Final Project Management Project

profilegd1222
Week2Scope-Schedule-Budget.docx

1

9

Target Stores

Maria Duplantier

Tasks and Milestone

Task Name

Duration

Business Plan Document

30 days

Project Planning

30 days

Funding

10 days

Budgeting

10 days

Goods and services/Procurement

10 days

Scheduling

0 days

Store Design

45 days

Security System

4 days

Interior Design

15 days

Lightening

15 days

Furnishings

4 days

Art and drawings

4 days

Decisions on paints and Color Schemes

3 days

Floor Space/ In store Displays

0 days

Windows Displays

30 days

Communication networks

10 days

Exterior Design

13 days

Lightening

10 days

Signage

2 days

Landscaping

2 days

Parking

2 days

Cleaning and Upgrading

7 days

Constructions and design

1 day

Vendor selections

1 day

Interior

2 days

Bathrooms

2 days

Cashier Counters

2 days

Customer service area

1 day

Employees area

1 day

Utilities

4 days

Electrical

2 days

Gas

2 days

Water

2 days

Sewer

1 day

Communication networks

23 days

Bid process

1 day

Vendor selections

1 day

Vendor Contracts

2 days

Cabling

2 days

Phone System

2 days

Application Implementation

3 days

Point Of sale

3 days

Inventory Management

2 days

Integrate SKU Data

2 days

Quality Review

3 days

Code Compliance

1 day

Occupancy Certificate

1 day

Head Office Review

2 days

Staffing

2 days

Advertising

1 day

Interviewing

1 day

Hiring

2 days

Training

1 day

Merchandising

11 days

Assemble Displays

1 day

Price Ticketing

1 day

SKU Scan

3 days

Display Merchandise

3 days

Gift Cards

3 days

Display Store Policies

4 days

Marketing

11 days

Staff Business Cards

4 days

Branded Shopping Bags

2 days

New Location Updates

5 days

New Location Updates

13 days

New Catalog

5 days

Print Media

5 days

Internet

3 days

Grand Opening

4 days

Special Guest Invitation

2 days

Advertising

3 days

Catering

1 day

Entertainment

1 day

Budget Estimates

 

Project Initiation

Project Planning

Project Execution

Project Shutdown

Category

Expense Totals

Business Plan Document

 

 

 

 

Project Planning

 

 

 

 

Funding

$ 120.00

$ 341.00

$ 200.00

$ 120.00

$ 781.00

Budgeting

$ 140.00

$ 230.00

$ 219.00

$ 340.00

$ 929.00

Goods and services/Procurement

$ 200.00

$ 210.00

$ 340.00

$ 230.00

$ 980.00

Scheduling

$ 260.00

$ 190.00

$ 461.00

$ 120.00

$ 1,031.00

Store Design

 

 

 

 

Security System

$ 380.00

$ 150.00

$ 703.00

$ 200.00

$ 1,433.00

Interior Design

$ 440.00

$ 130.00

$ 824.00

$ 390.00

$ 1,784.00

Lightening

$ 500.00

$ 110.00

$ 945.00

$ 580.00

$ 2,135.00

Furnishings

$ 560.00

$ 90.00

$ 1,066.00

$ 770.00

$ 2,486.00

Art and drawings

$ 620.00

$ 70.00

$ 1,187.00

$ 960.00

$ 2,837.00

Decisions on paints and Color Schemes

$ 680.00

$ 50.00

$ 1,308.00

$ 1,150.00

$ 3,188.00

Floor Space/ In store Displays

$ 740.00

$ 30.00

$ 1,429.00

$ 1,340.00

$ 3,539.00

Windows Displays

 

 

 

 

Communication networks

$ 860.00

$ 672.00

$ 1,671.00

$ 1,720.00

$ 4,923.00

Exterior Design

 

 

 

 

Lightening

$ 980.00

$ 91.17

$ 1,913.00

$ 2,100.00

$ 5,084.17

Signage

 

 

 

 

Landscaping

$ 1,100.00

$ 128.17

$ 2,155.00

$ 2,480.00

$ 5,863.17

Parking

$ 1,160.00

$ 146.67

$ 2,276.00

$ 2,670.00

$ 6,252.67

Cleaning and Upgrading

 

 

 

 

Constructions and design

$ 1,280.00

$ 183.67

$ 2,518.00

$ 3,050.00

$ 7,031.67

Vendor selections

$ 1,340.00

$ 202.17

$ 2,639.00

$ 3,240.00

$ 7,421.17

Interior

$ 1,400.00

$ 220.67

$ 2,760.00

$ 3,430.00

$ 7,810.67

Bathrooms

$ 1,460.00

$ 239.17

$ 2,881.00

$ 3,620.00

$ 8,200.17

Cashier Counters

$ 1,520.00

$ 257.67

$ 3,002.00

$ 3,810.00

$ 8,589.67

Customer service area

$ 1,580.00

$ 276.17

$ 3,123.00

$ 4,000.00

$ 8,979.17

Employees area

$ 1,640.00

$ 294.67

$ 3,244.00

$ 4,190.00

$ 9,368.67

Utilities

 

 

 

 

Electrical

$ 1,760.00

$ 331.67

$ 3,486.00

$ 4,570.00

$ 10,147.67

Gas

$ 1,820.00

$ 350.17

$ 3,607.00

$ 4,760.00

$ 10,537.17

Water

$ 1,880.00

$ 368.67

$ 3,728.00

$ 4,950.00

$ 10,926.67

Sewer

$ 1,940.00

$ 387.17

$ 3,849.00

$ 5,140.00

$ 11,316.17

Communication networks

 

 

 

 

Bid process

$ 2,060.00

$ 424.17

$ 4,091.00

$ 5,520.00

$ 12,095.17

Vendor selections

$ 2,120.00

$ 442.67

$ 4,212.00

$ 5,710.00

$ 12,484.67

Vendor Contracts

$ 2,180.00

$ 461.17

$ 4,333.00

$ 5,900.00

$ 12,874.17

Cabling

$ 2,240.00

$ 479.67

$ 4,454.00

$ 6,090.00

$ 13,263.67

Phone System

$ 2,300.00

$ 498.17

$ 4,575.00

$ 6,280.00

$ 13,653.17

Application

Implementation

 

 

 

 

Point Of sale

$ 2,420.00

$ 535.17

$ 4,817.00

$ 6,660.00

$ 14,432.17

Inventory Management

$ 2,480.00

$ 553.67

$ 4,938.00

$ 6,850.00

$ 14,821.67

Integrate SKU Data

$ 2,540.00

$ 572.17

$ 5,059.00

$ 7,040.00

$ 15,211.17

Quality Review

 

 

 

 

Code Compliance

$ 2,660.00

$ 609.17

$ 5,301.00

$ 7,420.00

$ 15,990.17

Occupancy Certificate

$ 2,720.00

$ 627.67

$ 5,422.00

$ 7,610.00

$ 16,379.67

Head Office Review

$ 2,780.00

$ 646.17

$ 5,543.00

$ 7,800.00

$ 16,769.17

Staffing

 

 

 

 

Advertising

$ 2,900.00

$ 683.17

$ 5,785.00

$ 8,180.00

$ 17,548.17

Interviewing

$ 2,960.00

$ 701.67

$ 5,906.00

$ 8,370.00

$ 17,937.67

Hiring

$ 3,020.00

$ 720.17

$ 6,027.00

$ 8,560.00

$ 18,327.17

Training

 

 

 

 

Merchandising

$ 3,140.00

$ 757.17

$ 6,269.00

$ 8,940.00

$ 19,106.17

Assemble Displays

$ 3,200.00

$ 775.67

$ 6,390.00

$ 9,130.00

$ 19,495.67

Price Ticketing

$ 3,260.00

$ 794.17

$ 6,511.00

$ 9,320.00

$ 19,885.17

SKU Scan

$ 3,320.00

$ 812.67

$ 6,632.00

$ 9,510.00

$ 20,274.67

Display Merchandise

$ 3,380.00

$ 831.17

$ 6,753.00

$ 9,700.00

$ 20,664.17

Gift Cards

$ 3,440.00

$ 849.67

$ 6,874.00

$ 9,890.00

$ 21,053.67

Display Store Policies

$ 3,500.00

$ 868.17

$ 6,995.00

$ 10,080.00

$ 21,443.17

Marketing

 

 

 

 

Staff Business Cards

$ 3,620.00

$ 905.17

$ 7,237.00

$ 10,460.00

$ 22,222.17

Branded Shopping Bags

$ 3,680.00

$ 923.67

$ 7,358.00

$ 10,650.00

$ 22,611.67

New Location Updates

$ 3,740.00

$ 942.17

$ 7,479.00

$ 10,840.00

$ 23,001.17

New Location Updates

$ 3,800.00

$ 960.67

$ 7,600.00

$ 11,030.00

$ 23,390.67

New Catalog

$ 3,860.00

$ 979.17

$ 7,721.00

$ 11,220.00

$ 23,780.17

Print Media

$ 3,920.00

$ 997.67

$ 7,842.00

$ 11,410.00

$ 24,169.67

Internet

$ 3,980.00

$ 1,016.17

$ 7,963.00

$ 11,600.00

$ 24,559.17

Grand Opening

 

 

 

 

Special Guest Invitation

$ 4,100.00

$ 1,053.17

$ 8,205.00

$ 11,980.00

$ 25,338.17

Advertising

$ 4,160.00

$ 1,071.67

$ 8,326.00

$ 12,170.00

$ 25,727.67

Catering

$ 4,220.00

$ 1,090.17

$ 8,447.00

$ 12,360.00

$ 26,117.17

Entertainment

$ 4,280.00

$ 1,108.67

$ 8,568.00

$ 12,550.00

$ 26,506.67

Total Costs

$ 128,340.00

$ 30,442.67

$ 255,167.00

$ 350,760.00

$ 764,709.67

References

Maserang, S. (2002). project Management: Tools & Techniques. Retrieved from www.umsl.edu: http://www.umsl.edu/~sauterv/analysis/488_f02_papers/ProjMgmt.html

Ridgwell, M. (2010, 01 28). How to Successfully Closeout a Project. Retrieved from network.projectmanagers.net: http://network.projectmanagers.net/profiles/blogs/how-to-successfully-closeout-a

Week 2 Individual Assignment: Project Scope, Schedule, and Budget

Assignment Recap

Use the following guidelines to complete your assignment:

· Project scope: Refine project scope statements from the scope statement in the charter from Week 1.

· Develop a work breakdown structure (WBS) from the refined scope statement.

· Project schedule: Using Microsoft® Project and the WBS you developed above, create a schedule for your project's lifecycle. Include specific tasks and milestones, with time and resource estimates, to meet organizational objectives in 350 words.

· Project budget: Using Microsoft® Excel® and the project schedule, WBS, and scope statement, create a time-phased budget containing cost estimates. Include direct and indirect costs for labor, machinery, equipment, supplies, and other elements applicable to the project.

Points 8

Points Earned 8

Additional Comments:

· Refine (if required) scope statement provided.

· Schedule created in Microsoft Project, encompassing full project lifecycle

· Schedule contains summary-level activities and tasks to produce specific deliverables

· Schedule contains milestones specified in project charter

· Schedule contains reasonable estimates of time and resources required for completion

· Budget created in Microsoft Excel, encompassing full project lifecycle

· Budget contains reasonable estimates of direct and indirect costs for labor, machinery, equipment, supplies, and other elements required to complete project

Maria,

Project Scope 1 Points

Refine project scope statements from the scope statement in the charter from Week 1.

Maria,

I can only assume that you did not “refine” your scope statement and therefore decided not to provide it as the instructions asks. It would have been nice if you restated your scope statement and stated there were no changes.

Project Schedule 3.5 Points

Your project schedule demonstrated an understanding of the basic capabilities of Microsoft Project.

The schedule incorporated the use of milestones that were in line with your previously submitted project charter.

The schedule also showed an understanding of committing resources to obtain project objectives.

Project Budget 3.5 Points

Your project budget presented reasonable estimates that were in line with your project schedule and incorporated the project lifecycle components.

The budget contained cost estimates for the resources that will be utilized by the project.

Please remember to post this week’s deliverables and your Week 1 deliverable (the project charter) along with future deliverables when submitting your final project plan in Week 6.

Organization/Development

Points Available 1

Points Earned 1

Additional Comments:

· The project schedule contains summary-level activities, tasks, and milestones.

· The structure of the project schedule and budget is clear, logical, and easy to follow.

 

Your deliverables this week were presented in a clear and concise manner.

Mechanics

Points Available 1

Points Earned 1

Additional Comments:

· Formatting or layout and graphics are pleasing to the eye, such as font, colors, and spacing.

· Rules of grammar, usage, and punctuation are followed, and spelling is correct.

 

The academic perspectives of this assignment were met. Spelling, grammar, and general layout of your deliverables were appropriate.

Total Available 10

Total Earned 10

Note:

Due to the diversity of file formats and the difficulty of inserting tabled text into an Excel spread sheet and a MS Project .mpp file, this matrix is feedback on all portions of your assignment.