· Use the table below to complete the items above.
|
Description |
Quantity Needed |
Unit Cost |
Comment |
|
Call Box |
To be calculated |
$1200 per box |
Material cost. There should be one call box every .25 acres. |
|
Wiring Harness |
1 unit per box |
$25 per box |
Material cost to be applied to each installed box. |
|
Installation Hardware Kit |
1 unit per box |
$20 per box |
Material cost to be applied to each installed box. |
|
Internal Labor |
200 hours per project |
$100 per hour |
Labor rate for each project team member. |
|
External Labor |
Site preparation per box |
$200 per box |
Supplier labor rate to prepare location for each box. |
|
External Labor |
Installation & testing per box |
$150 per box |
Supplier labor rate to complete installation and testing for each box. |
· Include a WBS created in MS Project which will define project cost estimates.
· Calculations should be done using formulas within Project, rather than by hand.