PM Comm Plan
Sheet3
| Project Name | Family House Project | Project # | 141 | ||
| Project Manager's Name | Joseph Dunhill | Sponsor | 0 | ||
| Project Timeframe | 6 Months | Updated | 2.2.2020 | ||
| Project Stages | WBS Code | Task/ Deliverables | Dependencies | Status Author: Options are: Open Closed | Effort Hours |
| Needs/ Requirements Assessment | 1 | Site Investigation | ID #1 | Complete | 42 |
| 2 | Detailed Planning | #2 | Not Complete | 43 | |
| 3 | Identifying Labor Requirements | #3 | Complete | 67 | |
| 4 | Identifying Machine and Technology Requirements | #4 | Not Complete | 87 | |
| 5 | Assessing Financial Needs/ Requirements | #5 | Complete | 30 | |
| 6 | Determining the Time Needed | #5 | Complete | 30 | |
| 7 | Assessing the Building materials Requirements | #6 | Complete | 30 | |
| Design and Analysis | 8 | Detailed Design | #7 | Complete | 30 |
| 9 | Architectural Design | #8 | Complete | 30 | |
| 10 | Drawing the Plan | #9 | Not Complete | 30 | |
| Development Phase | 11 | Preparation of site | #10 | Not Complete | 35 |
| 12 | Relocating services | #11 | Not Complete | 35 | |
| 13 | Piling (stakes) | #12 | Not Complete | 35 | |
| 14 | Constructing foundation | #13 | Not Complete | 35 | |
| 15 | Erecting pylons | #14 | Not Complete | 46 | |
| 16 | Filling the concretes | #15 | Not Complete | 46 | |
| 17 | Assessing the building materials Requirements | #16 | Complete | 45 | |
| 18 | Detailed design | #17 | Complete | 47 | |
| 19 | Architectural design | #18 | Complete | 49 | |
| 20 | Drawing the plan | #19 | Not Complete | 50 | |
| 21 | Design approval | #20 | Not Complete | 50 | |
| Completion and Implementation | 22 | Preparation of site | #21 | Not Complete | 52 |
| 23 | Relocating services | #22 | Not Complete | 54 | |
| 24 | Piling (stakes) | #23 | Not Complete | 56 | |
| 25 | Constructing foundation | #24 | Not Complete | 58 | |
| 26 | Erecting pylons | #25 | Not Complete | 59 | |
| Testing | 27 | Filling the concretes | #26 | Not Complete | 61 |
| 28 | Assessing the building materials requirements | #27 | Complete | 63 | |
| 29 | Detailed design | #28 | Complete | 65 | |
| 30 | Architectural design | #29 | Complete | 67 | |
| Repair and Maintenance | 31 | Drawing the plan | #30 | Not Complete | 68 |
| 32 | Preparation of site | #31 | Not Complete | 70 | |
| 33 | Relocating services | #32 | Not Complete | 72 | |
| 34 | Piling (stakes) | #33 | Not Complete | 74 | |