Bugs vs. Feature Requests
CMGT/410 v19
Title
ABC/123 vX
Page 2 of 2
Work Breakdown Structure (WBS)
Project estimate: 200 hours: Mobile Inventory Management System
|
|
Name Mobile inventory management system |
Duration |
|
|
Mobile app plan |
272 hours |
|
1 |
Project set-up |
56 |
|
1.1 |
assess user requirements |
16 hours |
|
1.2 |
Set up working environment |
32 hours |
|
1.3 |
Determine initial sprint velocity |
8 hours |
|
1.4 |
budget allocation to sprints |
2 hours |
|
1.5 |
select project tem |
8 hours |
|
1.6 |
Project setup complete |
2 hours |
|
2 |
Sprint 1 User interface |
48 hours |
|
2.1 |
Sprint 1 plan |
4 hours |
|
2.1.1 |
Select sprint 1 user stories |
2 hours |
|
2.1.2 |
Assign user stories |
2 hours |
|
2.1.3 |
Sprint 1 plan complete |
1 hours |
|
2.2 |
User Interface |
40 hours |
|
2.2.1 |
Design User Interface |
16 hours |
|
2.2.2 |
Build User Interface |
16 hours |
|
2.2.3 |
Test User Interface |
8 hours |
|
2.2.4 |
UAT of user Interface |
8 hours |
|
2.2.5 |
Correct Issues From UAT UI |
8 hours |
|
3 |
Sprint 2 functionalities implementation |
80 hours |
|
3.1 |
Sprint 2 plan |
32 hours |
|
3.1.1 |
selecting sprint 2 stories |
16 hours |
|
3.1.2 |
Assign user stories |
8 hours |
|
3.1.3. |
Sprint 2 completion |
8 hours |
|
3.2 |
Testing product modules functionalities |
48 hour |
|
3.2.1 |
Developing functionalities |
24 hours |
|
3.2.2 |
Testing programs |
16 hours |
|
3.2.3 |
Approval |
8 hours |
|
4 |
Sprint 3 project reports |
120 hours |
|
4.1 |
Sprint 3 plan |
4 hours |
|
4.1.1 |
Select sprint 3 user stories |
2 hours |
|
4.1.2 |
Assign user stories |
2 hours |
|
4.1.3 |
Sprint 3 plan completion |
1 hour |
|
4.2 |
Client Specified Reports |
54 hours |
|
4.2.1 |
Design Reports |
16 hours |
|
4.2.2 |
Build Reports |
16 hours |
|
4.2.3 |
Test Reports |
16 hours |
|
4.2.4 |
UAT of Reports |
8 hours |
|
4.2.5 |
Correcting of Issues From UAT of Reports |
8 hours |
|
5 |
Sprint 4 Platform |
54 hours |
|
5.1 |
Sprint 4 plan |
16 hours |
|
5.1.1 |
Select sprint 4 user stories |
16 hours |
|
5.1.2 |
Assign user stories |
16 hours |
|
5.1.3 |
Sprint 4 plan completion |
1 hour |
|
5.2 |
Cross Platform Support |
48 hours |
|
5.2.1 |
Design Cross Platform Support |
16 hours |
|
5.2.2 |
Build Cross Platform Support |
16 hours |
|
5.2.3 |
Test Cross Platform Support |
16 hour |
|
5.2.4 |
UAT of Cross Platform Support |
8 hours |
|
6 |
Project End |
16 hours |
|
6.1 |
client signing off |
8 hours |
|
6.2 |
issue project report |
4 hours |
|
6.3 |
Project End |
4 hours |