Documenting the Project Lifecycle

profilemackey66
Week_One_Project_Plan_Draft.xlsx

Task_Table

Mobile Inventory Tracker Applications
Name Duration Start End Predecessors Resources
Mobile app plan 34 days 2/5/20 3/17/20
Project set-up 7 days 2/1/20 2/9/20
assess user requirements 2 days 2/1/20 2/2/20 project manager, product owner
Set up working environment 4 days 2/3/20 2/8/20 3 technical administrator
Determine initial sprint velocity 1 day 2/9/20 2/9/20 4 lead developer
budget allocation to sprints 0 days 2/9/20 2/9/20 project manager
select project tem 1 day 2/9/20 2/9/20 6 project manager
Project setup complete 0 days 2/9/20 2/9/20 5
Sprint 1 User interface 6 days 2/10/20 2/17/20 2
Sprint 1 plan 0.5 days 2/10/20 2/10/20
Select sprint 1 user stories 0.25 days 2/10/20 2/10/20 product owner
Assign user stories 0.25 days 2/10/20 2/10/20 9 product owner, lead developer
Sprint 1 plan complete 0 days 2/10/20 2/10/20 10
User Interface 5 days 2/10/20 2/16/20
Design User Interface 2 days 2/10/20 2/11/20 UX developer
Build User Interface 2 days 2/12/20 2/15/20 13 UX developer
Test User Interface 1 day 2/16/20 2/16/20 14 test engineer
UAT of user Interface 1 day 2/17/20 2/17/20 12 test engineer, product owner
Correct Issues From UAT UI 1 day 2/26/20 2/26/20 25 UX developer
Sprint 2 functionalities implementation 10 days 2/10/20 2/22/20
Sprint 2 plan 4 days 2/10/20 2/13/20 scrum manager
selecting sprint 2 stories 2 day 2/10/20 2/12/20 scrum manager
Assign user stories 1 day 2/12/20 2/13/20 22
Sprint 2 completion 1 day 2/12/20 2/13/20 23
Testing product modules functionalities 6 days 2/14/20 2/2/20
Developing functionalities 3 days 2/14/20 2/18/20 24 project team
Testing programs 2 days 2/20/20 2/22/20 26 back end tester
Approval 1 day 2/22/20 2/22/20 26
Sprint 3 project reports 15 days
Sprint 3 plan 0.5 days 2/18/20 2/18/20
Select sprint 3 user stories 0.25 days 2/18/20 2/18/20 lead developer
Assign user stories 0.25 days 2/18/20 2/18/20 19 lead developer
Sprint 3 plan completion 0 days 2/18/20 2/18/20 20
Client Specified Reports 7 days 2/18/20 2/26/20
Design Reports 2 days 2/18/20 2/19/20 reporting developer
Build Reports 2 days 2/22/20 2/23/20 23 reporting developer
Test Reports 2 days 2/24/20 2/25/20 24 test engineer
UAT of Reports 1 day 2/29/20 2/29/20 22 test engineer, product owner
Correcting of Issues From UAT of Reports 1 day 3/8/20 3/8/20 reporting developer
Sprint 4 Platform 7 days 3/1/20 3/9/20 17
Sprint 4 plan 0.5 days 3/1/20 3/1/20
Select sprint 4 user stories 0.25 days 3/1/20 3/1/20 lead developer
Assign user stories 0.25 days 3/1/20 3/1/20 30 lead developer
Sprint 4 plan completion 0 days 3/1/20 3/1/20 31
Cross Platform Support 6 days 3/1/20 3/8/20
Design Cross Platform Support 2 days 3/1/20 3/2/20 technical administrator
Build Cross Platform Support 2 days 3/3/20 3/4/20 34 technical administrator
Test Cross Platform Support 1 day 3/7/20 3/7/20 35 technical administrator
UAT of Cross Platform Support 1 day 3/9/20 3/9/20 33 technical administrator, test engineer
Project End 2 days 3/16/20 3/17/20 44
client signing off 1 day 3/16/20 3/16/20 project manager, product owner
issue project report 0.5 days 3/17/20 3/17/20 48 project manager, product owner
Project End 0.5 days 3/17/20 3/17/20 49 project manager, product owner