Project Management_Scope and Schedule

profileNarsi
Week4_ScopeandSchedule.docx

Project: scope of project

Date: 09/19/2021

Project Management-GE 5103

Cloud Migration (Private cloud to AWS) 

Week4_Scope and Schedule

Finalized Scope:

The main purpose of this project is to transfer the data from one cloud to another of high availability and performance of project, so that we can secure the confidential files with access controls, the data storage, servers, network infrastructure, and security elements such as firewalls, setting up VPNs for project access everything can be done with in a data center, so far we do have 3 data centers as 2 for production and one for disaster recovery , so if any disaster occurs then the data can be recovered from disaster recovery center without any application delays. 

Requirements:

Describe

Work Breakdown Structure:

You can use this for reference

Resource

Duration

Responsibility

Budget

Planned Start Date

Planned End Date

Project Manager

4mnths

Manage the project

$275

10/01/2021

01/31/2022

Software Engineer

4mnths

Develop the code and maintain

$250

10/01/2021

01/31/2022

Hardware Engineer

1mnth

Set up hardware

$125

01/01/2022

01/31/2022

Test Engineer

1mnth

1.Quality check of the product

2. Test if the product passes all safety and quality standard

$125

01/01/2022

01/31/2022

Logistic Manager

4mnths

Supply and maintain warehouse material during the project and procurement shipping

$700k

10/01/2022

01/01/2022

Develop Project Schedule:

Resource

Month1

Month2

Month3

Month4

Project Manager

Assigning all the task to the team

And kick off the project

Checking every 15days for progress

Review the progress made till date and add new features if required

Go through the project and identify if any missing features and deliver the product to clients.

Software Engineer

Develop the working simulation.

Run, test and complete the simulation HW and SW team to collaborate

Enhancements based on the hardware design; complete working s/w based on the working h/w

Fix the bugs identified by the QA and retest in lower environments and deliver error free software

Hardware Engineer

Develop the working simulation and decide on Hardware paths needed for the device

Runs, test and complete the simulation

Check for any updates required for the hardware and add additional capacity if required

Set up required hardware for final product and maintain.

Test Engineer

NA

Collects the list of supplies for procuring the hardware parts

Order and purchase the parts

Complete Regression, sandbox testing and write unit cases at each stage

Logistic Manager

NA

NA

Review the work made till date and give a sample demo to stake holders

Demo the final output and deliver to clients.

Key Milestones and Deliverables:

Identify key milestones in the project and explain why?