PM Comm Plan

profileSbrain1722
workbreakdownstructure1.xlsx

Sheet3

Project Name Family House Project Project # 141
Project Manager's Name Joseph Dunhill Sponsor 0
Project Timeframe 6 Months Updated 2.2.2020
Project Stages WBS Code Task/ Deliverables Dependencies Status
Author: Options are: Open Closed
Effort Hours
Needs/ Requirements Assessment 1 Site Investigation ID #1 Complete 42
2 Detailed Planning #2 Not Complete 43
3 Identifying Labor Requirements #3 Complete 67
4 Identifying Machine and Technology Requirements #4 Not Complete 87
5 Assessing Financial Needs/ Requirements #5 Complete 30
6 Determining the Time Needed #5 Complete 30
7 Assessing the Building materials Requirements #6 Complete 30
Design and Analysis 8 Detailed Design #7 Complete 30
9 Architectural Design #8 Complete 30
10 Drawing the Plan #9 Not Complete 30
Development Phase 11 Preparation of site #10 Not Complete 35
12 Relocating services #11 Not Complete 35
13 Piling (stakes) #12 Not Complete 35
14 Constructing foundation #13 Not Complete 35
15 Erecting pylons #14 Not Complete 46
16 Filling the concretes #15 Not Complete 46
17 Assessing the building materials Requirements #16 Complete 45
18 Detailed design #17 Complete 47
19 Architectural design #18 Complete 49
20 Drawing the plan #19 Not Complete 50
21 Design approval #20 Not Complete 50
Completion and Implementation 22 Preparation of site #21 Not Complete 52
23 Relocating services #22 Not Complete 54
24 Piling (stakes) #23 Not Complete 56
25 Constructing foundation #24 Not Complete 58
26 Erecting pylons #25 Not Complete 59
Testing 27 Filling the concretes #26 Not Complete 61
28 Assessing the building materials requirements #27 Complete 63
29 Detailed design #28 Complete 65
30 Architectural design #29 Complete 67
Repair and Maintenance 31 Drawing the plan #30 Not Complete 68
32 Preparation of site #31 Not Complete 70
33 Relocating services #32 Not Complete 72
34 Piling (stakes) #33 Not Complete 74