Odyssey Business Consulting PASS Project – Work Breakdown Structure

Odyssey Business Consulting

Pilot Angels Scheduling System

The Work Breakdown Structure

image1.png

Work Breakdown Structure:

The project Life Cycle and System Development Life Cycle Phases and Deliverables were outlined in the Deliverable Structure Chart of the Scope Management Plan. The Phase Milestones, Deliverables, Deliverable Milestones and the Activities / Tasks that need to be performed to achieve the milestones are presented below.

Project Phases – Tasks, Deliverables and Milestones:

Table 1 illustrates the major phases, their deliverables, milestones and tasks for the Pilot Angels Scheduling System project. The table also lists the identified resource assignments and the estimated time to complete the task.

Estimation Techniques:

The Odyssey Business Consulting (OBC) used a combination of estimation techniques to come up with the time estimates of the activities and tasks in the Work Breakdown Structure. Time Boxing was used for the “Business Case” deliverable. OBC had two work weeks (10 days) within which the Business Case was to be prepared and presented to its client Husky Air Therefore OBC time boxed the Project Initiation phase for 7 days. Also a time box of two work weeks(10 days) was allotted to the Analysis Phase of the SDLC, because it has been observed that a lot of time is usually expended in the Requirements Gathering Phase if a bottom-up approach is used.

For all other times, bottom-up estimation technique has been used. In the activities and tasks outlines, there are a few tasks that could be performed simultaneously. This issue will be addressed during the preparation of the Project Schedule and Budget using Microsoft Project.

WBS

Task Description

Deliverable

Estimated Time

Resources

1

Pilot Angels Project

No

74.6 days?

Phase 1: Project Initiation - Deliverable, Milestones, Resource Allocation and estimated time schedule

1.1

Initialize and Conceptualize

No

7 days?

1.1.1

Identify MOV creation core team

No

1 day?

Project Manager,Sponsor

1.1.2

Arrive at MOV

No

2 day?

Project Manager,Sponsor

1.1.3

Alternatives Identification and Feasibility Analysis

No

2 days?

Project Manager,Sponsor,

Systems Architect

1.1.4

Deliverable: Business Case

No

1 day?

Project Manager

1.1.5

Client Approval of Business Case

Yes

1 day?

Sponsor

Phase 2: Project Planning - Deliverable, Milestones, Resource Allocation and estimated time schedule

1.2

Plan Project

No

5 days?

1.2.1

Define Project Scope

No

1 day?

Project Manager,

Systems Architect,Sponsor

1.2.2

Deliverable:Create Scope Management Plan

No

1 day?

Project Manager,Systems Architect

1.2.3

Deliverable:Create Communication Plan

No

1 day?

Project Manager

1.2.4

Define Project Phases

No

1 day?

Project Manager

1.2.5

Define Tasks

No

1 day?

Project Manager,Systems Architect

1.2.6

Estimate Budget and Schedule

No

1 day?

Project Manager

1.2.7

Deliverable:Create Baseline Project Plan

No

1 day?

Project Manager

1.2.8

Client approval on Baseline Project

Yes

1 day?

Sponsor

Phase 3: Project Execution and Control - Deliverable, Milestones, Resource Allocation and estimated time schedule

1.3

Execute Project

No

57.6 days?

1.3.1

Kick Off Meeting

Yes

0.1 days?

Project Manager,Systems Architect, Sponsor,SME,TESTERS

1.3.2

Analysis

No

12 days?

1.3.2.1

Current System Analysis

No

1 day?

BSA[50%],Systems Architect[50%]

1.3.2.2

Plan Requirements Gathering

No

1 day?

BSA

1.3.2.3

JAD Sessions for Requirements Gathering

No

5 days?

BSA,SME

1.3.2.4

Analyze Requirements

No

2 days

BSA,Systems Architect

1.3.2.5

Document Requirements

No

1 day?

1.3.2.5.1

Deliverable:Prepare Use Case Scenarios

No

1 days

BSA

1.3.2.5.2

Deliverable:Prepare Requirements Spec

No

1 day?

Systems Architect

1.3.2.6

Verify adherence to MOV

No

1 day?

BSA,Project Manager,Systems Architect

1.3.2.7

Client Sign off on requirements

Yes

1 day?

Sponsor

1.3.3

Design

No

7.5 days?

1.3.3.1

Develop Logical Design

No

2 days

1.3.3.1.1

Deliverable:Develop DFDs

No

1 day

Systems Architect,BSA

1.3.3.1.2

Deliverable:Develop UML Diagrams

No

1 day

BSA

1.3.3.2

Deliverable:Develop Physical Design

No

2.5 days

Systems Architect

1.3.3.3

Deliverable:Develop ERDs

No

1 day?

BSA

1.3.3.4

Deliverable:Design Document

No

1 day?

Systems Architect

1.3.3.5

Verify adherence to MOV and Requirements

No

1 day?

Project Manager,Systems Architect,BSA

1.3.3.6

Client Sign off

Yes

1 day?

Sponsor

1.3.4

Construction

No

23 days?

1.3.4.1

Set up infrastructure

No

5 days

Others

1.3.4.2

Coding

No

17 days?

Developer

1.3.4.3

verify MOV and Requirements with develeoped system

Yes

1 day?

Project Manager,Systems Architect

1.3.5

Testing

No

8 days?

1.3.5.1

Identify test cases

No

1 day?

BSA

1.3.5.2

Create Test Plan

No

1 day?

Project Manager

1.3.5.3

Create user test environment

No

1 day?

Developer

1.3.5.4

Co-ordinate testing

No

3 days?

BSA[10%],TESTERS

1.3.5.5

Analyze test results

No

1 day?

BSA

1.3.5.6

Client Sign off

Yes

1 day?

Sponsor

1.3.6

Implementation

No

7 days?

1.3.6.1

Create Implementation Plan

No

1 day?

Systems Architect

1.3.6.2

Create user environment

No

1 day?

Developer

1.3.6.3

Prepare User Training Programs

No

3 days?

BSA

1.3.6.4

Conduct user training

No

1 day?

Project Manager

1.3.6.5

Release system

No

1 day?

Project Manager,Systems Architect

1.3.6.6

Client sign off

No

1 day?

Sponsor

Phase 4: Project Close - Deliverable, Milestones, Resource Allocation and estimated time schedule

1.4

Close Project

No

4 days?

1.4.1

Prepare final report

No

1 day?

Project Manager

1.4.2

Evaluate & Release resources

No

2 days?

Project Manager

1.4.3

Final Presentation and Acceptance of the system

Yes

1 day?

Project Manager,Systems Architect,Sponsor

Phase 5: Project Evaluation - Deliverable, Milestones, Resource Allocation and estimated time schedule

1.5

Evaluate Project

No

2 day?

1.5.1

Post Implementation Review

No

1 day?

Project Manager,Systems Architect,Sponsor

1.5.2

Lessons Learned

No

2 days?

Project Manager

2

Evaluating MOV

No

2 days?

image2.png

image3.png

Acceptance and Approval:

The signatures below indicate acceptance and approval of the Work Breakdown Structure of the PASS project and its estimated schedule.

Name

Title/Role

Company

Signature

Mike Smith

PASS Sponsor

Husky Air

P

Project Manager

Odyssey Business Consulting

S

System Architect

Odyssey Business Consulting

PASS GNATT CHART