Project Status Summary (Percentage Complete: 5%) :

• After meeting with our Advisor, we have decided to change focus a little this week. We have decided to go full force on developing the game itself. All members have been working hard on learning and building Chess in Unity. A small amount of progress has been made on the web application, however, we have decided that we may want to wait to design the website until we have a working copy of the chess game to place there. With help from our advisor, we have found a few Chess AI engines and plan to use Stockfish. We are creating a GUI that communicates with Stockfish using the UCI protocol.

Lab Time and Accomplishments this week built on last week’s work

• No Lab Time this week.

• Learned more about Unity as well as well as continued to make chess game

• Investigated webgl for reactjs

• All members setup the code for our chess repo

• Investigated Stockfish and other chess engines

• Learning languages for this project (C#, Unity, JavaScript)

Next week’s SMART goals:

• Setup WebGL and other packages (webpack, babel... etc) on the web application. (Michael)

• Learn more about game development with Unity and C# (Michael, Ali, Izabella)

• Continue writing Chess application in Unity (Robert, Izabella, Michael, Ali).

• Continue researching stockfish and other chess engines for our game (Izabella).

• Begin design our UI for the website and assets (Izabella, Ali)

Action Plan (task responsibility, timing, help needed):

• Learn more about Unity and chess game development • Learn more about Stockfish and other Chess Engines

• Start Design chess game UML diagram

• Continue creating the base chess game

• Get the web application ready to receive and host the chess game

Open Issues, Risks, Change Requests:

• Finalizing choices of technologies/frameworks that will be used in project

Milestones and Deliverables:

Milestones /

Deliverables

Planned Date

Forecasted Date

Actual Date

Status

Note

First prototype of web application

2/6

2/13

2/27

Off schedule

We need the first prototype of the chess game to have this prototype

First Chess Game

2/6

2/20

N/A

On schedule

Design graph of Architecture

2/6?

2/6

N/A

On schedule

We have a small design already made, and need to extrapolate

Deliverables:

Figure 1: Level 0/1 Design of Architecture

* Examples adapted from CREG 257/258 at Lehigh University