Start: 9/2/19 ID: 1

Finish: 9/13/19 Dur: 2 wks

Res: Maketing team

Project scope definition

Start: 9/16/19 ID: 2

Finish: 9/16/19 Dur: 0.2 wks?

Res: Maketing team

Requirement definition

Start: 9/17/19 ID: 3

Finish: 9/17/19 Dur: 0.2 wks?

Res: Maketing team

Cost estimation

Start: 9/18/19 ID: 4

Finish: 9/18/19 Dur: 0.2 wks?

Res: Financial Team

Scheduling

Start: 9/19/19 ID: 5

Finish: 9/19/19 Dur: 0.2 wks?

Res: Maketing team

Risk Analysis

Start: 9/20/19 ID: 6

Finish: 9/20/19 Dur: 0.2 wks?

Res: Maketing team

Project Feasibility

Start: 9/23/19 ID: 7

Finish: 9/23/19 Dur: 0.2 wks?

Res: Maketing team

Project Plan

Start: 9/24/19 ID: 8

Finish: 9/24/19 Dur: 0.2 wks?

Res: Maketing team

Design

Start: 9/2/19 ID: 9

Finish: 9/2/19 Dur: 0.2 wks?

Res: Website Designer

Delivery platform Selection

Start: 9/3/19 ID: 10

Finish: 9/3/19 Dur: 0.2 wks?

Res: Website Designer

Development tools selection

Start: 9/4/19 ID: 11

Finish: 9/4/19 Dur: 0.2 wks?

Res: Website Designer

Component Architecture

Start: 9/5/19 ID: 12

Finish: 9/5/19 Dur: 0.2 wks?

Res: Website Designer

System Modeling

Start: 9/6/19 ID: 13

Finish: 9/6/19 Dur: 0.2 wks?

Res: Website Designer

Storyboard

Start: 9/9/19 ID: 14

Finish: 9/9/19 Dur: 0.2 wks?

Res: Website Designer

Database Design

Start: 9/10/19 ID: 15

Finish: 9/10/19 Dur: 0.2 wks?

Res: Website Designer

Interface Design

Start: 9/11/19 ID: 16

Finish: 9/11/19 Dur: 0.2 wks?

Res: Website Designer

Project Plan Updates

Start: 9/12/19 ID: 17

Finish: 9/12/19 Dur: 0.2 wks?

Res: Website Designer

System Implementation

Start: 9/2/19 ID: 18

Finish: 9/2/19 Dur: 0.2 wks?

Res: Website Designer

Networks Testing

Start: 9/3/19 ID: 19

Finish: 9/3/19 Dur: 0.2 wks?

Res: Website Designer

Database Implementation

Start: 9/4/19 ID: 20

Finish: 9/4/19 Dur: 0.2 wks?

Res: Website Designer

Interface Implementation

Start: 9/5/19 ID: 21

Finish: 9/5/19 Dur: 0.2 wks?

Res: Website Designer

Code Documentation

Start: 9/6/19 ID: 22

Finish: 9/6/19 Dur: 0.2 wks?

Res: Website Designer

Project Plan Update

Start: 9/9/19 ID: 23

Finish: 9/9/19 Dur: 0.2 wks?

Res: Website Designer

Testing

Start: 9/2/19 ID: 24

Finish: 9/2/19 Dur: 0.2 wks?

Res: Website Designer

System Testing

Start: 9/3/19 ID: 25

Finish: 9/3/19 Dur: 0.2 wks?

Res: Website Designer

User Testing

Start: 9/4/19 ID: 26

Finish: 9/4/19 Dur: 0.2 wks?

Res: Website Designer

System Rework

Start: 9/5/19 ID: 27

Finish: 9/5/19 Dur: 0.2 wks?

Res: Website Designer

System Develoment

Start: 9/6/19 ID: 28

Finish: 9/6/19 Dur: 0.2 wks?

Res: Website Designer

Project Close Out

Start: 9/2/19 ID: 29

Finish: 9/2/19 Dur: 0.2 wks?

Res: Maketing team

Summative Evaluation

Start: 9/3/19 ID: 30

Finish: 9/3/19 Dur: 0.2 wks?

Res: Maketing team

Release Notes

Start: 9/4/19 ID: 31

Finish: 9/4/19 Dur: 0.2 wks?

Res: Maketing team

Packaging

Start: 9/5/19 ID: 32

Finish: 9/5/19 Dur: 0.2 wks?

Res: Sales

Product Support

Start: 9/6/19 ID: 33

Finish: 9/6/19 Dur: 0.2 wks?

Res: Sales

Client Acceptance

Start: 9/9/19 ID: 34

Finish: 9/9/19 Dur: 0.2 wks?

Res: Sales

<New Task>

Start: 9/2/19 ID: 35

Finish: 9/2/19 Dur: 0.2 wks?

Res:

John Smith

Start: 9/2/19 ID: 0

Finish: 9/24/19 Dur: 3.4 wks?

Comp: 49%

Page 1

Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical

Page 2

Project: John Smith

Date: Mon 10/7/19