Running Head: WORK SCHEDULE AND WBS OF EATERY COFFEE 1

WORK SCHEDULE AND WBS OF EATERY COFFEE 2

Eatery Coffee Shop WBS and Project Work Schedule

Student Name

Institution

Course

Date

Introduction

The project to open the eatery coffee restaurant was an idea I previously chose due to my interest in fast food joints. The coffee business venture will provide breakfast, lunch, and evening coffee to people and tourists of Minnesota State and government institutions with a specialty on offering fresh and purely ground coffee drinks.

In this paper, I analyze the Work-breakdown structure (WBS) of this project, which divides the main work of opening eatery coffee into smaller activities, which acts as a guide to accomplish the desired results. In this, we look at the business idea of the creation and distribution of eatery coffee in Minnesota State. The WBS shows the breakdown of core activities before the grand opening of the eatery coffee in Minnesota State. These activities are supposed to be scheduled for smooth implementation of the events and ensure the time efficiency of 6 months is achieved.

The core activities include deciding where the capitalization of the business, the furniture to be bought, site location, kitchen designing, wall paintings and decoration, recruitment and training of staff and ordering the supplies, stock, buying of equipment, utensils, and computers.

The WBS and project schedule below shows the core activities with duration and anticipated budget of every action.

Designing exterior features

· welcome board and glow signs

· installation desired Lights and electronics such sound system

Obtaining coffee business permit and Franchise license and any necessary approvals

Acquisition of stock such raw-materials, tools, instruments and utensils

Decoration of interiors wall

· painting and decoration

· Designing the counter and computer stand.

· Installation of instruments kitchen equipment and computer for the counter

Designing budgets for eatery coffee business

Hiring of staff and training them and getting necessary resources

Identification of suitable site for coffee location in Minnesota and

Signing of leasing contracts

Designing of the shop and kitchen

Financial plan and

Blue print on furniture layout, equipment to be acquired and plumbing and electrical needs

Eatery coffee structural planning

Budget $ 421,000

Creation and distribution of Eatery coffee in Minnesota State

Budget $ 500,000

.

WORK-BREAKDOWN STRUCTURE OF EATERY COFFEE

Coffee shop facilities

Budget $ 59,000

Resources and Operations

Budget $ 20,000

PROJECT SCHEDULE OF OPENING EATERY COFFEE RESTAURANT IN MINNESOTA STATE

Activity

Duration

Estimated cost

Core Activities

156 days

$ 500,450

1

Creating a business plan

4 days

$ 1000

2

Surveying and discussing site location for setting up the business and also researching on customers’ tastes/preferences of people of Minnesota

5 days

$ 3000

3

Creation pre-production plan

2 days

$ 500

4

Signing an agreement with potential shareholders of the business.

2 days

$ 600

5

Discussing the capitalization of the shop

1 day

$ 800

Comparing the rental prices of different

2 days

$ 1,500

Inspecting and Choosing the a store/shop

1 day

$ 1,400

6

Meeting with landlord/real estate

2 days

$ 2,500

7

Discussing terms and conditions

1 day

$ 1,000

8

The signing of lease agreements

2 days

$ 20,000

9

Inspection of the location, payment of rental fee and exchange of keys

5 days

$ 1,700

10

Insurance of the coffee restaurant

2 days

$ 1500

11

Acquisition of equipment for coffee business such as utensils, computers, refrigerators among others

7 days

$ 2,000

12

Sourcing and identification of potential suppliers

3 days

$ 350

13

Designing of the structural plan with shareholders, stakeholders

4 days

$ 1000

14

Blueprint- discussing on furniture and equipment layout

7 days

$ 1,700

15

Renovations such as plumbing and electrical needs, e.g., unique lights

20 days

$ 4,000

16

Painting and decorations

15 days

$ 3,000

17

Installation of equipment, furniture, menu boards, counters, and fixtures

10 days

$ 2,800

18

Designing the interior –choose design and wall frames

14 days

$ 3,700

19

Designing the exterior such patio furniture and outside color

6 days

$ 4,500

20

The hiring of cashiers, waiters and other assistants ( posting jobs, interviewing, selection and hiring)

15 days

$ 2,400

21

Purchasing the stock from vendors

2 days

$ 15,000

22

Installation of CCTV cameras

10 days

$ 2,700

23

Installation of routers for internet access

2 day

$ 2,400

24

Implementation of security measures in the site

1 day

$ 1 400

25

Payment of franchise fee

2 days

$ 420,000

26

Grand opening restaurant

-

-

References

Băncescu, M. (2016). Controlling project schedule progress, using control charts. Cybernetics and Systems47(7), 602-615.

Rahman, W. A. Z. W. A., Zaki, N. M., & Husain, M. A. (2019). A review of work breakdown structure and man-hours estimation method used in shipbuilding production. International Journal of Mechanical Engineering and Technology10(1), 1141-1158.

Sanghera, P. (2019). Project Schedule Management. In CAPM® in Depth (pp. 173-220). Apress, Berkeley, CA.

Zecheru, V., & Olaru, B. G. (2016). Work Breakdown Structure (WBS) in Project Management. Review of International Comparative Management/Revista de Management Comparat International17(1).