CMGT/410: Project Scheduling and Documentation

profileBlackWolf
Week1ProjectPlanDraft_microsoftexcelspreadsheet.xlsx

Sheet1

banking software
name duration start finish predecessors resources
idea generation 5 days
1 proposal 2 days 1/6/20 3/6/20 1 project manager
2 concept 2 days 3/6/20 5/6/20 2 project manager
3 initiation 1 day 5/6/20 6/6/20 3 project manager
pre-feasibility 4 days
4 initial investigation 1 day 6/6/20 7/6/20 4 project manager
5 initial assessment 1 day 7/6/20 8/6/20 5 project manager, software developers
6 evaluation 1 day 8/6/20 9/6/20 6 project manager, software developers
7 research 1 day 9/6/20 10/6/20 7 software developer
feasibility 5 days
8 project definition 3 days 10/6/20 13/6/2020 8 project manager, business analyst, project sponsors
9 business case 1 day 13/6/2020 14/6/2020 9 project manager, business analyst, project sponsors
10 authorization 1 day 14/6/2020 15/6/2020 10 project manager, business analyst, project sponsors
development and execution 17 days
11 implementation 5 days 15/6/2020 20/6/2020 11 project manager, software developers
12 project realization 2 days 20/6/2020 22/6/2020 12 project manager, software developers
13 production 3 days 22/6/2020 25/6/2020 13 project manager, software developers
14 build 3 days 25/6/2020 28/6/2020 14 project manager, software developers
15 develop and testing 4 days 28/6/2020 2/7/20 15 project manager, software developers
commissioning 5 days project manager, software developers
16 alpha test 2 days 2/7/20 4/7/20 16 project manager, software developers
17 beta test 2 days 4/7/20 6/7/20 17 project manager, software developers
18 validation 1 day 6/7/20 7/7/20 18 project manager, project sponsor
launch 5 days
19 release 1 day 7/7/20 8/7/20 19 project manager, project sponsor
20 implementation 2 days 8/7/20 10/7/20 20 project owner, project sponsor
21 handing over 1 day 10/7/20 11/7/20 21 project owner, project sponsor
22 acceptance by client 1 day 11/7/20 12/7/20 22 project owner, project sponsor
post-implementation review 5 days
23 business review 2 days 12/7/20 14/7/2020 23 IT auditor, project owner, project sponsor
24 audit 3 days 14/7/2020 17/7/2020 24 IT auditor, project owner, project sponsor
25 post-project review 2 days 17/7/2020 19/7/2020 25 IT auditor, project owner, project sponsor