WBS TASK# TASK ACTION DURATION PREDECESSORS RESOURCES
1.0 Project Initiation 1 week
1.1 Business case Develop a business case of how the project will be completed 2 days Undertake feasibility study Project Manager
1.2 Feasibility study Justify the Business case 4 days Form a project team Project Manager
1.3 Project Team Form a project team 1 day Project Manager
2.0 Project Planning 2 weeks
2.1 Project Plan Develop a plan for the IT project 4 days create a resource plan PC specialist
2.2 Resource Plan Create a plan of getting the resources 3 days identify and mitigate the risks Project Manager
2.3 Risk Plan Create a risk plan to ensure the project is successful. 2 days Outsource the resources Project Manager
2.4 Procurement Plan Create a procument plan 5 days Setup, deploy and testing Project Manager
3.0 Project Execution 4 weeks
3.1 IT Area Test Desktop computers and Laptops Test Network servers Install network servers 5 days 4 network servers 1 desktop PC 2 laptops 2 VOIP phones
3.2 Administrative Areas Test all wireless systems Test all the computers Install network servers 1 week 4 PCs 4 VOIP phones Copier
3.3 Conference Room Test all wireless systems Test all the computers Install network servers 2 days Projector Network connectivity VOIP phone
3.4 Meeting Room Test all wireless systems Test all the computers Install network servers 1 week Projector 1 Desktop PC 2 VOIP phones
3.5 Individual Offices Test all wireless systems Test all the computers Install network servers 1 week Desktop PC VOIP phone
3.6 Computer Labs 1 week Projector Desktop PC 25 Desktop PCs VOIP phone Copier
4.0 Project Closure
4.1 Phase review Review the project 1 day Project team