Procurement Contracts and Statement of Work
PM5018 Project Procurement Analysis
Project Procurement Analysis
1. Project Scope Statement
1.1 Version History
|
Version |
Date |
Approver |
Changes Made |
|
1.0 |
3/25/2024 |
[Name] |
Initial Project Scope Statement |
|
1.01.0 |
3/25/2024 |
[Name] |
Approved Project Scope |
1.2 Project Name
Project Name: Project NEO Prepared by: Marlvetta Lewis Date (MM/DD/YYYY): 10/25/2024
1.3 Executive Summary
The project scope involves designing an employee orientation module accessible via the company Intranet for new employee orientations. This module includes presentations, quizzes, and sign-offs, with successful testing and acceptance by the Human Resource department.
1.4 Business Objectives
1.4.1 Product Description (Solution)
A NearlyFree.com New Employee Orientation Module for the Human Resource department, accessed through the company Intranet. New employees will review presentations, take a quiz, and sign off on the orientation process.
1.4.2 Business Objectives
Automate new employee orientation by providing electronic documentation for presentations and maintaining a database to track and document completed orientations.
2. Project Description
2.1 Project Scope
2.1.1 Includes (list Deliverables)
· Design a web-based Human Resource module for new employee orientations.
· Integrate HR module with the company Intranet.
· Migrate existing hard copy presentations into electronic format.
· Create a quiz to assess new employees on their understanding of HR processes.
· Create electronic sign-off for a successfully completed orientation.
· Create online help for new employees during the orientation process.
· Provide documentation to the HR department for future changes to the orientation material.
2.1.2 Does Not Include
The scope does not include anything beyond maintaining the website.
2.2 External Dependencies
All project requirements, including hard copy documents, will be promptly provided by Cheryl Gladstone.
2.3 Assumptions
All necessary hardware and software are in place. The NearlyFree.com Employee Orientation module will be created and integrated into the HR section of the Intranet.
2.4 Constraints
No new requirements can be added by sponsors without affecting the project timeline and budget.
3. Project Milestones
|
Milestone |
Target Date |
|
Project Start |
3/09/2024 |
|
Project Charter |
3/09/2024 |
|
Work Breakdown Structure |
3/19/2024 |
|
Project Scope Statement |
3/26/2024 |
|
Project Schedule |
4/01/2024 |
|
Responsibility Assignment Matrix |
4/06/2024 |
|
Project Schedule Resources |
4/09/2024 |
|
Project Cost Estimate |
4/16/2024 |
|
Project Quality Statement |
4/23/2024 |
|
Stakeholder Analysis |
4/28/2024 |
|
Communication Plan |
4/30/2024 |
|
Risk Matrix |
5/07/2024 |
|
Final Project Plan |
5/13/2024 |
|
Software Orientation Learning Module Complete |
6/18/2024 |
|
Final Integration Testing Complete |
6/17/2024 |
|
Documentation provided to HR department |
6/21/2024 |
|
Training HR on new module complete |
6/21/2024 |
|
Project Complete |
6/21/2024 |
|
Post Mortem Lessons Learned |
6/22/2024 |
4. Project Approach
4.1 Primary Plans
The NearlyFree.com project will have formal written plans for:
· Project schedule.
· Cost estimate.
· Responsibility Assignment Matrix.
· Quality Statement.
· Communication Plan.
· Risk Analysis.
· Change Management.
4.2 Project-Specific
4.2.1 Change Management
Change control procedures include:
· Change Request Log establishment.
· Assessment of Change Requests.
· Review and approval by the project owner.
· Reflection of approved Change Requests' effects on the scope and schedule.
· Update of the Change Request Log.
4.2.2 Communication Management
Strategies for effective communication include:
· Weekly project status presentations to sponsors.
· Monthly written status reports to sponsors.
· Urgent issue notifications via email.
· Weekly update and status meetings for the project team.
· Central storage for all electronic Project Documents.
4.2.3 Resource Management
The Resource Management Plan will include:
· Lists of major goods and services.
· Indication of external sources for goods and services.
· Assignment of project team members and schedule.
5. Authorizations
5.1 Project Scope Statement Approval / Signatures
Project Name: NEO Project Project Manager: Marlvetta Lewis
|
Name |
Role |
Signature |
Date |
|
Marlvetta Lewis |
Project Manager |
e-sig |
4/01/2024 |
|
Jennifer Beal |
Project Sponsor |
e-sig |
4/01/2024 |
|
Cheryl Gladstone |
HR Manager |
e-sig |
4/01/2024 |
The signatures above indicate an understanding of the purpose and content of this document. By signing, they agree to this as the formal Project Scope Statement document.
5.2 Quality Statement
To: Jennifer Beal, Alice Yee, Cheryl Gladstone, John Sachs, and Tom Johansen From: Marlvetta Lewis Re: NearlyFree.com NEO Project Quality Statement
PMO Quality Management Discipline and Policies
The PMO upholds the IT Service Oriented Architecture and Enterprise, providing a framework for IT-related activities. The NEO Project will implement and abide by PMO Quality Policies.
Ensuring Process Quality
· Detailed documentation of the development process.
· Regular program code test and review meetings.
· Exit phase meetings for documentation and lessons learned.
· Regular internal audits for IT processes, Finance, and Human Resources.
Quality Control
Testing Techniques
· Expert Review.
· Inspections.
· Audits.
Testing Cycles
· Unit testing.
· Integration testing.
· System testing.
· User acceptance testing.
Conclusion
The NEO Project will comply with PMO quality policies and guidelines, ensuring all project team members adhere to strict policies and guidelines.
| Marlvetta Lewis | Signed by PM |
6. Cost Estimate
6.1 Task Name
|
Task Name |
Fixed Cost |
Total Cost |
Baseline Cost |
Cost Variance |
Actual Cost |
Remaining Cost |
|
NearlyFree Employee Orientation Project |
$0.00 |
$30,380.00 |
$22,300.00 |
$8,080.00 |
$20,453.95 |
$9,926.05 |
|
|
|
|
|
|
|
|