phase status begin end duration
1.0 requirements gathering complete 3/6/18 3/16/18 10 days
1.1 requirements detailed complete 3/6/18 3/10/18
1.2 documentation detailed complete 3/11/18 3/16/18
2.0 design not complete 3/17/18 4/5/18 30 days
2.1 designing interfaces 3/17/18 4/5/18
3.0 testing not complete 4/6/18 4/14/18 9 days
3.1 unit testing 4/6/18 4/8/18
3.2 system testing 4/9/18 4/11/18
3.3 user acceptance testing 4/12/18 4/14/18
4.0 launch not complete 4/15/18 4/19/18 5 days
4.1 Online Documentation 4/15/18 4/17/18
4.1 Roll out 4/18/18 4/19/18
54 days