| Project: | 1313 Mockingbird Lane |
| Name: | Michael Chadukiewicz |
| Date: | 13-Mar-11 |
| ID | LEVEL 1 TASK | LEVEL 2 TASK | LEVEL 3 TASK | RESOURCE |
| 1 | Foundation |
| 1.1 | | Footings |
| 1.1.1 | | | Excavate Site | John Smith |
| 1.1.2 | | | Place Forms | Nancy Post |
| 1.1.3 | | | Place Rebar | Bob Johnson |
| 1.1.4 | | | Pour Concrete | Nancy Post |
| 1.1.5 | | | Strip Forms | Bob Johnson |
| 1.2 | | Walls |
| 1.2.1 | | | Place Forms | Bill Williamson |
| 1.2.2 | | | Place Rebar | Bill Williamson |
| 1.2.3 | | | Pour Concrete | Bill Williamson |
| 1.2.4 | | | Strip Forms | Bill Williamson |
| 1.3 | | Slab |
| 1.3.1 | | | Place Rebar | Nancy Post |
| 1.3.2 | | | Pour Concrete | Bob Johnson |
| 1.3.3 | | | Float Concrete | John Smith |
| 2 | Framing |
| 2.1 | | Walls |
| 2.1.1 | | | First Floor | Adam Smith |
| 2.1.3 | | | Second Floor | Adam Smith |
| 2.1.4 | | | Sheathing | Adam Smith |
| 2.2 | | Floors |
| 2.2.1 | | | First Floor Joists | Bill Williamson |
| 2.2.2 | | | First Floor - Sub Floor | Bill Williamson |
| 2.2.3 | | | Second Floor Joists | Bill Williamson |
| 2.2.4 | | | Second Floor - Sub Floor | Bill Williamson |
| 2.3 | | Roof |
| 2.3.1 | | | Roofs Joists | Nancy Post |
| 2.2.2 | | | Roof Sheathing | Nancy Post |
| 3 | Roofing |
| 3.1 |