| WBS | TASK# | TASK ACTION | DURATION | PREDECESSORS | RESOURCES |
| 1.0 | Project Initiation | | 1 week | | |
| 1.1 | Business case | Develop a business
case of how the project
will be completed | 2 days | Undertake feasibility
study | Project Manager |
| 1.2 | Feasibility study | Justify the Business
case | 4 days | Form a project team | Project Manager |
| 1.3 | Project Team | Form a project team | 1 day | | Project Manager |
| 2.0 | Project Planning | | 2 weeks |
| 2.1 | Project Plan | Develop a plan for the
IT project | 4 days | create a resource plan | PC specialist |
| 2.2 | Resource Plan | Create a plan of getting
the resources | 3 days | identify and mitigate the risks | Project Manager |
| 2.3 | Risk Plan | Create a risk plan to
ensure the project is
successful. | 2 days | Outsource the resources | Project Manager |
| 2.4 | Procurement Plan | Create a procument
plan | 5 days | Setup, deploy and testing | Project Manager |
| 3.0 | Project Execution | | 4 weeks |
| 3.1 | IT Area | Test Desktop computers and Laptops Test Network servers
Install network servers | 5 days | | 4 network servers
1 desktop PC
2 laptops
2 VOIP phones |
| 3.2 | Administrative Areas | Test all wireless systems
Test all the computers
Install network servers | 1 week | | 4 PCs
4 VOIP phones
Copier |
| 3.3 | Conference Room | Test all wireless systems
Test all the computers
Install network servers | 2 days | | Projector
Network connectivity
VOIP phone |
| 3.4 | Meeting Room | Test all wireless systems
Test all the computers
Install network servers | 1 week | | Projector
1 Desktop PC
2 VOIP phones |
| 3.5 | Individual Offices | Test all wireless systems
Test all the computers
Install network servers | 1 week | | Desktop PC
VOIP phone |
| 3.6 | Computer Labs | | 1 week | | Projector
Desktop PC
25 Desktop PCs
VOIP phone
Copier |
| 4.0 | Project Closure |
| 4.1 | Phase review | Review the project | 1 day | | Project team |