Project Resources and Cost Assignment

profilelolay22
Week4-MGT-440_WK4ProjCostFeedback.xlsx

Ex. 2

1 2 3 3 4 7
0 1 1 4 C 6 6 C 5
3 C 5 5 4 9 9 3 12
3 3 6 9 5 14
3 C 0 This project network is accurate for after completing the resource loading chart. However, you did not include the initial project network, which should have the project duration of 12 days.
1 3 4 4 5 9 12 2 14
5 C 3 3 2E 3
6 1 7 7 5 12
Legend
Early Start Duration Early Finish
ID
Late Start Slack Late Finish
Loading Schedule
Carpenter 4 5 1 3 4 5 7 8 5 5 5 8 5 6 7
Electrician 4 4 5 4 3 2 4 9 6 6 5 3 5 8 8 This resource loading chart is not accurate. As an example, the carpenter should be "1" in months 0 -3, and "3" in month 4
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Activity Resource Schedule
ID/RES ES LS EF LF SL
1-C 1 3 6 9 3 Your calculations here are not accurate. As an example 1C should be as follows:
2-C 1 5 11 17 6 ES(0), LS(0), EF(3), LF(3), SL(0)
3-C 0 12 30 48 18
4E 4 12 24 36 12
2-5E 0 10 25 40 15
6-C 0 12 30 48 18

Ex.5

ID RES DUR ES LS LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13
1 1 1 0 2 3 3 2 3 3 2 3 3 2 3 3 2 3 3 0
2 2 3 0 1 3 2 1 1 3 2 1 3 2 1 3 2 1 3 2 1
3 2 4 1 3 2 2 1 3 2 2 3 2 2 3 2 2 3 2 2 1
4 1 5 3 2 2 3 2 2 2 3 2 2 3 2 2 3 2 2 3 2
5 2 3 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
6 2 2 1 1 0 2 3 1 0 2 1 0 2 1 0 2 1 0 2 3
Resources Scheduled 2 3 3 2 2 3 3 2 2 3 3 2 2 3
Resources Available 3 3 3 3 3 3 3 3 3 3 3 3 3 3
This is not accurate. As an example, ID 1 should only have a "1" in column 0.
ID 2 should have a "2" in columns 3, 4, 5, and 6

Ex. 6

ID RES DUR ES LF SL 0 1 2 3 4 5 6 7 8 9 10 11 12 13
1 1 1 0 5 4 2 1 1 2 0 2 1 1 2 1 1 2 0 1
2 2 1 0 3 1 2 1 0 1 2 0 1 2 2 2 0 1 2 2
3 2 1 0 3 0 1 2 0 1 2 2 0 2 0 1 2 0 1
4 1 1 2 7 3 1 0 2 1 2 0 1 2 2 0 1 2 0 1
5 2 2 3 7 0 2 1 2 0 1 2 2 1 2 0 1 2 2
6 2 2 7 5 0 1 2 1 0 2 2 0 1 2 0 1 2 0 1
Resources Scheduled 2 2 2 2 2 1 1 2 2 1 1 2 2 2
Resources Available 2 2 2 2 2 2 2 2 2 2 2 2 2 2
This is not accurate. As an example, ID 1 should only have a "1" in column 2
ID 2 should only have a "1" in columns 0 and 1
ID 3 should onlu have a "1" in columns 0, 1, and 2

Ex. 11

3 3 6
15 Order Parts 14
18 2 20
0 1 1 1 2 3 3 4 7 8 6 14
10 Design Prototype 11 11 Build Prototype 12 13 Prepare Production 13 10 Assemble & Test 6
10 2 12 12 3 15 16 4 20 18 2 20 14 7 21
6 Launch 0
20 1 21
3 5 8
12 Prepare Marketing 12
15 5 20
Legend
Early Start Duration Early Finish
Description
Late Start Slack Late Finish
Budget 0 1 2 3 4 5 6 7 8 9 10 11 12 13
Design Prototype 24 12 12
Build Prototype 30 10 10 10
Order Parts 10 5 5
Prepare Production 64 16 10 22 16
Prepare Marketing 30 6 6 0 6 12
Assemble & Test 36 18 18
Launch 12 12
Total 206 0 79 61 32 22 12
Cumulative 0 79 140 172 194 206