Week 8 Assignment
Question 1
List and briefly describe the six main processes involved in project integration management.
Question 2
Which of the following techniques led to the acceptance of project management principles?
|
|
a. |
Ineffectiveness of over-the-fence management |
|
|
b. |
Six Sigma |
|
|
c. |
Total quality management |
|
|
d. |
The need for better management of smaller projects |
Question 3
All of the stakeholders involved in a project either directly or indirectly may have a different definition of project success.
True
False
Question 4
Scope creep is generally the result of:
|
|
a. |
Having the wrong people assigned to the project |
|
|
b. |
Too much detail in the specifications |
|
|
c. |
Having too many levels in the WBS |
|
|
d. |
A poorly defined SOW |
Question 5
The person with the ultimate responsibility to make sure that all work required by the SOW and only the work required by the SOW is performed is the:
|
|
a. |
Project sponsor |
|
|
b. |
Appropriate subject matter expert for that work package |
|
|
c. |
Project manager |
|
|
d. |
Customer |
Question 6
In which of the following schedule compression techniques is the cost of rework usually the greatest?
|
|
a. |
Performing series work in parallel |
|
|
b. |
Crashing |
|
|
c. |
Overtime |
|
|
d. |
Outsourcing |
Question 7
In which life cycle phase is the total project risk generally the least?
|
|
a. |
Planning |
|
|
b. |
Initiation/approval |
|
|
c. |
Closure |
|
|
d. |
Execution |
Question 8
Which of the following type of authority would come from the project manager's job description?
|
|
a. |
De facto |
|
|
b. |
Project manager |
|
|
c. |
De jure |
|
|
d. |
Implied |
Question 9
Which of the following types of interpersonal influences would be representative of workers that are attracted to a particular project?
|
|
a. |
Legitimate power |
|
|
b. |
Reward power |
|
|
c. |
Expert power |
|
|
d. |
Referent power |
Question 10
If the schedule variance is positive and the cost variance is negative, the project's status is:
|
|
a. |
Over budget and ahead of schedule |
|
|
b. |
Under budget and behind schedule |
|
|
c. |
Over budget and behind schedule |
|
|
d. |
Under budget and ahead of schedule |