exel 2-2
Activity List
| Porta-Vac Project | ||||
| Activity List for the PORTA-VAC Project | ||||
| Activity | Description | Immediate Predecessor | Estimated Completion Time (weeks) | |
| A | Develop product design | --- | 6 | Instructions: |
| 1. Draw the PERT Diagram on a separate sheet of paper based on this Activity List. | ||||
| B | Plan market research | --- | 2 | |
| C | Prepare routing | A | 3 | 2. Check the next sheet for a solution and compare your work! |
| D | Build prototype | A | 5 | |
| E | Prepare marketing brochure | A | 3 | 3. Continue to the next sheet for further instructions. |
| F | Prepare cost estimate | C | 2 | |
| G | Do preliminary design testing | D | 3 | |
| H | Complete Market survey | B, E | 4 | |
| I | Prepare pricing and forecast report | H | 2 | |
| J | Prepare final report | F, G, I | 2 | |
Project Flow
| Porta-Vac Project | |||||||
| Format | Example | ||||||
| Earliest Start | Activity Name | Earliest Finish | Slack | 1 | Z | 3 | 3 |
| Latest Start | Activity Duration | Latest Finish | 4 | 3 | 6 | ||
| C | F | J | |||||
| A | D | G | |||||
| Finish | |||||||
| Start | |||||||
| E | |||||||
| B | H | I | |||||
| Instructions: (see class notes for more details) | Questions: | ||||||
| Note: Activity Times are listed on the Activity List. | |||||||
| 1. What is the expected completion time? | |||||||
| Step 1: Perform a forward pass -- computing the Earilest Start and Earliest Finish times. Insert these in the TOP row. | |||||||
| Step 2: Perform a backward pass -- computing the Latest Finish and Latest Start times. Insert these in the BOTTOM row. | 2. Where is the Critical Path? | ||||||
| Step 3: Calculated the slack time for each activity. Insert this in the YELLOW box. | (describe by the series of letter for the activities on the Crtical Path) | ||||||
| Step 4: Determine the Critical Path. | |||||||
| Then, proceed to the next sheet to determine the RISK of the project. |
Project Risk
| Porta-Vac Project | |||||||||||
| Instructions: | Questions: | ||||||||||
| Complete the tables below to answer the questions to the right. | 1. What is the probability that this project will be completed within the goal of 20 weeks? | ||||||||||
| 2. What is the probability that this project will be completed faster, within 19 weeks? | |||||||||||
| Data given by Porta-Vac Production Leaders | (see formulas and hints in green to the right) | A-E-H-I-J | A-C-F-J | A-D-G-J | B-H-I-J | ||||||
| Activity | Optimistic (a) | Most Probable (m) | Pessimistic (b) | Expected Completion Time (weeks) | Variance (weeks^2) | Slack (weeks) | On critical Path? (Yes=1 or No=blank) | Path 1 (Yes=1 or No=blank) | Path 2 (Yes=1 or No=blank) | Path 3 (Yes=1 or No=blank) | Path 4 (Yes=1 or No=blank) |
| A | 4 | 5 | 12 | ||||||||
| B | 1 | 1.5 | 5 | ||||||||
| C | 2 | 3 | 4 | ||||||||
| D | 3 | 4 | 11 | ||||||||
| E | 2 | 3 | 4 | ||||||||
| F | 1.5 | 2 | 2.5 | ||||||||
| G | 1.5 | 3 | 4.5 | ||||||||
| H | 2.5 | 3.5 | 7.5 | ||||||||
| I | 1.5 | 2 | 2.5 | ||||||||
| J | 1 | 2 | 3 | ||||||||
| Expected completion time= | weeks | (Hint: Try =SUMPRODUCT(Path,Expected Completion Time) | |||||||||
| Goal to complete = | 20 | weeks | Path variance= | weeks-squared | (Hint: Same =SUMPRODUCT as above) | ||||||
| Path StDev= | weeks | (Hint: take the square-root of the variance. =SQRT(x) | |||||||||
| z-score= | |||||||||||
| Probability to complete within Goal = | Note: P = NORM.S.DIST(z-score), as Standard-Normal Distribution has a Mean=0 and StDev=1. | ||||||||||
| Probability to complete Critical Path on-time = | |||||||||||
| Probability to complete all paths by the goal = | Note: All tasks must be completed on time, not just the Critical Path. Therefore, P(all) = P1 * P2 * P3 * P4 | ||||||||||
| Hint: Change the goal in cell D21, then paste the answers above. | |||||||||||