress updates. The analysis of these
documents provided comprehensive information about project timelines, budgets, and
performance metrics.
3.3 Data Source
The data for this analysis was collected from well-known contractors in Egypt who had
executed these projects. The projects were distributed across multiple cities, including Cairo,
Ain Sokhna, Alexandria, North Coast, Gouna, Giza, and 6th of October. This geographic
diversity allowed us to examine construction projects within the same country, taking into
account regional variations and challenges.
3.4 Data Collection Tools
To collect and analyze project data, the following tools were utilized:
3.4.1 Primavera P6:
Primavera P6, a widely used project management software, was employed to access and extract
schedule-related data. This tool facilitated the gathering of information on planned start and
finish dates, as well as progress over time.
3.4.2 Microsoft Excel:
Microsoft Excel was utilized to manage and analyze cost data. It allowed for the comparison
of planned and actual project costs, enabling us to identify budget overruns or savings.
3.4.3 Power Point Presentations:
Weekly progress presentations were utilized to manage the progress data, which allow to
compare between the budget cost of work schedule and the project cost of work performed.
3.5 Data Validation
To ensure the reliability and accuracy of the collected data, several measures were taken:
3.5.1 Multiple Interviews:
Multiple interviews were conducted with different sources, including contractors, project
managers, and site personnel, to cross-verify the information provided and minimize potential
biases.
3.5.2 Site Visits:
Site visits played a crucial role in verifying the data. On-site observations and data collection
helped in confirming the progress and performance of the projects.
3.6 Data Collection Duration
The data collection process spanned approximately one year. This duration was necessary to
obtain comprehensive and accurate information for all 30 selected projects. Some of the data
collection tasks, such as site visits, required substantial time and effort.
3.7. Data Analysis Methodology
The gathered data from the document analysis was then evaluated and used to apply the idea
of EVM. All of the collected data was thoroughly analysed using a pre-defined process. After
obtaining the earned value (EV), planned value (PV), and actual cost (AC) data for each project,
the calculations for three different techniques will be discussed separately. The subsequent
table summarizes the distinctions between these three methods and the calculations involved
in forecasting the project's completion date.
1- The Earned Schedule method relies on the concept of earned schedule, which is
calculated as follows:
𝐸𝑆 = t + EV − 𝑃𝑉
𝑃𝑉 − 𝑃𝑉
Table 1 Comparison between three methods
Equation 3 Earned Schedule (Vanhoucke,2009)
Where ES = Earned schedule
t = Time where earned value happened
𝑃𝑉= = Planned value at time t
𝑃𝑉= Planned value at time t+1
The graphical presentation above shows the difference between earned schedule when the
project is ahead of schedule as shown in the right and in case of the project is delayed as shown
in the figure on the left.
Where SV(t) is the schedule variance in time units and SV is schedule variance in cost units,
and AT is the actual time.
To calculate the Estimate at completion in time units the equation is as follows:
𝐸𝐴𝐶= 𝐴𝑇 +
Equation 4 Estimate at Completion (Vanhoucke,2009)
Where AT is the actual time and PDWR is the planned duration for work remaining and PF is
the performance factor where PF = 1 when the duration of the remaining work is as planned
and PF = SPI(t) when the duration of remaining work is following the SPI(t) trend and PF =
SCI(t) when duration of remaining work is following the cost and time trend.
The calculation of SPI, SPI(t), SCI, SCI(t) is as follows:
SPI=
SPI(t) =
Figure 4: ES difference between two scenarios
Equation 5 Schedule Performance index (Vanhoucke,2009)
SCI = SPI X CPI
SCI(t) = SPI(t) X SCI
Equation 6 Schedule Cost Index (Vanhoucke,2009)
Finally, PDWR = PD – AT
Where PD is the planned duration and AT is the actual duration.
In order to examine the accuracy of the estimation the following equation is used:
Accuracy = | |
Equation 7 Accuracy (Vanhoucke,2009)
Where AD is the equal to the actual project finish date, and the EAC is the estimation at
completion.
2- Earned Duration Method uses the concept of earned duration and it is calculated using
the following formula:
ED Earned Duration = AD X SPI
Equation 8 Earned Duration (Vanhoucke,2009)
Where AD is the Actual duration and SPI is the schedule performance index and it is
calculated as before.
The Estimate at completion in time units using this method is called estimate duration at
completion (EDAC) and it is calculated as follows:
EDAC = AD + UDR
Equation 9 Estimate Duration at Completion (Vanhoucke,2009)
Where UDR is unearned duration remaining and AD is the actual duration.
UDR is calculated using the following formula where PD is the planned duration, ED is the
earned duration and PF is the performance factor.
UDR =
Equation 10 Unearned Duration Remaining (Vanhoucke,2009)
Similar to the previous method performance factor could be PF = 1, SPI, SCI based on the
calculations of the remaining duration.
After that assess the accuracy of the estimation the following equation is used:
Accuracy = | |
Where EDAC is the estimate duration at completion and AD is the actual duration of the
project.
3- The third and final method is the planned value method which is calculated based on a
metric called planned value rate 𝑃𝑉
and TV which the time variance.
𝑃𝑉
= 𝐵𝐴𝐶
𝑃𝐷
Equation 11 Planned Value rate (Vanhoucke,2009)
𝑃𝑉
is the planned rate per time to finish the project on time where BAC = budget at completion
and PD is the planned project duration.
As for the time variance (TV) is the difference in time between the planned budget and actual
cost in time units and it is calculated using the following equation:
𝑇𝑉 = 𝑆𝑉
𝑃𝑉
Equation 12 Time Variance (Vanhoucke,2009)
Where SV is the schedule variance, and it is calculated as follows SV = EV – PV
With the 𝑃𝑉
the time variance is calculated.
The calculation of the estimate at completion is calculated using TEAC which is time estimate
at completion and it is calculated using this formula TEAC = PD – TV when the remaining
work is following the plan, when the remaining work is following the SPI trend, this formula
is used
𝑇𝐸𝐴𝐶 = 𝑃𝐷
𝑆𝑃𝐼
Equation 13 Time Estimate At Completion (Vanhoucke,2009)
Finally, when the remaining work is following the SCI trend the following formula is used.
𝑇𝐸𝐴𝐶 = 𝑃𝐷
𝑆𝐶𝐼
Similarly, the accuracy is of the estimation is calculated using the following equation:
Accuracy = ||
3.8. Ethical Considerations
To maintain confidentiality and ethical standards, the names of the contractors and specific
project details were excluded from this research. Instead, projects were categorized by type,
such as commercial, educational, power stations, renovation, administrative, and residential.
Chapter 4: Data Collection
In this chapter, we provide an overview of the data collection process for the analysis of 30
construction projects across various cities in Egypt. These projects were selected from different
sectors, including commercial, educational, power stations, renovation, administrative, and
residential projects. The data collection process involved a combination of methods, tools, and
sources to gather relevant information for our analysis.
4.6 Projects Overview
The outcomes derived from site visits and interviews include the collection of BCWP, ACWP,
and BCWS data from 30 projects.
1. Budgeted Cost of Work Performed (BCWP): BCWP, also known as EV, represents the
value of the work that has actually been completed in monetary terms. This metric reflects
the progress made in a project and is measured on a monthly basis to track how much of
the planned work has been accomplished.
2. Budgeted Cost of Work Scheduled (BCWS): BCWS, also referred to as PV, signifies the
budgeted value of the work that was originally scheduled to be completed during a specific
period. It provides a planned baseline for project performance and is assessed monthly to
compare the planned progress with the actual progress.
3. Actual Cost of Work Performed (ACWP): ACWP represents the actual costs incurred
during a given month in executing the project. This metric is essential for monitoring
project expenses and determining the financial aspects of project execution.
Additionally, both the original schedules and actual schedules were gathered to facilitate
the analysis of the collected data. The detailed presentation of the data collected for each project
will be provided below. The projects used will be discussed in briefly in the table below and in
details.
Table 2 Projects Data collected.
P
T BCWS
(EGP)
BCWP
(EGP)
ACWP
(EGP)
CV
(EGP)
P
A
D
(D )
1 160,387,330 160,387,330 171,886,590 -11,499,260 20-Feb-18 30-Oct-18 -252
2 E 145,263,973 145,263,973 157,985,453 -12,721,480 30-Apr-17 20-Dec-17 -234
3 I 322,179,850 322,179,850 334,650,146 -12,470,296 19-Apr-19 30-Sep-19 -164
Project 1: Commercial Project
Project 1 commenced on March 1, 2015, with a planned completion date of February 20, 2018.
However, it encountered delays, resulting in an actual finish date of October 30, 2018, which
was 252 days behind schedule. The project had a planned budget of 160 million EGP, but the
actual cost amounted to 172 million EGP, exceeding the budget by 12 million EGP. The
Schedule Performance Index (SPI) started at 76% but dropped to 55%, indicating that the
project was both over budget and behind schedule.
Project 2: Educational Project
This educational project began on July 25, 2015, with a scheduled completion date of April 30,
2017. Unfortunately, it faced delays and ultimately finished on December 20, 2017, 234 days
later than planned. The planned budget was 145 million EGP, but the actual cost reached 157
million EGP, resulting in a 12 million EGP budget overrun. The SPI started at 92% but declined
to 66%, indicating that the project was both over budget and behind schedule.
4 498,371,317 498,371,317 510,650,568 -12,279,251 4-Sep-19 30-Nov-20 -453
5 R 1,844,515,667 1,328,283,068 1,297,649,614 30,633,454 13-Jan-23 30-Jun-23 -169
6 505,782,177 505,782,177 455,858,281 49,923,896 30-Mar-21 30-May-21 -61
7 R 129,946,203 129,946,203 149,674,697 -19,728,494 30-Sep-21 30-Dec-21 -91
8 E 524,011,456 524,011,456 491,657,287 32,354,169 25-Sep-20 20-Nov-20 -56
9 R 934,084,850 869,551,166 908,852,210 -39,301,044 25-Oct-21 28-Feb-23 -491
10 101,460,922 101,460,922 103,647,402 -2,186,480 20-Mar-16 28-Feb-17 -345
11 278,072,672 278,072,672 276,227,816 1,844,856 7-Dec-21 30-Nov-22 -358
12 224,382,775 224,382,775 231,577,203 -7,194,428 1-Oct-19 31-Mar-20 -182
13 I 391,381,394 391,381,394 345,945,404 45,435,990 21-Feb-17 30-Dec-17 -312
14 E 237,039,879 237,039,879 228,301,480 8,738,399 20-Jul-19 14-Sep-19 -56
15 106,717,901 106,717,901 99,209,499 7,508,402 31-Dec-20 25-Jan-21 -25
16 209,859,079 209,859,079 237,328,844 -27,469,765 17-Nov-22 30-Jun-23 -225
17 E 583,273,944 583,273,944 677,666,732 -94,392,788 17-Apr-23 30-Oct-23 -196
18 550,151,073 489,264,996 553,748,233 -64,483,237 4-Aug-22 30-Mar-23 -239
19 I 154,528,736 154,528,736 136,354,130 18,174,606 20-Jun-20 29-Jul-21 -404
20 758,418,631 758,418,631 628,632,758 129,785,873
31-May-22 30-Mar-23 -303
21 R 39,050,912 39,050,912 38,163,075 887,837 22-Apr-20 30-Jun-20 -69
22 I 1,540,046,857 1,540,046,857 1,253,676,323 286,370,534
12-May-20 30-Sep-21 -506
23 I 188,803,564 188,803,564 200,787,624 -11,984,060 3-Apr-21 15-Jun-21 -73
24 61,742,362 61,742,362 57,837,539 3,904,823 30-Jan-19 30-Apr-19 -90
25 341,780,342 341,780,342 360,220,926 -18,440,584 23-Jan-23 30-Dec-23 -341
26 74,027,664 74,027,664 80,492,656 -6,464,992 26-May-22 30-Aug-23 -460
27 172,742,103 172,742,103 192,355,326 -19,613,223 2-Mar-20 30-Dec-20 -303
28 R 299,554,952 299,554,952 339,899,961 -40,345,009 24-Jul-17 30-Apr-18 -280
29 I 167,766,090 167,766,090 160,622,767 7,143,323 31-Jan-19 30-Apr-19 -89
30 I 106,927,735 106,927,735 95,321,477 11,606,258 15-Feb-17 30-Sep-17 -227
Project 3: Power Station Project
Project 3 was a power station project that was initially planned to start on November 5, 2017,
and finish on April 19, 2019. However, it experienced delays and concluded on September 30,
2019, 164 days later than scheduled. The planned budget for the project was 322 million EGP,
but the actual cost amounted to 335 million EGP, resulting in a 13 million EGP budget
deviation. The SPI trend began at around 50% and improved to 87%, with an average SPI of
approximately 80%. Nevertheless, the project was both over budget and behind schedule.
Project 4: Commercial Project
Project 4, a commercial project, was initiated on May 6, 2017, with a planned completion date
of September 4, 2019. However, it faced scheduling challenges, resulting in an actual finish
date of November 30, 2020, which was 453 days later than anticipated. The project was
budgeted at 498 million EGP, and the actual cost reached 510 million EGP, exceeding the
budget by 12 million EGP. The SPI trend showed fluctuations, starting on schedule, and
dropping to 43%, and the CPI trend fluctuated between 88% and 95%. Consequently, the
project was both over budget and behind schedule.
Project 5: Residential Project
This residential project was set to commence on January 14, 2021, with a planned finish date
of January 13, 2023. Unfortunately, it experienced delays, and the forecasted finish date
extended to March 31, 2023, resulting in a deviation of 78 days from the original schedule. The
SPI trend began at 117% but dropped to 76%, indicating that the project was behind schedule.
On the other hand, the CPI trend remained nearly constant at 105%, indicating that the project
was under budget.
Project 6: Commercial Project
Project 6, another commercial project, was scheduled to begin on September 29, 2019, and
conclude on March 30, 2021. However, it faced setbacks, and the actual finish occurred on
May 30, 2021, with a 61-day deviation from the original plan. The planned budget for the
project was 505 million EGP, but the actual cost was 455 million EGP, resulting in a budget
surplus of nearly 50 million EGP. The CPI trend remained consistently at 111%, indicating that
the project was under budget, although it was behind schedule.
Project 7: Renovation Project
A renovation project, Project 7, was slated to start on March 10, 2018, and finish on September
30, 2021. However, it experienced delays and was completed on December 30, 2021, with a
91-day deviation from the planned schedule. The planned budget for the project was 130
million EGP, but the actual cost reached 150 million EGP, resulting in a 20 million EGP budget
overrun. The SPI trend started at 110% but decreased to 97%, and the CPI began at 130% and
decreased to 87%. Consequently, the project was both over budget and behind schedule.
Project 8: Educational Project
Project 8, an educational project, was set to commence on September 25, 2019, and conclude
on September 25, 2020. However, it faced scheduling challenges and was completed on
November 20, 2020, 56 days later than planned. The planned budget for the project was 524
million EGP, while the actual cost was 492 million EGP, resulting in an underspend of 32
million EGP. The SPI trend started at 95% but fluctuated, while the CPI trend showed an
average of 108%. Consequently, the project was under budget but behind schedule.
Project 9: Commercial Project
Project 9, also a commercial project, was planned to start on October 19, 2014, and finish on
March 20, 2016. However, it experienced a significant drop in the SPI, reaching around 55%,
and concluded on February 28, 2017, with an extra 345 days compared to the planned schedule.
The planned budget was 101 million EGP, and the actual cost amounted to 103 million EGP,
resulting in a 2 million EGP budget deviation. The CPI remained at around 96% throughout
the project, indicating that the project was both behind schedule and over budget by 2 million
EGP.
Project 10: Residential Project
Project 10, a residential project, was planned to start on September 28, 2020, and finish on
October 25, 2021, with a total duration of 757 days. However, the SPI trend started at 85% and
declined to 62%, and the project was forecasted to finish on February 28, 2023, with a deviation
of 491 days from the original schedule. The planned budget was 934 million EGP, and the
actual cost was 908 million EGP, resulting in an overspend of 26. The CPI trend started at
111% and dropped to 96%. Consequently, the project was behind schedule and over budget.
Project 11: Administrative Project
Project 11, an administrative project, was scheduled to start on December 8, 2020, and finish
on December 7, 2021, with an overall duration of 364 days. However, the SPI trend started at
90% and dropped to 35%, resulting in the project finishing on November 30, 2022, with a
deviation of 358 days from the original plan. The CPI trend began at 133% and decreased to
98%. Based on the CPI percentage, the project budget was 278 million EGP, and the actual
cost was 276 million EGP, indicating that the project was under budget by 2 million EGP.
Project 12: Commercial Project
Project 12, another commercial project, was planned to start on May 10, 2018, and end on
October 1, 2019. Unfortunately, it faced scheduling issues as the SPI dropped to 70%, resulting
in the project concluding on March 31, 2020, with a deviation of 182 days from the schedule.
The planned budget was 224 million EGP, and the actual cost was 231 million EGP, resulting
in a budget deviation of 7 million EGP. The CPI trend fluctuated between 108% and 101%.
Consequently, the project was behind schedule but within budget.
Project 13: Industrial Project
Project 13, an industrial project, was scheduled to start on December 1, 2015, and finish on
February 21, 2017. However, the SPI dropped to 75%, leading to the project's completion on
December 30, 2017, with a deviation of 312 days from the planned schedule. The project
budget was not disclosed, but the cost performance index ranged from 102% to 114%, and the
project concluded with a CPI of 113%. This indicated that the project was under budget but
behind schedule.
Project 14: Educational Project
Project 14, an educational project, was planned to start on September 9, 2018, and end on July
20, 2019, with an initial duration of 314 days. However, the SPI dropped from 96% to 75%,
resulting in the project's completion on September 14, 2019, with a deviation of 56 days. The
cost performance index (CPI) began at 111% but dropped to 104%, indicating that the project
was under budget but behind schedule.
Project 15: Commercial Project
Project 15 was a commercial project set to start on October 13, 2019, and finish on December
31, 2020. However, the SPI fluctuated between 105% and 95%, causing the project to be
completed on January 25, 2021, with a 25-day delay. The planned budget for the project was
not disclosed, but the CPI ranged from 127% to 108%, ending at 108%. The project was behind
schedule but within budget.
Project 16: Commercial Project
Project 16, another commercial project, was planned to start on November 17, 2021, and end
on November 17, 2022. However, the SPI dropped from 90% to 69%, resulting in the project's
completion on June 30, 2023, with a deviation of 225 days. The planned budget for the project
was not disclosed, but the CPI trend started at 111% and dropped to 88%. The project was both
over budget and behind schedule.
Project 17: Commercial Project
Project 17, a commercial project, was scheduled to start on April 20, 2021, and finish on April
17, 2023. However, the SPI trend started at 105% and dropped to 72%, resulting in a
completion date of October 30, 2023, with a 196-day deviation from the planned schedule. The
planned budget for the project was 583 million EGP, but the actual cost reached 677 million
EGP, resulting in a 94 million EGP budget overrun. The SPI trend indicated that the project
was both over budget and behind schedule.
Project 18: Commercial Project
Project 18 was a commercial project planned to start on December 15, 2021, and finish on
August 4, 2022. The expected actual finish date was March 30, 2023, with a deviation of 239
days. The planned budget for the project was 550 million EGP, the earned value was 489
million EGP, and the actual cost was 553 million EGP, indicating a budget deficit of 64 million
EGP. The SPI was 80%, and the CPI was 88%, demonstrating that the project was behind
schedule and over budget.
Project 19: Industrial Project
Project 19, an industrial project, was intended to start on December 20, 2018, and finish on
June 20, 2020. However, it concluded on July 29, 2021, with a deviation of 89 days. The
planned budget was 154 million EGP, and the actual cost was 136 million EGP, resulting in an
underspend of 18 million EGP. The SPI was 49%, and the CPI was 113%, indicating that the
project was behind schedule but under budget.
Project 20: Commercial Project
Project 20, another commercial project, was planned to start on January 22, 2020, and finish
on May 31, 2022. However, the project was completed on March 30, 2023, with a 303-day
delay. The planned budget was 758 million EGP, and the actual cost was 628 million EGP,
resulting in an underspend of 130 million EGP. The SPI was 68%, and the CPI was 121%,
demonstrating that the project was behind schedule but under budget.
Project 21: Residential Project
This residential project was scheduled to begin on August 22, 2019, and finish in 2020, but it
concluded on June 30, 2020, with a 69-day deviation. No cost deviation information was
provided.
Project 22: Industrial Project
Project 22 was an industrial project that was planned to start on November 12, 2018, and finish
on May 12, 2020. However, it finished on September 30, 2021, with a deviation of 506 days
from the planned duration. The planned budget was 1540 million EGP, but the actual cost was
1253 million EGP, indicating a budget deviation of 286 million EGP. The SPI was 66%, and
the CPI was 123%, showing that the project was behind schedule and under budget.
Project 23: Industrial Project
Project 23 was an industrial project that was planned to start on May 3, 2020, and finish on
April 3, 2021. However, it finished on June 15, 2021, with a delay of 73 days from the planned
duration. The planned budget was 189 million EGP, but the actual cost was 201 million EGP,
indicating a budget deviation of 12 million EGP. The SPI was 94%, and the CPI was 73%,
showing that the project was behind schedule and over budget.
Certainly, here's a rephrased version of the information about Projects 24 to 30 in paragraph
format:
Project 24: Commercial Project
Project 24 falls under the category of commercial projects. Originally scheduled to commence
on June 1, 2018, and conclude by January 30, 2019, it faced a deviation, finishing on April 30,
2019, marking a 90-day delay. The Schedule Performance Index (SPI) at the planned duration
was 54%. In terms of budget, it's important to note that the project consistently remained under
budget throughout its duration, concluding with an actual cost of 58 million EGP compared to
the planned budget of 62 million EGP, resulting in a 4 million EGP budget surplus.
Project 25: Commercial Project
Project 25 is another commercial project that was initially planned to kick off on August 15,
2021, and wrap up by January 23, 2023. Unfortunately, due to low performance, it concluded
on December 30, 2023, reflecting a significant deviation of 341 days from the original plan,
which was a 526-day schedule. The SPI at the planned duration was at 61%. In terms of costs,
the Cost Performance Index (CPI) began under budget at 111% but progressively decreased to
95% by the project's end, resulting in a 19 million EGP deviation from the planned budget of
342 million EGP, with an actual cost of 360 million EGP.
Project 26: Commercial Project
Project 26, also classified as a commercial project, was initially intended to start on May 18,
2021, and conclude on May 26, 2022. However, it faced substantial delays, concluding on
August 30, 2023, resulting in a total duration of 834 days instead of the planned 373 days. The
SPI at the planned duration was 65%. On the cost front, the project initially operated under
budget, but it gradually moved into an over-budget scenario, with a final CPI of 92%.
Project 27: Commercial Project
Project 27, another commercial project, was initially scheduled to begin on October 1, 2019,
and end on March 2, 2020. However, the project faced significant delays, concluding on
December 30, 2020, representing a total deviation of 303 days from the planned duration,
which was initially set at 153 days. The SPI at the end of the project was 56%. In terms of
costs, the project experienced a continuous state of being over budget, with a CPI of 95% at
the start and 90% at the conclusion.
Project 28: Residential Project
Project 28 falls into the residential project category. It was planned to start on March 23, 2015,
and finish by July 24, 2017. However, the project experienced a substantial delay, concluding
on April 30, 2018, marking a total deviation of 280 days from the planned 854-day duration.
The project consistently lagged behind schedule. On the cost side, it was over budget
throughout its duration, with a 40 million EGP deviation from the planned budget of 300
million EGP, concluding with an actual cost of 340 million EGP.
Project 29: Industrial Project
Project 29 is an industrial project that was initially scheduled to begin on July 2, 2018, and
conclude by December 31, 2019. However, the project finished on April 30, 2019, with an 89-
day deviation from the planned duration, primarily due to low performance and a low SPI.
From a cost perspective, the project remained under budget throughout, with a 7 million EGP
budget surplus when compared to the planned budget of 167 million EGP and an actual cost of
160 million EGP.
Project 30: Industrial Project
Finally, Project 30, another industrial project, was planned to begin on June 5, 2016, and
conclude by February 15, 2017, representing a total duration of 255 days. However, the project
faced extensive delays, concluding on September 30, 2017, with an actual duration of 482 days,
resulting in a 227-day deviation from the planned finish date. The project was behind schedule
primarily due to low performance, with an SPI of 50% at the planned finish date. In terms of
costs, the project consistently remained under budget, concluding with an actual cost of 95
million EGP compared to the planned budget of 107 million EGP, resulting in an 11 million
EGP budget surplus.
4.7 Conclusion
In this Chapter, the data collection process, and an overview of the 30 projects analyzed for
this study. The projects were collected from various cities across Egypt, including Cairo, Ain
Sokhna, Alexandria, North Coast, Gouna, Giza, and 6th of October. These projects encompass
a diverse range of types, including residential, commercial, administrative, renovation,
educational, and power station construction. Subset of these projects were examined in detail
to highlight the data collection process and provide insights into their schedules and budgets.
In the following chapter (Chapter 5), we will delve into the data analysis techniques that will
be applied to this dataset. These techniques include the earned schedule method, earned
duration method, and planned value method, each of which will be discussed in detail to
provide a comprehensive understanding of the project performance metrics and trends.
Chapter 5: Analysis
In this chapter, We compare the three methods of EVM which are earned schedule method,
earned duration method, and planned value method on 30 actual projects in order to find an
accurate estimation of the finish date and define which method fits best in different cases. The
projects have different types such as commercial, industrial, educational, residential,
renovation and administrative. These projects are located in different cities across Egypt such
as Cairo, Giza, 6th of October, Ain Sokhna, Hurghada, North coast and Alexandria. These
projects have different timelines ranging from 2015 to 2023, in addition to different contract
prices. All these projects were evaluated from the contractor’s point of view. The projects data
were collected from various contractors across Egypt.
5.1 Demonstrating Calculation Procedures in the Sample Project
The calculations will be remonstrated in one project in order to show how the
calculations works, the project used for these calculations is a commercial project with a total
budget of 498 million EGP the project started in 06th May 2017 and it was planned to finish on
4th September 2019 and actual finish is 30th November 2020. The Month that will be using the
calculations for is 01st November 2018 in which the earned value is 127,800,365 million EGP
while the actual cost is 145,807,922 and the planned value is 255,378,951 million EGP.
The analysis incorporated three distinct earned value techniques: Earned Duration method,
Earned Schedule method, and Planned Value method. Each method had its own set of metrics
to evaluate project performance and forecasting accuracy of calculating finish date:
1- Earned Duration Method:
Earned Duration (ED): This metric indicates the equivalent duration based on the value
of work completed. It quantifies the time required to complete the earned value.
In a related context, Jacob and Kane (2004) introduced a concept, earned duration (ED),
which is the result of multiplying the actual project duration (AD) by the schedule
performance index (SPI). Jacob (2003) and Jacob and Kane (2004) advocated for the earned
duration method as a robust approach for forecasting a project's final duration by
incorporating the schedule performance index (SPI).
The earned duration is calculated using the following formula.
ED Earned Duration = AD X SPI
The actual duration AD is 544 days and the SPI =
= ,,
,, = 50%
Then the Earned duration is calculated ED = 50% x 544 = 272 Days
After that estimate at completion is calculated using this formula EDAC = 𝐴𝐶 +
PD is the planned total duration of the project which is 851 days and earned duration is 272
days.
The estimate at completion will be calculated three times, the first time when the performance
factor PF = 1, the second time when the PF is equal to SPI, and the third time when the PF is
equal to SCI which schedule cost index.
𝐸𝐴𝐶=544 +
= 1123 Days
At PF = SPI
𝐸𝐴𝐶=544 +
. = 1702 Days
At PF = SCI
SCI = SPI x CPI
CPI = =
= ,,
,, = 88%
SCI = SPI x CPI = 88% x 50% = 44%
𝐸𝐴𝐶=544 +
. = 1865 Days
The actual finish date 30th November 2020 and the actual project duration is 1304 days.
Then the three estimates are compared with the actual finish date and the accuracy is calculated
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = ||
= 86%
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = ||
= 69%
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = ||
= 57%
Therefore, the highest accuracy achieved when the PF = 1
2- Planned Value Method:
Anbari (2003) developed the planned value method, which relies on established earned
value metrics to project a project's duration. This method calculates the average planned
value per time period, known as the planned value rate (PVrate). PVrate is determined by
dividing the project's baseline budget at completion (BAC) by its planned duration (PD).
This metric helps translate schedule variance (SV) into time units, represented as time
variance (TV).
First planned value rate is calculated as shown below:
𝑃𝑉
=
= ,,
= 585,630
Then time variance is calculated.
𝑇𝑉 = 𝑆𝑉
𝑃𝑉
SV = EV – PV = 127,800,365 - 255,378,951 = -127,579,585 EGP
𝑇𝑉 = ,,
, = -218 days
After that estimate at completion is calculated when the performance factor = 1 using this
formula
𝑇𝐸𝐴𝐶= PD – TV = 851 – (-218) = 1069 days
At PF = SPI
Time variance is calculated using this formula 𝑇𝐸𝐴𝐶 =
=
% = 1702 days
At PF = SCI
The time variance is calculated using this formula 𝑇𝐸𝐴𝐶 =
=
% = 1942 days
Then the three estimates are compared with the actual finish date and the accuracy is calculated
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = ||
= 82%
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = ||
= 69%
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − | |
= = ||
= 51%
Therefore, the highest accuracy achieved with planned value method is when PF = 1
3- Earned Schedule Method:
Earned Schedule (ES): ES represents the time when the value of the work is earned. It is
calculated using the following formula:
𝐸𝑆 = t +
= 544 + ,, ,,
,,,, = 330 Day
To calculate the Estimate at completion in time units the equation is as follows:
First at PF = 1,
𝐸𝐴𝐶 = 𝐴𝑇 +
= 𝐴𝑇 +
= 544 +
= 1065 day
at PF = SPI,
𝐸𝐴𝐶 = 𝐴𝑇 +
= 𝐴𝑇 +
= 544 +
% = 1403 day
at PF = SCI,
𝐸𝐴𝐶 = 𝐴𝑇 +
= 𝐴𝑇 +
= 544 +
% = 1524 day
Comparing the result with the actual finish date, the accuracy is determined as shown below.
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = ||
= 82%
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − | |
= = ||
= 92.4%
𝐴𝑐𝑐𝑢𝑟𝑎𝑐𝑦 = 1 − ||
= = | |
= 83%
Therefore, the highest accuracy achieved with earned schedule is when PF = SPI, in addition
to being the highest accuracy obtained
Following the project calculations, the results will be presented in four figures. These
figures will depict the project duration percentages under different scenarios: first, when the
performance factor is set to 1; second, when the performance factor is configured to SPI; third,
when the performance factor is set to SCI; and finally, a comprehensive comparison figure to
assess the overall estimation. This comparison will highlight the most suitable technique to
employ based on the performance factor.
figure 6 presents an average comparison among the three techniques for the
demonstrative project. As depicted, the Earned Schedule method demonstrates consistent
accuracy between 75% and 90% throughout the project duration. In contrast, the Earned
Duration method exhibits a decline from 20% to 75% of the project duration, followed by a
subsequent increase leading to its peak accuracy at the conclusion of the project. Likewise, the
Planned Value method experiences a decrease from 20% to 75% of the project duration,
reaching its lowest accuracy among the three techniques by the project's end.
Figure 7 offers a comparative assessment of the three techniques when the performance
factor is equal to 1. Initially, all three methods exhibited nearly identical accuracy, hovering
around 65%. Subsequently, as the project duration percentage advanced to 85%, all methods
showed a continuous increase. However, a notable divergence occurred thereafter: the Planned
Value method began to decline, reaching approximately 69% towards the project's conclusion.
In contrast, the Earned Schedule method achieved a 97.5% accuracy by the project's end, while
the Earned Duration method reached the highest percentage, standing at 98.5% at the
conclusion of the project.
Figure 8 provides a comparative evaluation of the three techniques when the
performance factor is set to SPI. Initially, all three methods demonstrated nearly identical
accuracy, hovering around 65%. As the project duration percentage advanced to 20%, all three
methods experienced an increase. However, a divergence emerged after this point: the Planned
Duration and Earned Duration methods gradually decreased, reaching their lowest points
around the 75% duration mark. In contrast, the Earned Schedule method-maintained accuracy
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
AVER AGE E ARN ED S CHEDULE VS E ARNE D DUR ATION VS
PLANN ED DUR ATION
Earned Duration Earned Schedule Planned Value
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HEDULE VS EARNED DUR ATIO N VS P LANNED
DURATION AT PF =1
Earned Duration Earned Schedule Planned Value
Figure 7 Average accuracy Earned schedule vs earned duration vs planned duration At PF = 1
Figure 6 Average Earned Schedule VS earned Duration VS Planned Duration
between 85% and 95% throughout the project duration, concluding with a 94% accuracy.
Towards the end of the project, the Earned Duration method exhibited an increase, reaching
98%, while the Planned Value method declined, concluding with a 68% accuracy.
Figure 9 conducts a comparative assessment of the three techniques with the
performance factor set to SCI. Initially, all three methods demonstrated virtually identical
accuracy, hovering around 65%. As the project duration percentage progressed to 20%, two
methods, namely Earned Schedule and Planned Value, exhibited an increase, maintaining
accuracy between 80% and 95% throughout the project duration and culminating in a 94%
accuracy by the project's conclusion. In contrast, Earned Duration experienced a decline,
reaching 29% at the 75% mark of the project duration percentage. Subsequently, it underwent
an upward trend, reaching 98% by the conclusion of the project.
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SCHEDULE VS EARNED DURATION VS
PLANNED DURATION AT PF =SPI
Earned Duration Earned Schedule Planned Value
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SCHEDULE VS EARNED DURATION VS PLANNED
DURATION AT PF =SCI
Earned Duration Earned Schedule Planned Value
Figure 8 Average accuracy Earned schedule vs earned duration vs planned duration At PF = SPI
Figure 9 Average accuracy Earned schedule vs earned duration vs planned duration At PF = SCI
However, it's worth noting that the choice of the most effective technique also depends on
the specific project type and its duration. For renovation and residential projects, the Earned
Schedule method outperformed the others, achieving the highest accuracy. On the other
hand, for industrial, commercial, and educational, the Earned Duration method was
consistently the most accurate.
5.2 The Analysis of Industrial Projects.
The detailed discussion of the outcomes for each project type begins with industrial projects.
As previously noted, the Earned Duration method yields the highest overall percentage.
However, when the performance factor is set to SPI, Earned Schedule takes the lead in
accuracy. The following illustration provides a comprehensive overview of accuracy
percentages across project duration percentages, considering performance factors 1, SPI, SCI,
and the average.
Figure 10 depicts the accuracy comparison among the three methods on an average basis.
Figure 11 illustrates the comparison of accuracy among the three methods under the condition
of a performance factor set to 1.
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
AVER AGE COMPARIS ON BE TWE EN EA RNED S CHEDULE VS
EAR NED DU RATION VS P LANNED DURATION ( INDUS TR IAL
PR OJ ECTS )
Earned Duration Earned Schedule Planned Value
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HE DULE VS EARNED DUR ATION VS PLA NNED
DURATION AT PF = 1 (IN DUST RIAL PRO J ECTS )
Earned Duration Earned Schedule Planned Value
Figure 10 Average Accuracy between Earned Schedule vs Earned duration vs Planned duration (Industrial Projects)
Figure 12 displays the accuracy comparison among the three methods when the performance
factor is set to SPI.
The fourth and final visual representation for the industrial project showcases the accuracy
comparison under the condition of a performance factor set to SCI.
Figure 13 displays the accuracy comparison among the three methods when the performance
factor is set to SCI.
5.3 The Analysis of Commercial Projects.
Similarly, in commercial projects, the Earned Duration method attains the highest
overall percentage, and this trend persists when the performance factor is set to 1. Conversely,
when the performance factor is SPI, the highest accuracy percentage is achieved by the Earned
Schedule method. The forthcoming illustration will present a comprehensive overview of
accuracy percentages across project duration percentages for performance factors 1, SPI, SCI,
and the average.
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HE DULE VS EARNED DUR ATION VS PLA NNED
DURATION AT P F = SPI (IN DU STR IA L PROJ ECTS)
Earned Duration Earned Schedule Planned Value
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S C HEDULE VS EARN ED DUR ATIO N VS PLANNE D
DURATION AT P F = SCI (INDU S TR IA L PROJ EC TS )
Earned Duration Earned Schedule Planned Value
Figure 11 Accuracy comparison between Earned Schedule vs Earned duration vs Planned duration (Industrial Projects) AT PF = 1
Figure
12 Average comparison between Earned Schedule vs Earned duration vs Planned duration (Industrial Projects) AT PF =SPI
Figure 13 Average comparison between Earned Schedule vs Earned duration vs Planned duration (Industrial Projects) at PF = SI
Figure 14 illustrates the comparison of accuracy among the three methods on an average scale.
Figure 15 depicts the accuracy comparison among the three methods when the
performance factor is set to 1.
Figure 16 showcases the accuracy comparison among the three methods when the performance
factor is configured to SPI.
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S CHEDULE VS EAR NED DUR ATIO N VS PLANNE D
DURATION AT PF =1 ( COMMET RIAL PROJ EC TS)
Earned Duration Earned Schedule Planned Value
Figure 14 Average Earned Schedule vs Earned duration vs Planned duration (Commetrial Projects)
Figure
15
Average Earned Schedule vs Earned duration vs Planned duration (Commetrial Projects)
at PF = 1
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
AVER AGE EA RNED S CHEDULE VS EAR NE D DUR ATION VS
PLAN NED DUR ATION (C OM MET RIAL PROJ EC TS)
Earned Duration Earned Schedule Planned Value
Figure 17 is visual representation for the commercial projects highlights the accuracy
comparison when the performance factor is set to SCI.
5.4 The Analysis of Educational Projects.
In the case of educational projects, the Earned Duration method achieves the highest
overall percentage. Additionally, when the performance factor is set to SPI and SCI, Earned
Duration maintains its supremacy. However, under the condition of a performance factor equal
to 1, Earned Schedule exhibits the highest accuracy. The upcoming visual representation will
provide a thorough overview of accuracy percentages across project duration percentages for
performance factors 1, SPI, SCI, and the average.
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S C HE DULE VS EAR NED D UR ATION VS PLANNE D
DURATION AT PF =S C I (C OMM ETR IAL PROJ ECTS)
Earned Duration Earned Schedule Planned Value
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S CHEDULE VS EAR NED DUR ATIO N VS PLANNE D
DURATION AT PF =S P I (COMM ETRIAL PR OJ EC T S)
Earned Duration Earned Schedule Planned Value
Figure 16 Average Earned Schedule vs Earned duration vs Planned duration (Commercial Projects) at PF = SPI
Figure 17 Average Earned Schedule vs Earned duration vs Planned duration (Commercial Projects) AT PF = SCI
Figure 18 depiction showcases the comparison of accuracy among the three methods
on an average scale.
Figure 19 illustrates the accuracy comparison among the three methods under the
condition of a performance factor set to 1.
Figure 20 presents the accuracy comparison among the three methods when the
performance factor is set to SPI.
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
AVER AGE E ARN ED S CHEDULE VS E ARNE D DUR ATION VS
PLANNE D DUR ATIO N (ED UCTIO NA L PRO J EC TS)
Earned Duration Earned Schedule Planned Value
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HE DULE VS EAR NED DUR ATION VS PLA NNED
DURATION AT PF =1 ( E DUC TIONAL PROJ EC TS )
Earned Duration Earned Schedule Planned Value
Figure 18 Average Earned Schedule vs Earned duration vs Planned duration (Educational projects)
Figure
19
Earned Schedule vs Earned duration vs Planned duration at
PF
=1 (Educational projects)
Figure 21 is the visual representation for the commercial projects underscores the
accuracy comparison when the performance factor is set to SCI.
5.5 The Analysis of Residential Projects.
For residential projects, in contrast to other projects, the Earned Schedule method secures the
highest overall percentage. Furthermore, under the conditions of a performance factor set to 1,
SPI, and SCI, the upcoming visual representation will deliver a comprehensive overview of
accuracy percentages across project duration percentages for performance factors 1, SPI, SCI,
and the average.
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HE DULE VS EARNED DUR ATION VS PLA NNED
DURATION AT PF = SP I (EDU C TIONAL PROJ EC TS)
Earned Duration Earned Schedule Planned Value
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S C HEDULE VS EARNED DUR ATIO N VS PLANNE D
DURATION AT P F = SCI (EDUCTIO NA L PROJ ECT S)
Earned Duration Earned Schedule Planned Value
Figure 20 Earned Schedule vs Earned duration vs Planned duration (Educational projects) at PF = SPI
Figure 21 Earned Schedule vs Earned duration vs Planned duration (Educational projects) AT PF = SCI
Figure 22 highlights the comparison of accuracy among the three methods on an
average scale.
Figure 23 illustrates the comparison of accuracy among the three methods when the
performance factor is set to 1.
Figure 24 showcases the accuracy comparison among the three methods when the performance
factor is configured to SPI.
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
AVER AGE EARNE D S CHEDULE VS EA RNE D DUR ATION VS
PLANNE D DUR ATIO N (RES IDNETIAL PR OJ ECT S)
Earned Duration Earned Schedule Planned Value
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HEDULE VS EARNED DUR ATIO N VS P LANNED
DURATION AT PF = 1(R ES ID NET IAL PROJ ECTS )
Earned Duration Earned Schedule Planned Value
Figure 22Average Earned Schedule vs Earned duration vs Planned duration (Residential projects)
Figure
23
Average Earned Schedule vs Earned duration vs Planned duration (Residential projects)
AT PF = 1
Figure 25 is the visual representation for commercial projects emphasizes the accuracy
comparison when the performance factor is set to SCI.
5.6 The Analysis of Renovation Projects.
In renovation endeavours, much like residential projects, the Earned Schedule method
consistently achieves the highest overall percentage. Additionally, when the performance
factor is set to 1, the earned duration takes precedence, while equality between the performance
factor, SPI, and SCI results in the earned duration coming out on top. A forthcoming visual
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S CHEDULE VS EAR NED DUR ATIO N VS PLANNE D
DURATION AT PF =S CI (RESID NETIAL P ROJ ECT S)
Earned Duration Earned Schedule Planned Value
Figure 25 Earned Schedule vs Earned duration vs Planned duration (Residential projects) AT PF = SCI
60%
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HEDULE VS EARNED DUR ATIO N VS P LANNED
DURATION AT P F = SP I (RE SIDN ET IAL PR OJEC TS)
Earned Duration Earned Schedule Planned Value
representation will provide a comprehensive overview of accuracy percentages across project
duration percentages for performance factors 1, SPI, SCI, and the average.
Figure 26 emphasizes the comparison of accuracy among the three methods on an average
scale.
Figure 27 depicts a comparison of accuracy among the three methods under the condition of a
performance factor set to 1.
Figure 28 displays a comparison of accuracy among the three methods under the configuration
of the performance factor to SPI.
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
AVER AGE E ARN ED S CHEDULE VS E ARNE D DUR ATION VS
PLANNE D DUR ATION (R EN O VATIO N P ROJEC TS )
Earned Duration Earned Schedule Planned Value
90%
95%
100%
Accuracy
Duration Percentage
EAR NED S CHEDULE VS EAR NED DUR ATIO N VS PLANNE D
DURATION AT P F = 1(RE NO VATIO N PRO J ECT S)
Earned Duration Earned Schedule Planned Value
Figure 26 Average Earned Schedule vs Earned duration vs Planned duration (Renovation projects)
Figure 27 Earned Schedule vs Earned duration vs Planned duration (Renovation projects) AT PF =1
Figure 29 is the visual representation for commercial projects emphasizes the accuracy
comparison when the performance factor is set to SCI.
In summary, the analysis of various project types reveals distinct patterns in the
performance of Earned Duration and Earned Schedule methods under different performance
factors. In industrial projects, Earned Duration consistently secures the highest overall
percentage, except when the performance factor is set to SPI, where Earned Schedule excels in
accuracy. A similar trend is observed in commercial projects, with Earned Duration dominating
overall and Earned Schedule leading under the SPI performance factor. Educational projects
showcase a nuanced scenario, where Earned Duration performs best overall but Earned
Schedule surpasses under a performance factor set to 1. Notably, residential and renovation
projects deviate from the general pattern, with Earned Schedule emerging as the method with
the highest overall percentage. The detailed visual representations across project duration
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HEDULE VS EARNED DUR ATIO N VS P LANNED
DURATION AT P F = SP I ( RE NOVATION PROJ ECTS)
Earned Duration Earned Schedule Planned Value
65%
70%
75%
80%
85%
90%
95%
100%
Accuracy
Duration Percentage
EARNED SC HE DULE VS EARNED DUR ATION VS PLA NNED
DURATION AT PF = SC I (RENOVATION P ROJ EC TS)
Earned Duration Earned Schedule Planned Value
Figure 28 Average Earned Schedule vs Earned duration vs Planned duration (Renovation projects) AT PF = SPI
Figure 29 Average Earned Schedule vs Earned duration vs Planned duration (Renovation projects) AT PF = SCI
percentages and performance factors 1, SPI, SCI, and the average offer a comprehensive
overview, aiding in understanding the nuanced dynamics of accuracy across diverse project
types and conditions.
5.7 International and domestic project managers
Another crucial criterion employed for the analysis involves assessing the accuracy by
comparing projects managed by international and domestic project managers. This aims to
underscore potential disparities between these two factors. Table 3 illustrates the variance in
accuracy between domestic and international project managers when using performance factor
equal to 1. As depicted in the table, projects led by international project managers consistently
exhibit higher accuracy levels compared to those overseen by domestic counterparts throughout
the project timeline.
Table 3 Comparison between international and domestic project managers when performance
factor equal to 1
Table 4 presents the discrepancy in accuracy between domestic and international
project managers when utilizing the performance factor equivalent to SPI. As indicated in the
table, projects supervised by international project managers consistently demonstrate higher
accuracy levels in comparison to those managed by domestic counterparts throughout the
project timeline.
Duration %
PM Accuracy At PF = 1 PM Accuracy At PF = 1
ED
ES
PV
ED
ES
PV
5%
International
75.23% 74.37% 74.64% Domestic
64.58%
64.50% 64.40%
10%
International
74.63% 75.06% 73.15%
Domestic
69.82%
70.82% 69.48%
15%
International
79.06% 81.04% 76.92%
Domestic
68.53%
70.21% 68.47%
20%
International
75.05% 75.40% 72.52% Domestic
69.56%
71.84% 69.38%
25%
International
78.74% 78.90% 76.18% Domestic
75.17%
76.17% 74.04%
30%
International
77.86% 73.94% 74.78% Domestic
75.34%
74.69% 74.51%
35%
International
78.54% 77.11% 74.61% Domestic
77.18%
75.77% 76.85%
40%
International
82.40% 80.71% 78.59% Domestic
81.71%
80.75% 81.47%
45%
International
85.06% 84.10% 81.32% Domestic
81.62%
82.03% 81.49%
50%
International
84.98% 81.05% 82.80% Domestic
84.74%
85.16% 84.12%
55%
International
87.67% 81.11% 86.63% Domestic
85.91%
86.38% 85.46%
60%
International
88.11% 84.76% 85.47%
Domestic
86.10%
85.62% 84.48%
65%
International
89.99% 86.79% 85.75%
Domestic
88.38%
89.92% 86.14%
70%
International
89.01% 85.75% 83.15% Domestic
90.65%
89.32% 84.47%
75%
International
92.19% 89.32% 83.78% Domestic
91.18%
90.40% 82.77%
80%
International
93.22% 90.59% 84.12% Domestic
92.44%
92.55% 80.39%
85%
International
93.64% 94.11% 81.25% Domestic
93.27%
92.32% 78.77%
90%
International
95.80% 95.55% 77.61% Domestic
93.59%
94.28% 74.19%
95%
International
97.56% 96.91% 72.71% Domestic
96.42%
96.41% 73.68%
100%
International
99.18% 98.93% 70.56% Domestic
99.12%
98.79% 68.22%
Table 4 Comparison between international and domestic project managers when performance factor equal to 1
Table 5 displays the variation in accuracy between domestic and international project
managers, utilizing the performance factor equivalent to SCI. As outlined in the table, projects
overseen by international project managers consistently showcase higher accuracy levels
compared to those managed by their domestic counterparts across the project timeline.
Duration %
PM Accuracy At PF = SPI PM Accuracy At PF = SPI
ED
ES
PV
ED
ES
PV
5%
International 72.43% 71.29% 72.43% Domestic
68.04%
64.21% 68.04%
10%
International 79.15% 64.98% 79.15% Domestic
73.79%
69.60% 73.79%
15%
International 80.29% 71.99% 80.29% Domestic
72.99%
74.13% 72.99%
20%
International
82.68% 86.37% 82.68%
Domestic
77.00%
71.44% 77.00%
25%
International
81.69% 86.27% 81.69%
Domestic
85.55%
79.28% 85.55%
30%
International
78.78% 76.75% 78.78%
Domestic
77.70%
85.81% 77.70%
35%
International
85.51% 86.51% 85.51% Domestic
76.15%
85.82% 76.15%
40%
International 83.67% 84.67% 83.67% Domestic
75.67%
84.62% 75.67%
45%
International 81.23% 83.28% 81.23% Domestic
81.33%
85.24% 81.30%
50%
International 79.48% 80.37% 79.48% Domestic
80.62%
79.38% 80.39%
55%
International 77.62% 85.78% 77.34% Domestic
79.49%
79.31% 79.36%
60%
International 75.36% 79.48% 73.85% Domestic
82.81%
81.99% 82.37%
65%
International 77.53% 81.77% 75.90% Domestic
81.23%
81.19% 80.18%
70%
International
86.18% 86.78% 79.97%
Domestic
84.85%
85.36% 81.42%
75%
International
87.12% 88.50% 78.65%
Domestic
82.85%
84.44% 75.89%
80%
International
91.28% 88.28% 82.89%
Domestic
88.36%
85.16% 78.26%
85%
International
92.69% 92.67% 81.53% Domestic
87.07%
87.46% 74.54%
90%
International 95.88% 93.67% 78.54% Domestic 92.23%
89.62% 74.18%
95%
International 97.80% 95.41% 72.92% Domestic 96.01%
93.61% 74.19%
100%
International 99.19% 98.63% 70.51% Domestic 99.11%
97.79% 68.22%
Duration %
PM Accuracy At PF = SCI PM Accuracy At PF = SCI
ED
ES
PV
ED
ES
PV
5%
International
66.08% 66.47% 66.47% Domestic
63.58%
61.67% 61.67%
10%
International
73.66% 68.51% 68.51% Domestic
69.74%
69.10% 69.10%
15%
International
71.55% 65.62% 65.62% Domestic
68.41%
70.52% 70.52%
20%
International
76.57% 82.89% 82.89% Domestic
73.04%
72.14% 72.14%
25%
International
76.35% 81.58% 81.58%
Domestic
82.34%
82.69% 82.69%
30%
International
75.75% 73.82% 73.82%
Domestic
76.58%
86.36% 86.36%
35%
International
83.68% 81.07% 81.07% Domestic
75.00%
84.41% 84.41%
40%
International
80.78% 79.37% 79.37% Domestic
74.97%
83.53% 83.53%
45%
International
76.90% 76.94% 76.94% Domestic
79.48%
82.05% 82.05%
50%
International
76.99% 77.55% 77.55% Domestic
80.35%
78.46% 78.46%
55%
International
76.29% 80.57% 80.57% Domestic
78.15%
77.60% 77.60%
60%
International
72.44% 74.56% 74.56% Domestic
80.35%
79.20% 79.20%
65%
International
75.84% 77.77% 77.77% Domestic
80.85%
79.19% 79.19%
70%
International
85.03% 84.10% 84.10% Domestic
83.19%
83.95% 83.95%
In conclusion, the analysis of accuracy in project management, considering 1, SPI and SCI
performance factors, revealed consistent trends when comparing projects led by international
and domestic project managers. Tables 3, 4, and 5 consistently demonstrate that projects
supervised by international project managers consistently exhibit higher accuracy levels than
those managed by domestic counterparts throughout the entire project timeline. This
underscores a notable pattern suggesting that international project managers tend to achieve
higher accuracy in project execution, emphasizing the significance of managerial expertise in
achieving project objectives.
5.8 Guidelines Derived from the Above.
Following an in-depth analysis and meticulous calculations for project types, the subsequent
phase involves extending our scrutiny to encompass the collective results derived from thirty
distinct projects. This comprehensive examination aims to unveil overarching patterns and
insights, shedding light on the most effective method for projecting project completion dates.
Through a nuanced exploration of various facets and project durations, we endeavour to distil
valuable conclusions that will serve as practical guidance for optimizing the accuracy of project
forecasting methods.
First and foremost, the Earned Duration method emerged as the most accurate among the
three techniques across various metrics, including average accuracy, performance factor set
to 1, and performance factor set to SPI Earned Schedule were the highest. However, under
the performance factor set to SCI, both Planned Duration and Earned Schedule surpassed
Earned Duration, achieving an accuracy of 81.52%%. This underscores the Earned
Duration method's exceptional efficacy in predicting project completion dates across a
diverse spectrum of project types and durations.
75%
International
85.51% 84.60% 84.60%
Domestic
81.28%
81.84% 81.84%
80%
International
88.98% 85.44% 85.44%
Domestic
87.37%
83.48% 83.48%
85%
International
90.01% 91.64% 91.64% Domestic
85.73%
85.53% 85.53%
90%
International 94.42% 92.60% 92.60% Domestic 91.91%
88.72% 88.72%
95%
International 97.24% 95.04% 95.04% Domestic 95.87%
93.11% 93.11%
100%
International 99.13% 98.57% 98.57% Domestic 99.12%
97.70% 97.70%
In Figure 30, the variation in average accuracy achieved by each method is illustrated. The
gauge chart displays four categories, ranging from 0 to 25%, 25% to 50%, 50% to 75%, and
finally, 75% to 100%, with each category represented by a distinct color as shown below.
Furthermore, the thesis unveiled a useful guideline for selecting the most efficient
technique based on project duration percentages. These guidelines will assist project
managers and practitioners in making informed decisions about which technique to employ
for the most accurate project forecasting in general:
1- For projects with a duration ranging from 0% to 20% of the total project timeline,
the Earned Duration method is recommended.
2- In the case of projects spanning from 20% to 50% of the project duration, the Earned
Schedule method is the optimal choice.
3- Projects in the 55% to 65% duration range are best suited for the Earned Duration
method.
Figure 30 Overall accuracy achieved per method.
4- Between 65% and 70% of the project timeline, the Earned Schedule method proves
to be the most efficient.
5- For projects from 70% to 75% of their duration, the Earned Duration method is once
again the recommended technique.
6- In the 75% to 80% project duration range, the Earned Schedule method is the most
effective.
7- Finally, for projects nearing completion, from 80% to 100% of the project duration,
the Earned Duration method is the superior choice.
Figure 31 illustrates the best method to use over the project duration percentage as mentioned
above.
Additionally, the thesis introduced a practical guideline for selecting the most effective
technique based on project duration percentages. These recommendations are designed to aid
project managers and practitioners in making well-informed decisions regarding the choice of
techniques for precise project forecasting when using a performance factor equal to 1:
1- For projects constituting 0% to 5% of the total project timeline, it is advisable to use
the Earned Duration method.
2- Projects with a duration falling within the 5% to 30% range of the total project timeline
are best suited for the Earned Schedule method.
3- Optimal results are achieved with the Earned Duration method for projects spanning
from 30% to 60% of the project duration.
Figure 31 Comparison Between Earned Duration vs Earned Schedule over the project duration Percentage.
0 % 5 % 1 0 % 1 5 % 2 0% 2 5 % 3 0 % 3 5 % 4 0 % 4 5 % 5 0 % 5 5 % 6 0% 6 5 % 7 0 % 7 5 % 8 0% 8 5 % 9 0 % 9 5 % 1 0 0 %
DURATION PERCENTAGE
COM PARISON BE TWEE N E AR NED DURATIO N VS EAR NED
SCHED U LE OVER THE P ROJ EC T DU RAT ION P ERC ENTAGE
Earned Duration Earned Schedule
4- Projects with a duration ranging from 65% to 70% are most appropriately managed
using the Earned Schedule method.
5- Between 70% and 100% of the project timeline, the Earned Duration method
demonstrates the highest efficiency.
Figure 32 depicts the overall outcome when the performance factor is set to 1.
Moreover, the thesis introduced a valuable guideline for selecting the most effective
technique based on project duration percentages. These recommendations aim to assist project
managers and practitioners in making well-informed decisions regarding the choice of
techniques for accurate project forecasting, particularly when employing the performance
factor SPI:
1. It is advisable to use the Earned Duration method for projects constituting 0% to 30%
of the total project timeline.
2. Projects with a duration falling within the 30% to 65% range of the total project timeline
are most suitable for the Earned Schedule method.
3. Optimal results are attained with the Earned Duration method for projects spanning
from 65% to 70% of the project duration.
4. Projects with a duration ranging from 70% to 75% are best managed using the Earned
Schedule method.
5. Between 75% and 100% of the project timeline, the Earned Duration method
demonstrates the highest efficiency.
Figure 32 Comparison Between Earned Duration vs Earned Schedule over the project duration Percentage.
0% 5% 1 0% 1 5% 2 0 % 2 5 % 3 0 % 3 5 % 40 % 4 5% 50 % 5 5 % 60 % 6 5% 70 % 7 5 % 8 0% 8 5 % 90% 9 5 % 1 0 0 %
DURATION PERCENTAGE
COM PARISON BE TWEE N E AR NED DURATIO N VS EAR NED
SCHED U LE OVER THE P ROJ EC T DU RAT ION PE RC ENTAGE AT
PF = 1
Earned Duration Earned Schedule
Figure 33 illustrates the overall outcome when the performance factor is configured to SPI.
The selection of techniques for precise project forecasting when utilizing the performance
factor SPI multiplied by CPI:
1. It is recommended to employ the Earned Duration method for projects encompassing
0% to 15% of the total project timeline.
2. Projects with a duration ranging from 15% to 55% of the total project timeline are most
appropriately managed using the Earned Schedule method.
3. Optimal outcomes are achieved with the Earned Duration method for projects spanning
from 55% to 60% of the project duration.
4. Projects with a duration falling within the 60% to 65% range are most effectively
handled through the Earned Schedule method.
5. Between 65% and 70% of the project timeline, the Earned Duration method
demonstrates the highest efficiency.
6. Within the 70% to 75% duration range, the Earned Schedule method exhibits the
highest efficiency.
7. For projects constituting 75% to 100% of the project timeline, the Earned Duration
method demonstrates the highest efficiency.
Figure
33
Comparison Between Earned Duration vs Earned Schedule over the project duration Percentage AT PF = SPI
.
0 % 5 % 1 0 % 1 5 % 2 0% 2 5 % 3 0 % 3 5 % 4 0 % 4 5 % 5 0% 5 5 % 60 % 6 5 % 7 0 % 7 5 % 8 0% 8 5 % 9 0 % 9 5 % 1 0 0%
DURATION PERCENTAGE
COMPARIS ON BE TW E EN EAR NED DURATION VS E AR NED
SC HE D ULE OVER THE P ROJEC T DU RATION PE RC EN TA GE AT
PF = S PI
Earned Duration Earned Schedule
Figure 34 depicts the overall outcome when the performance factor is set to SCI.
The analysis considered each technique based on three essential performance factors:
Performance Factor (PF) equal to 1, PF equal to Schedule Performance Index (SPI), and
PF equal to SPI multiplied by Cost Performance Index (CPI). The Average comparison
between the three methods is shown in figure 35.
Figure 35 Average comparison between Earned Schedule Vs Earned Duration Vs Planned Value
The findings from the projects indicate the following:
0 % 5 % 1 0 % 1 5 % 2 0% 2 5 % 3 0% 3 5 % 4 0 % 4 5 % 5 0 % 5 5 % 6 0 % 6 5 % 7 0 % 7 5% 8 0 % 8 5 % 9 0 % 9 5 % 1 0 0 %
DURATION PERCENTAGE
COM PARISON BE TWEE N E AR NED DURATIO N VS EAR NED
SCHED U LE OVER THE P ROJ EC T DU RAT ION PE RC ENTAGE AT
PF = SC I
Earned Duration Earned Schedule
Figure 34 Comparison Between Earned Duration vs Earned Schedule over the project duration Percentage AT PF = SCI.
60.00%
70.00%
80.00%
90.00%
100.00%
Accuracy
Duration Percentage
Average comparison between Earned Schedule Vs Earned
Duration Vs Planned Value
Earned Duration Earned Schedule Planned Value
1- When evaluating the performance factor (PF) as 1, or simply assessing whether projects
were completed on schedule without considering cost and schedule performance, the
Earned Duration method consistently emerged as the superior technique with 98.88%
very close to earned schedule percentage which is 98.71% as shown in figure 36.
2- Similarly, when focusing solely on the Schedule Performance Index (SPI), which
measures schedule adherence regardless of cost performance, the Earned Duration
method consistently displayed the highest accuracy as shown in figure 37.
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
Axis Title
Axis Title
Earned Schedule Vs Earned Duration Vs Planned Value at PF = 1
Earned Duration Earned Schedule Planned Value
Figure 36 Earned Schedule Vs Earned Duration Vs Planned Value at PF = 1
Figure 37 Earned Schedule Vs Earned Duration Vs Planned Value at PF = SPI
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
Axis Title
Axis Title
Earned Schedule Vs Earned Duration Vs Planned Value at PF = SPI
Earned Duration Earned Schedule Planned Value
3- Notably, when considering both schedule and cost performance together, represented
as PF = SPI x CPI, both the Earned Duration and Earned Schedule methods achieved
the same level of accuracy. This indicates that in scenarios where both schedule and
cost performance are vital considerations, these two methods provide equally reliable
results as shown in figure 38.
In a similar fashion, encompassing the project types, the subsequent outcomes were derived
from the examination of both industrial and commercial projects in table 4.
In industrial projects, the highest accuracy throughout the project duration is consistently
attained with the earned duration method, particularly when employing the performance factors
equal to SPI and one. In some instances, the earned schedule also emerges as a leading method.
Similarly, for commercial projects, the pattern is largely analogous to industrial projects, with
earned duration predominating in most phases of the project timeline. In the context of
educational projects, earned duration consistently secures the highest accuracy across a
significant portion of the project duration percentages, while earned schedule and planned
value take precedence in certain duration percentages. The overall outcomes are shown in table
4 which illustrates the methods and performance factors with highest accuracy according to
duration % and project industrial, commercial, and educational.
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
Axis Title
Axis Title
Earned Schedule Vs Earned Duration Vs Planned Value at PF =
SCI
Earned Duration Earned Schedule Planned Value
Figure 38 Earned Schedule Vs Earned Duration Vs Planned Value at PF = SCI
Table 5 Industrial, commercial, and educational projects comparison based on duration percentage.
Similarly, considering the various project types, the subsequent results were obtained through
an analysis of both educational and renovation projects in table above. Finally, incorporating
the project types, the following results were obtained through the examination of renovation
projects. However, it should be noted that this may not be a robust measure, as only one project
was utilized in this analysis in table 6.
Table 6 method and performance factors with highest accuracy according to duration
% and project type (Educational and Residential)
Duration %
Type PF
Method
Accuracy
Type PF Method
Accuracy
Type PF
Method
Accuracy
5% Industrial
1 ED 61.91% Commercial
SPI
ED
69.76%
Educational
SPI
ED
79.76%
10% Industrial
SPI
ES 72.08% Commercial
SPI
ED 69.47% Educational
SPI
ED 84.76%
15% Industrial
SPI
ED 72.61% Commercial
SPI
ES 72.77% Educational
1 ES 83.11%
20% Industrial
SPI
ES 80.72% Commercial
SPI
ED 76.12% Educational
SPI
ED 86.00%
25% Industrial
SPI
ES 78.88% Commercial
SPI
ED
82.09%
Educational
SPI
ED
89.50%
30% Industrial
1 ES 73.94% Commercial
SPI
ES 76.57% Educational
SPI
ED 92.70%
35% Industrial
SCI
ED 83.90% Commercial
SPI
ES 84.46% Educational
SCI
ED 95.53%
40% Industrial
1 ED 77.18% Commercial
SPI
ES 81.29% Educational
1 ED 89.95%
45% Industrial
1 ED 79.57% Commercial
SPI
ES
88.65%
Educational
1
ES
91.52%
50% Industrial
1 ED 79.23% Commercial
1 ED 82.67% Educational
1 ES 92.10%
55% Industrial
SPI
ES 82.36% Commercial
1 ED 85.18% Educational
1 ES 95.02%
60% Industrial
1 ED 80.55% Commercial
1 ED 86.10% Educational
1 PV 94.74%
65% Industrial
SPI
ED 86.97% Commercial
1 ED 88.94% Educational
1 PV 94.10%
70% Industrial
SPI
ED 88.86% Commercial
1 ED 90.93% Educational
1 PV 94.75%
75% Industrial
SPI
ED 89.96% Commercial
1
ED
91.56%
Educational
1
ED
95.32%
80% Industrial
SPI
ED 90.66% Commercial
1 ED 92.76% Educational
1 ES 97.54%
85% Industrial
SCI
ES 93.80% Commercial
1 ED 93.50% Educational
SCI
ED 96.34%
90% Industrial
SPI
ED 93.98% Commercial
1 ED 93.10% Educational
SCI
ES 98.20%
95% Industrial
SPI
ED 96.61% Commercial
1
ED
96.05%
Educational
S
CI
ES
97.67%
100% Industrial
SCI
ES 99.18% Commercial
SCI
ED 98.58% Educational
SCI
ED 98.98%
Duration
% Type PF Method
Accuracy
Accuracy
Type PF Method
Accuracy
5%
Residential
SPI
ED
77.52%
10%
Renovation
1
ES
93.43%
10%
Residential
SCI
ES
85.39%
15%
Renovation
1
ES
93.45%
15%
Residential
SPI
ED
79.52%
20%
Renovation
1
ES
93.46%
20%
Residential
SPI
ED
84.59%
25%
Renovation
1
ES
99.86%
25%
Residential
SPI
ED
94.52%
30%
Renovation
1
ES
93.46%
30%
Residential
SPI
ES
89.02%
40%
Renovation
1
ES
97.84%
35%
Residential
SPI
ED
93.73%
45%
Renovation
1
ES
97.79%
40%
Residential
SPI
ES
97.27%
50%
Renovation
1
ES
99.94%
45%
Residential
SPI
ES
95.36%
55%
Renovation
SCI
ED
99.10%
50%
Residential
SPI
ES
95.55%
60%
Renovation
SCI
ED
99.85%
55%
Residential
1
ED
92.48%
65%
Renovation
1
ES
99.94%
60%
Residential
1
ES
91.68%
75%
Renovation
1
ES
99.87%
65%
Residential
1
ES
92.76%
80%
Renovation
1
ES
99.97%
70%
Residential
1
ES
93.53%
85%
Renovation
1
ES
97.84%
Table 6 Residential and renovation comparison based on duration percentage.
Ultimately, by integrating the various project types, the subsequent results were derived
through the comprehensive analysis of all projects, excluding consideration of specific project
types. In general, the earned duration method proves to be the most effective throughout nearly
the entire project duration. Concerning performance factors, it is generally advisable to utilize
the schedule performance index (SPI) for up to approximately 50% of the project duration.
Subsequently, employing the performance factor equal to 1 emerges as the preferred approach
to attain optimal results.
In conclusion to the discussion chapter, future research directions could involve
implementing the identified findings and assessing their accuracy. A valuable avenue for
exploration would be to compare the outcomes of this study with subsequent measurements,
75%
Residential
1
ES
94.49%
90%
Renovation
SCI
ES
99.26%
80%
Residential
1
ES
95.45%
95%
Renovation
SCI
ED
98.13%
85%
Residential
1
ES
91.32%
100%
Renovation
1
ES
100.00%
90%
Residential 1 ED 94.95%
95%
Residential 1 ED 95.05%
100%
Residential 1 ED 96.68%
Duration
% PF Method
Accuracy
5%
SPI
ED
68.36%
10%
SPI
ED
74.25%
15%
SPI
ED
73.59%
20%
SPI
ED
77.84%
25%
SPI
ED
83.64%
30%
SPI
PV
79.74%
35%
SPI
PV
84.19%
40%
SPI PV 83.66%
45%
SPI PV 85.48%
50%
1 ED 84.08%
55%
1
ED
86.16%
60%
1
ED
86.35%
65%
1
ED
88.42%
70%
1 ED 90.05%
75%
1 ED 91.47%
80%
1 ED 92.60%
85%
1 ED 92.96%
90%
1 ED 93.79%
95%
1 ED 96.22%
100%
1 ED 98.42%
Table 7 Overall Projects highest accuracy achieved based on duration percentage.
analyzing any differences in accuracy between the initial and subsequent results. Additionally,
while the study delved into various EVM techniques and highlighted their limitations, future
research might explore alternative approaches for comparison.
Moreover, the study raises questions about the continued reliance on EVM,
emphasizing the need for proper improvements to potentially enhance the application of these
techniques in upcoming construction projects. It is worth noting that the research did not
address the construction of a model for future estimations, leaving room for further
investigation in this area.
The next chapter, Conclusion, will serve as the culmination of this research journey,
summarizing the essential discoveries, outlining practical implications, and suggesting avenues
for further exploration. Our exploration of EVM within the construction landscape will come
full circle, providing a comprehensive understanding that bridges theory and practice.
Chapter 6: Conclusion
the implementation of EVM within the Egyptian construction industry presents notable
challenges pertaining to application, accuracy, and result interpretability. Despite these
challenges, there exists a significant opportunity to leverage technological advancements and
develop a refined, controlled EVM approach that can markedly enhance project management
practices.
This research aims to contribute to this enhancement by conducting a thorough
evaluation of Earned Duration, Earned Schedule, and Planned Value methods in the context of
a diverse array of 30 construction projects across various sectors in Egypt. Spanning
commercial, educational, industrial, renovation, and residential domains, these projects were
analyzed for their accuracy in forecasting completion dates, with a focus on identifying the
most efficient method based on project duration percentages.
The comprehensive study covered a significant timeframe, from January 15, 2015, to
December 30, 2023, providing a robust foundation for the findings. Notably, the Earned
Duration method emerged as the most accurate technique across multiple metrics, including
average accuracy, performance factors set to 1 and SPI. However, under the performance factor
set to SCI, both Planned Duration and Earned Schedule surpassed Earned Duration,
emphasizing the need for nuanced considerations in method selection.
While Earned Duration consistently proved effective for industrial, commercial, and
educational projects, the Earned Schedule method outperformed in renovation and residential
contexts. The thesis not only shed light on the most accurate methods but also provided
practical guidelines for selecting techniques based on project duration percentages, offering
valuable insights for project managers in the Egyptian construction sector. The introduced
guidelines, tailored to different performance factors, serve as a roadmap for informed decision-
making, contributing to improved project forecasting accuracy and overall project management
practices. The applicability of these recommendations underscores the importance of aligning
the choice of technique with the unique characteristics of each construction project, thus
enhancing the reliability and efficiency of the forecasting process.
Furthermore, the investigation prompts inquiries regarding the ongoing dependence on
EVM, underscoring the necessity for substantial enhancements to potentially elevate the
efficacy of these techniques in forthcoming construction projects. Importantly, it is essential to
highlight that the study did not encompass projects beyond the geographical scope of Egypt.