Top Three Takeaways
Whats the BIM Idea?
Why does this happen?
Project Delivery Methods
▪ Traditional
Owner
Contractor Architect & Engineer
Sub. Sub. Sub. Sub.Sub.
Design-Bid-Build
Current Models
Planning Design Bid Construction Occupancy Design-Bid-Build
(Linear Process)
CM at Risk; Design-Build
(Collaborative Process)
Planning
Design
Construction
Occupancy
Current Construction Model
Concept & Design
Civil
Struc.
Mech.
Elec.Plumb.
Fire
Prot.
Arch.
Construction &
Operation
2-D Drawings & Specifications
Coordination / Quality
RFI
RFI
RFI
RFI
RFI
RFI
Uncoordinated Drawings = Multiple RFI’s
Why does this happen?
How the subcontractor
installed it
How the project was
Documented
How the owner
was billed
When it was delivered What the owner really wanted
How the owner
requested it
How the project manager
understood it
How the architect
designed it
What the contractor bid How the marketing team
described it
Current AEC Process
New Model
Planning Design Bid Construction Occupancy Design-Bid-Build
(Linear Process)
CM at Risk; Design-Build
(Collaborative Process)
Planning
Design
Construction
Occupancy
Planning
Design
Construction
Occupancy
CM at Risk; Design-Build
+ VDC/BIM
Technology-Enabled
Collaborative Process ( )
What Is BIM?
What is BIM?
Building
Information
Modeling
(BIM) Virtual Time Machine
Integrated Project Data
Data Sharing
Enhanced Visualization
Coordination
Collision Detection
Linked Parametric
Information
Process Collaboration
Interoperability
Digital
Intelligent
Object-Oriented
Data-Rich
... all based around the concept that BIM is a process of using technology
-- not just technology itself
There are so many definitions!
Building Information Modeling
▪ Software simulation of design, construction, and facility operation
▪ Virtual Construction - Building it twice – Once in the computer - Once in the field.
▪ Data-Rich Computer Model - Not just an electronic drawing tool.
▪ Object-Based (not just lines) Relational Database
▪ Intelligent ‘Drawings’: Data→ Physical and Functional Characteristics.
BIM =
BIM: Virtual Representations
▪ A BIM is a virtual representation of the physical and functional characteristics of a facility, for good or bad.
BIM: Virtual Representations
Construction Model with BIM
Relational
Database
Civil Struc.
Elec.
Construction &
Operation
Design, Documents, & Data (3-D, 4-D, 5-D)
Arch.
Facility
Mgmt.
Fire
Prot. Cost
Data
Mech.
Plumb. Concept & Design
Why does this happen?
How the subcontractor
installed it
How the project was
Documented
How the owner
was billed
When it was delivered What the owner really wanted
How the owner
requested it
How the design team modeled
it
What the owner visualized and
approved.
What the contractor bid How the marketing team
described it
AEC Process With BIM
Influence vs Cost Curve E
ff o
rt Typical ‘Value’ Engineering !
Strategy Design Construction Operation
25% 75%
L if
e cy
cl e
co st
Virtual Building Design Proposed Entry
Definitions/Terminology
(How to Speak BIM)
BIM Terminology
▪ Current state industry utilizes
▪ 2D construction document ▪ Definition: “2D refers to objects that are constructed
on two planes (X and Y, height and width, row and column, etc.)” (1)
▪ Advantages
▪ Standardized
▪ Easy to construct
▪ Dimensionable
▪ Disadvantages
▪ Difficult to visualize
▪ Requires interpretation
▪ Limited usage (2D)
2D (two-dimensional)
▪ Definition: “3D modeling refers to the creation of three-dimensional objects that are defined mathematically and geometrically”
▪ 3D (L X W X H) Project Geometry. Multiple Views
▪ Visualization & Design Assist
▪ Collision Detection & Coordination
▪ Constructibility Review
▪ Digital As-Built Record Documents
▪ Usually drawn the same way as 2D documents, so draftsmen can be productive -- just add the height dimension.
BIM Terminology
3D (three-dimensional)
▪ Size, location, and intelligent attributes of all objects.
▪ Objects may be linked to each other to form a spatial relationship.
▪ From this model, floor plans, sections, elevations, and details are derived within the same software platform.
▪ Models from different disciplines may be linked together to form a federated model.
BIM Terminology
3D (three-dimensional)
2D to 3D
2D AutoCAD Drawing: HVAC 3D Model: HVAC
3D printouts used by field workers
Definitions / Terms
2-D (L + W) in straight
projection
3-D Image showing
length, width, height
2-D CAD
3-D BIM
Mechanical / Plumbing / Sprinkler Model
Structural Model
Architectural Model
Compiled Multi-Discipline Model
3D- Visualization
Constructability / Code Approval
3D- Visualization
3D- Visualization
3D- Visualization
3D- Visualization
3D- Visualization
3D- Visualization
Definitions / Terms
(3D + Time) Model & Schedule Linked
• Coordinate complex sequencing & phasing issues
• Evaluate site logistics needs and work flow
• Discover hidden logic flaws in the schedule
4D (four-dimensional) TIME
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
4D BIM: 3D Model + Time
Definitions / Terms
QTO: Window Panel Schedule
Windows IsolatedWith Walls DisplayedWith Roof HiddenComposite Model
•Quantity Takeoffs
• Options Analysis
• Purchasing
5-D Model with quantity and cost data input and extracted.
▪ Each component in the model is tied to the Cost Estimate
5D (five-dimensional)
BIM Terminology
Embedded Knowledge
• Quantities of all materials
linked directly to databases
•Data-Rich Model enables
accurate quantity survey of
materials
• Cost implications of design
changes can be understood
in “real time”
5D Design Cost Analysis
Preconstruction – Version 1
52
5D BIM: 3D Model + Cost
Preconstruction – Version 2
53
5D BIM: 3D Model + Cost
Version 1 Version 2
Unit Unit Price Quantity Price Unit Price Quantity Price
Gross Footage sf 890,000 890,000
Exterior Wall sf 330,444 241,433
Brick sf 18.00$ 247,833 4,460,994.00$ 18.00$ 181,075 3,259,345.50$
Glass sf 75.00$ 82,611 6,195,825.00$ 75.00$ 60,358 4,526,868.75$
Total 10,656,819.00$ 7,786,214.25$
54
6D BIM: 3D Model + Asset Information
• As-built Drawings
• Operations & Maintenance Manuals
• Manufacturer #’s, Model #’s Serial #’s
• Warranty & Replacement Information
• Energy Usage/Cost Simulation
BIM Terminology
Animation
▪ Use of 3D images to illustrate movement and/or passage of time along user- defined path
BIM Terminology
Parametric ▪ Software objects that reflect the real-world behaviors and attributes
of construction materials, equipment, and assemblies.
▪ Objects possess characteristics of construction materials, equipment, and assemblies and the interrelationship and interaction between them.
▪ Consistent relationships between elements as the model is
manipulated.
BIM Terminology
Interoperability (as it relates to BIM)
• The ability of Data-Rich Models to share valuable data with each other, through either import or export.
BIM Terminology
Collaborative BIM ▪ Model is developed collaboratively with the owner,
design team, construction team, and others all contributing.
Non-collaborative BIM ▪ Model is not developed collaboratively, and the
construction team must develop its own model based on the information provided by the design team in construction documents. Contractor has greater control over information in model.
BIM Terminology
Integrated Project Delivery (IPD) ▪ Single Model = Integrated Design
▪ Collaborative approach that brings designers, engineers, construction managers, trade workers, suppliers, and fabricators together early in the project to facilitate decision making and optimize project results.
▪ Under IDP a single model is commonly used for spatial coordination.
▪ Highlighted by the opportunity to use a different contracting vehicle – shared risk/reward.
Traditional vs. Integrated
Traditional Project Delivery Integrated Project Delivery
Fragmented; Assembled on “just
as needed” basis; Strongly
hierarchical
Teams Composed of key project
stakeholders; Assembled early
in process; Open, collaborative
Linear; Distinct; Segregated Process Early contributions of
knowledge; Information openly
shared; Trust; Respect
Individually managed;
Transferred to greatest extent
possible
Risk Collectively managed;
Appropriately shared
Individually pursued; Minimum
effort for maximum returns
Compensation/Reward Team success tied to project
success; Value-based
Paper-based; 2D Communication/Technology Digitally-based; Virtual; BIM
Unilateral effort; Allocate and
transfer risk; No sharing
Agreements Encourage; Foster; Promote
and support multi-lateral open-
sharing and collaboration; Risk
sharing
BIM Terminology
Spatial Coordination
▪ Identification of physical interferences between objects or disciplines within the Model(s)
▪ Synonyms: Clash Detection,
Interference, Collision, Conflict,
Variance, Trade Coordination
Spatial Coordination
Designers or 3rd party 3D modelers
Subcontractors
Construction Phase
Architectural Design
Structural Design
Mechanical Shopdrawings
Plumbing Shopdrawings
Electrical Shopdrawings
Other Shopdrawings
Mechanical Model
Plumbing Model
Electrical Model
Other Model
Structural Model
Architectural Model
Consolidated Model
Clash ReportRevision of
Design
Coordination
Meeting
Automated
Clash Detection
Turner
Formalized Process
Short Feedback Cycles
Reliable Clash Check
Ensure Constructability
66
Harborview – Clash Report
67
Model Coordinator
Electrical Coordinator
Ductwork Coordinator
Fire Sprinkler Coordinator Mech Pipe Coordinator Plumbing Coordinator
MEP Manager
Spatial Coordination
69
70
Spatial Coordination
71
Spatial Coordination
72
Spatial Coordination
73
Spatial Coordination
74
Spatial Coordination
75
Spatial Coordination
76
Spatial Coordination
▪ 2D Construction Doc’s
▪ 3D Model
▪ Construction Schedule
▪ Sequence Animation
▪ Marketing Model
▪ Cost Estimate
▪ Space Plan
▪ O&M Program
• 2D Construction Doc’s
created through 3D Model
• Construction Schedule
linked to 3D Model
• Cost Estimate extracted
from 3D Model
• Space Plan extracted from
3D Model
• O&M linked to 3D Model
Is It BIM?
NO YES
Case Study
Geospatial Engineering
BIM Benefits-Owners
SI Explorer: New Google Maps Interface
BIM & Facility
Management
91
3D Visual Models
BIM & Facility
Management
92
STRI
National Zoo
SERC
Coordination with Master Plans
BIM & Facility
Management
The New Meadowlands Stadium East Rutherford, NJ
Image Courtesy of Skanska USA Building, Inc.
Images Courtesy of Skanska USA Building, Inc. Participants
Owner – Jets + Giants – 99 year joint contract
GC – Skanska USA Building + Civil
Architect – Ewing Cole (Kansas City)
Structural Engineer – Thornton Tomasetti
Precast – High Concrete
Steel – CanAm Steel
The New Meadowlands Stadium East Rutherford, NJ
Statistics
Cost $1.3B
1.9M Square Feet
82,000 Seats
217 Box Seats
9,200 Club Seats
4x 40’x130’ Video Scoreboards
21,938 Tons of Steel
13,841 Steel Pieces
3200 Precast Pieces
Innovation Drivers
Delivery pressure due to aggressive sports schedule
Limited on-site storage
-Very Large Pieces
-“Just In Time” Delivery. Pick from truck and place into
structure
Need to coordinate production schedule across entire
supply chain
Quality control critical to erection schedule
Dave Campbell
Vice President, Corporate Director - SimCon
Skanska USA
Robust Production Management = Reliability
Internet
TabletPC with RFID Reader
Manufactured1
RFID Tag
2 Ready to ship
RFID Tag
Received on Site3 RFID Tag
Erected4
RFID Tag
VelaSystems Servers (Vela Hosting Facility)
Reports
Factory Jobsite
Building Information Model
Tag
Tracking Precast Components
RFID Reader
RFID Tag
Tag
Tag Scanning
Tag Scanning
Information Entry
Vela Systems
Sync Buttons
Building Information Model
Status
Information
Visual Reporting
Estimated cost and time benefit:
Gain of 10 days on project schedule @ $100,000/day
benefit = $1.0M savings
Meadowlands Benefits
Real-time supply chain information; visibility into
the status of pre-cast concrete components
Creating real-time communication and collaboration
between key stakeholders and suppliers
Increasing accuracy by eliminating cumbersome,
error-prone paper-based processes
Dave Campbell
Vice President, Corporate Director - SimCon
Skanska USA
The New Meadowlands Stadium East Rutherford, NJ
Image Courtesy of Skanska USA Building, Inc.
Residential BIM
The Next Big Thing!
Computational/Parametric Design
Reality Capture
Design to Fabrication
Labor Deliverables
Contracts Fee
Structures Risk
Rapid Prototype Printing
Field Mobility
Leverage of Mobile Apps
Data Driven Productivity
???
Profit Driven Analytics
Cloud Driven Transformations