Bugs vs. Feature Requests

profilemackey66
Wk2pt2.docx

CMGT/410 v19

Title

ABC/123 vX

Page 2 of 2

C:\Users\djshirey\OneDrive - University of Phoenix\F_Drive\Style Guides\UPX Logos\Horizontal format\UOPX_Sig_Hor_Black_Medium.pngWork Breakdown Structure (WBS)

Project estimate: 200 hours: Mobile Inventory Management System

Name Mobile inventory management system

Duration

Mobile app plan

272 hours

1

Project set-up

56

1.1

assess user requirements

16 hours

1.2

Set up working environment

32 hours

1.3

Determine initial sprint velocity

8 hours

1.4

budget allocation to sprints

2 hours

1.5

select project tem

8 hours

1.6

Project setup complete

2 hours

2

Sprint 1 User interface

48 hours

2.1

Sprint 1 plan

4 hours

2.1.1

Select sprint 1 user stories

2 hours

2.1.2

Assign user stories

2 hours

2.1.3

Sprint 1 plan complete

1 hours

2.2

User Interface

40 hours

2.2.1

Design User Interface

16 hours

2.2.2

Build User Interface

16 hours

2.2.3

Test User Interface

8 hours

2.2.4

UAT of user Interface

8 hours

2.2.5

Correct Issues From UAT UI

8 hours

3

Sprint 2 functionalities implementation

80 hours

3.1

Sprint 2 plan

32 hours

3.1.1

selecting sprint 2 stories

16 hours

3.1.2

Assign user stories

8 hours

3.1.3.

Sprint 2 completion

8 hours

3.2

Testing product modules functionalities

48 hour

3.2.1

Developing functionalities

24 hours

3.2.2

Testing programs

16 hours

3.2.3

Approval

8 hours

4

Sprint 3 project reports

120 hours

4.1

Sprint 3 plan

4 hours

4.1.1

Select sprint 3 user stories

2 hours

4.1.2

Assign user stories

2 hours

4.1.3

Sprint 3 plan completion

1 hour

4.2

Client Specified Reports

54 hours

4.2.1

Design Reports

16 hours

4.2.2

Build Reports

16 hours

4.2.3

Test Reports

16 hours

4.2.4

UAT of Reports

8 hours

4.2.5

Correcting of Issues From UAT of Reports

8 hours

5

Sprint 4 Platform

54 hours

5.1

Sprint 4 plan

16 hours

5.1.1

Select sprint 4 user stories

16 hours

5.1.2

Assign user stories

16 hours

5.1.3

Sprint 4 plan completion

1 hour

5.2

Cross Platform Support

48 hours

5.2.1

Design Cross Platform Support

16 hours

5.2.2

Build Cross Platform Support

16 hours

5.2.3

Test Cross Platform Support

16 hour

5.2.4

UAT of Cross Platform Support

8 hours

6

Project End

16 hours

6.1

client signing off

8 hours

6.2

issue project report

4 hours

6.3

Project End

4 hours