Critical path method problems

profilegunnala
Works.xlsx

Sheet1

1 Q)
Draw the network. Compute ESs, EFs, LSs, LFs, and total slack times.
Estimate headcounts for each activity and estimate activity cost along with the overall project cost at completion.
Assume your hourly or per day headcount rates
2Q)
Draw the network. Compute ESs, EFs, LSs, LFs, and total slack times.
Estimate headcounts for each activity and estimate activity cost along with the overall project cost at completion.
Assume your hourly or per day headcount rates
3Q)
Draw the network. Compute ESs, EFs, LSs, LFs, and total slack times.
Estimate headcounts for each activity and estimate activity cost along with the overall project cost at completion.
Assume your hourly or per day headcount rates
4Q)
Draw the network. Compute ESs, LSs, and total slack times.
Estimate headcounts for each activity and estimate activity cost along with the overall project cost at completion.
5Q) Draw the network. Compute ESs, LSs, and total slack times.
Estimate headcounts for each activity and estimate activity cost along with the overall project cost at completion.
Activity J M V Y L Q Z
Predecessors J M V J L Y, Q
Duration (weeks) 6 4 6 8 2 8 2
Systems Analysts (weekly) 8 5 3 2 5 3 5
Programmers (weekly) 3 4 2 3 3 2 3
Do the 5th question in 2 formats

Sheet2

Sheet3

image1.png

image2.png

image3.png

image4.png