| phase | status | begin | end | duration |
| 1.0 requirements gathering | complete | 3/6/18 | 3/16/18 | 10 days |
| 1.1 requirements detailed | complete | 3/6/18 | 3/10/18 |
| 1.2 documentation detailed | complete | 3/11/18 | 3/16/18 |
| 2.0 design | not complete | 3/17/18 | 4/5/18 | 30 days |
| 2.1 designing interfaces | | 3/17/18 | 4/5/18 |
| 3.0 testing | not complete | 4/6/18 | 4/14/18 | 9 days |
| 3.1 unit testing | | 4/6/18 | 4/8/18 |
| 3.2 system testing | | 4/9/18 | 4/11/18 |
| 3.3 user acceptance testing | | 4/12/18 | 4/14/18 |
| 4.0 launch | not complete | 4/15/18 | 4/19/18 | 5 days |
| 4.1 Online Documentation | | 4/15/18 | 4/17/18 |
| 4.1 Roll out | | 4/18/18 | 4/19/18 |
| | | | | 54 days |