Project Management Framework Final
PROJECT
PERFORMANCE
MANAGEMENT AND
CLOSURE
2GRANTHAM.EDU |
PROJECT MONITORING INFORMATION SYSTEM
Creating a project monitoring system involves determining
What data to collect
How, when, and who will collect the data
How to analyze the data
How to report current progress to management
What data are collected?
Current status of project (schedule and cost)
Remaining cost to compete project
Date that project will be complete
Potential problems to be addressed now
Out-of-control activities requiring intervention
Cost and/or schedule overruns and the reasons for them
Forecast of overruns at time of project completion
3GRANTHAM.EDU |
PROJECT MONITORING INFORMATION SYSTEM –
CONT’D
Collecting data and analysis
Who will collect project data?
How will data be collected?
When will the data be collected?
Who will compile and analyze the data?
Reports and reporting
Who will receive the reports?
How will the reports be transmitted?
When will the reports be distributed?
4GRANTHAM.EDU |
SAMPLE PROJECT PROGRESS REPORT
FORMAT
5GRANTHAM.EDU |
PROJECT CONTROL PROCESS
Control
The process of comparing actual performance against plan to
identify deviations, evaluate courses of action, and take
appropriate corrective action.
Project Control Steps
Setting a baseline plan.
Measuring progress and performance.
Comparing plan against actual.
Taking action.
Tools
Tracking and baseline Gantt charts
Control charts
6GRANTHAM.EDU |
DEVELOPING AN INTEGRATED COST/SCHEDULE
SYSTEM
Define the work using a WBS.
Scope
Work packages
Deliverables
Organization units
Resources
Budgets
Develop work and resource schedules.
Schedule resources
to activities
Time-phase work packages into a network
Develop a time-phased budget using work packages included in an activity. Accumulate budgets (PV).
At the work package level, collect the actual costs for the work performed (AC). Multiply percent complete times original budget (EV)
Compute the schedule variance (EV-PV) and the cost variance (EV-AC).
7GRANTHAM.EDU |
DEVELOPMENT OF PROJECT BASELINES
Purposes of a Baseline (PV)
An anchor point for measuring performance
A planned cost and expected schedule against which actual cost and schedule are measured.
A basis for cash flows and awarding progress payments.
A summation of time-phased budgets (cost accounts as summed work packages) along a project timeline.
What Costs Are Included in Baselines?
Labor, equipment, materials, project direct overhead costs (DOC)
Rules for Placing Costs in Baselines
Costs are placed exactly as they are expected to be “earned” in order to
track them to their point of origin.
Percent Complete Rule
Costs are periodically assigned to a baseline as units of work are completed over the duration of a work package.
8GRANTHAM.EDU |
METHODS OF VARIANCE ANALYSIS
Comparing Earned Value
With the expected schedule value.
With the actual costs.
Assessing Status of a Project
Required data elements
Data Budgeted cost of the work scheduled (PV)
Budgeted cost of the work completed (EV)
Actual cost of the work completed (AC)
Calculate schedule and cost variances
A positive variance indicates a desirable condition, while a negative variance suggests problems or changes that have taken place.
Cost Variance (CV)
Indicates if the work accomplished using labor and materials costs more or less than was planned at any point in the project.
Schedule Variance (SV)
Presents an overall assessment in dollar terms of the progress of all work packages in the project scheduled to date.
9GRANTHAM.EDU |
COST/SCHEDULE GRAPH
10GRANTHAM.EDU |
INDEXES TO MONITOR PROGRESS
Performance Indexes
Cost Performance Index (CPI)
Measures the cost efficiency of work accomplished to date.
CPI = EV/AC
Scheduling Performance Index (SPI)
Measures scheduling efficiency
SPI = EV/PV
Percent Complete Indexes
Indicates how much of the work accomplished represents of the total
budgeted (BAC) and actual (AC) dollars to date.
PCIB = EV/BAC
PCIC = AC/EAC
11GRANTHAM.EDU |
FORECASTING FINAL PROJECT COST
Methods used to revise estimates of future project costs:
EACre Allows experts in the field to change original baseline durations and costs because new
information tells them the original estimates are not accurate.
EACf Uses actual costs-to-date plus an efficiency index to project final costs in large projects where the
original budget is unreliable.
EACf = ETC + AC
EAC = Work Remaining / CPI
= (BAC – EV) / (EV/AC)
Where EACf : Estimated total cost at completion ETC : Estimated cost to completing remaining work AC : cumulative actual cost of work completed to date CPI : cumulative cost index to date BAC : total budget of the baseline EV : cumulative budgeted cost of work completed to date
12GRANTHAM.EDU |
MAJOR TASKS OF PROJECT CLOSURE
Evaluate if the project delivered the expected benefits to all
stakeholders.
Was the project managed well?
Was the customer satisfied?
Assess what was done wrong and what contributed to
successes.
Identify changes to improve the delivery of future projects.
13GRANTHAM.EDU |
PROJECT CLOSURE
Types of Project Closure
Normal
Premature
Perpetual
Failed Project
Changed Priority
Close-out Plan: Questions to be Asked
What tasks are required to close the project?
Who will be responsible for these tasks?
When will closure begin and end?
How will the project be delivered?
14GRANTHAM.EDU |
RETROSPECTIVES
Lessons Learned
An analysis carried out during and shortly after the project life cycle to
capture positive and negative project learning—“what worked and what
didn’t?”
Goals of Retrospectives
To reuse learned solutions
To stop repetitive mistakes
Barriers to Organizational Learning
Lack of post-project time for developing lessons
No post-project direction or support for teams
Lessons become blame sessions
Lessons are not applied in other locations
Organizational culture does not recognize
value of learning
15GRANTHAM.EDU |
REFERENCES
Anbari, F. T., “Earned Value Project Management Method and Extensions,” Project
Management Journal, vol. 34, no. 4 (December 2003), pp. 12–22.
Bowles, M. “Keeping Score,” PMNetwork, May 2011, pp. 50–59.
Brandon, D. M., Jr., “Implementing Earned Value Easily and Effectively,” Project
Management Journal, vol. 29, no. 3 (June 1998), pp. 11–17.
Cooke-Davies, T., “Project Management Closeout Management: More than Simply
Saying Good Bye and Moving On,” in J. Knutson (Ed.), Project Management for
Business Processionals (Indianapolis, IN: John Wiley and Sons, 2001), pp. 200–14.
Fretty, P., “Why Do Projects Really Fail?” PM Network, March 2006, pp. 45–48
Kerth, Norman L., Project Retrospectives: A Handbook for Team Reviews (New York:
Dorset House, 2001).
16GRANTHAM.EDU |
GLOSSARY OF TERMS