Project Management Process - Initiation

profileMkrenisky84
WBSBreakdown.docx

Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the Greendale Stadium Case located at the end of Chapter 6

Greendale Project ReDux

Project Management

Microsoft Project file Snapshot

C:\Users\Dinkar Mishra\Desktop\2016-02-06 19_21_37-Settings.png

C:\Users\Dinkar Mishra\Desktop\2016-02-06 19_24_53-Start.png

When will the project be completed?

Project Completion Date: 12th October, 2018

What is the critical path for the project?

Critical path can be drawn as,

C:\Users\Dinkar Mishra\Desktop\2016-02-06 19_27_53-Settings.png

How much slack / float are in your project? What activities have the greatest slack / float?

C:\Users\Dinkar Mishra\Desktop\2016-02-06 19_32_47-Settings.png

ID

Duration

Activity

Start

Free Slack

Total Slack

1

695 days

Baseball Stadium

2

70 days

Clear stadium site

0 days

0 days

3

30 days

Demolish building

0 days

0 days

4

70 days

Set up construction site

0 days

0 days

5

120 days

Drive support piling

0 days

0 days

6

120 days

Pour lower concrete bowl

0 days

0 days

7

120 days

Pour main concourse

0 days

0 days

8

90 days

Install playing field

275 days

275 days

9

120 days

Construct upper steel bowl

0 days

0 days

10

140 days

Install seats

0 days

0 days

11

90 days

Build luxury boxes

155 days

155 days

12

30 days

Install jumbotron

0 days

0 days

13

120 days

Stadium infrastructure

125 days

125 days

14

75 days

Construct steel canopy

0 days

0 days

15

30 days

Light installation

0 days

0 days

16

90 days

Build roof supports

5 days

5 days

17

180 days

Construct roof

5 days

5 days

18

90 days

Install roof tracks

95 days

95 days

19

90 days

Install roof

5 days

5 days

20

20 days

Inspection

0 days

0 days

Identify the top three (3) activities that you believe could impact the project completion date.

Top three activities are, Build luxury boxes, Stadium infrastructure, and Install playing field

What additional activities you would add to this project to make it more complete, from a project management viewpoint?

Company should give them 700 days to complete the task.