| Task_Name | Duration | Predecessors | Resource_Names | Remaining_Cost |
| Software Development | 88 days | | | 18420 |
| Scope | 2.5 days | | | 360 |
| Determine project scope | 4 hrs | | Management | 120 |
| Define preliminary project resources | 1 day | 2 | Project Manager | 120 |
| Secure core resources | 1 day | 3 | Project Manager | 120 |
| Scope complete | 0 days | 4 | | 0 |
| Analysis/Software Requirements | 12.5 days | | | 1940 |
| Conduct needs analysis | 5 days | 5 | Analyst | 800 |
| Draft preliminary software specifications | 3 days | 7 | Analyst | 480 |
| Develop preliminary budget | 2 days | 8 | Project Manager | 240 |
| Review software specifications/budget with team | 4 hrs | 9 | Project Manager,Analyst | 140 |
| Incorporate feedback on software specifications | 1 day | 10 | Analyst | 160.00000000000003 |
| Secure required resources | 1 day | 11 | Project Manager | 120 |
| Analysis complete | 0 days | 12 | | 0 |
| Design | 14 days | | | 2480 |
| Review preliminary software specifications | 2 days | 13 | Analyst | 320.00000000000006 |
| Develop functional specifications | 5 days | 15 | Analyst | 800 |
| Develop prototype based on functional specifications | 4 days | 16 | Analyst | 640.00000000000011 |
| Review functional specifications | 2 days | 17 | Management | 480 |
| Incorporate feedback into functional specifications | 1 day | 18 | Management | 240 |
| Design complete | 0 days | 19 | | 0 |
| Development | 32 days | | | 6400 |
| Acquire software development resources | 1 day | 20 | Developer | 200 |
| Assign development staff | 1 day | 22 | Developer | 200 |
| Develop code & functionality to support e-commerce | 15 days | 23 | Developer | 3000 |
| Developer testing (primary debugging) | 15 days | 24FS-75% | Developer | 3000 |
| Development complete | 0 days | 25 | | 0 |
| Testing | 59 days | | | 4200 |
| Develop unit test plans using product specifications | 4 days | 20 | Testers | 480 |
| Develop integration test plans using product specifications | 4 days | 20 | Testers | 480 |
| Unit Testing | 15 days | | | 1800 |
| Review modular code | 5 days | 28,26 | Testers | 600.00000000000011 |
| Test component modules to product specifications | 2 days | 26,31 | Testers | 240 |
| Identify anomalies to product specifications | 3 days | 32 | Testers | 360 |
| Modify code | 3 days | 33 | Testers | 360 |
| Re-test modified code | 2 days | 34 | Testers | 240 |
| Unit testing complete | 0 days | 35 | | 0 |
| Integration Testing | 12 days | | | 1440 |
| Test module integration | 5 days | 36 | Testers | 600.00000000000011 |
| Identify anomalies to specifications | 2 days | 38 | Testers | 240 |
| Modify code | 3 days | 39 | Testers | 360 |
| Re-test modified code | 2 days | 40 | Testers | 240 |
| Integration testing complete | 0 days | 41 | | 0 |
| Training | 56 days | | | 2560 |
| Develop training specifications for end users | 3 days | 20 | Trainers | 240 |
| Develop training specifications for helpdesk support staff | 3 days | 20 | Trainers | 240 |
| Identify training delivery methodology (computer based training, classroom, etc.) | 2 days | 20 | Trainers | 160.00000000000003 |
| Develop training materials | 3 wks | 44,26,45,46 | Trainers | 1200.0000000000002 |
| Conduct training usability study | 4 days | 47 | Trainers | 320.00000000000006 |
| Finalize training materials | 3 days | 48 | Trainers | 240 |
| Develop training delivery mechanism | 2 days | 49 | Trainers | 160.00000000000003 |
| Training materials complete | 0 days | 50 | | 0 |
| Deployment | 4 days | | | 480 |
| Set up website in internal servers | 1 day | | Deployment Team | 120 |
| Set up failover | 1 day | 53 | Deployment Team | 120 |
| Retire Current Website | 1 day | 54 | Deployment Team | 120 |
| Train support staff | 1 day | 55 | Deployment Team | 120 |
| Deployment complete | 0 days | 56 | | 0 |