3-4eProject Execution

Executing the project involves taking the necessary actions to complete the activities in the project plan. The products of the project are created during project execution, and it usually takes the most resources to accomplish this process.  Table 3-11  lists the knowledge areas, executing processes, and outputs of project execution from the PMBOK® Guide – Sixth Edition.

Table 3-11

Executing processes and outputs

Knowledge Area

Executing Process

Outputs

Project Integration Management

Direct and manage project work

Deliverables

Work performance data

Issue log

Change requests

Project management plan updates

Project documents updates

Organizational process assets updates

Manage project knowledge

Lessons-learned register

Project management plan updates

Organizational process assets updates

Project Quality Management

Manage quality

Quality report

Test and evaluation documents

Change requests

Project management plan updates

Project documents updates

Project Resource Management

Acquire resources

Physical resource assignments

Project team assignments

Resource calendars

Change requests

Project management plan updates

Project documents updates

Enterprise environmental factors updates

Organizational process assets updates

Team performance assessments

Develop team

Change requests

Project management plan updates

Project documents updates

Enterprise environmental factors updates

Organizational process assets updates

Manage team

Change requests

Project management plan updates

Project documents updates

Enterprise environmental factors updates

Project Communications Management

Manage communications

Project communications

Project management plan updates

Project documents updates

Organizational process assets updates

Project Risk Management

Implement risk responses

Change requests

Project documents updates

Project Procurement Management

Conduct procurements

Selected sellers

Agreements

Change requests

Project management plan updates

Project documents updates

Organizational process assets updates

Project Stakeholder Management

Manage stakeholder engagement

Change requests

Project management plan updates

Project documents updates

Organizational process assets updates

Enlarge Table

Source: PMBOK® Guide – Sixth Edition, 2017.

Many project sponsors and customers focus on deliverables related to providing the products, services, or results desired from the project. However, it is equally important to document change requests and update planning documents as part of execution. Templates related to this process group are listed later in this chapter.

Erica knew that providing strong leadership and using good communication skills were crucial to good project execution. For this relatively small project, she was able to work closely with all the team members to make sure they were producing the desired work results. She also used her networking skills to get input from other people in the firm and from external sources at no additional cost to the project. She made sure that everyone who would use the resulting intranet application understood what the team was producing as part of the project and how the intranet application would help them in the future.

Erica also knew that working efficiently was critical for successful execution, regardless of the size of the project. Therefore, she used resources throughout the company when they were available. For example, she used the firm’s formal change request form, even though it had primarily been used for external projects. The firm also had contract specialists and templates for several procurement documents that the project team members would use for the portions of the project it planned to outsource.

Erica kept in mind that Joe, the CEO and project sponsor, liked to see work performance data through milestone reports. He also wanted Erica to alert him to any potential issues or problems. Erica met with most of her project team members often, and she talked to Joe about once a week to review progress on completing milestones and to discuss any other project issues. Although Erica could have used project management software to create milestone reports, she used word-processing software instead because this project was small and she could more easily manipulate the report format.  Table 3-12  shows a sample of a milestone report for the project management intranet site project that Erica reviewed with Joe in mid-June.

Table 3-12

Milestone report as of June 17

Milestone

Date

Status

Responsible

Issues/Comments

Initiating

Stakeholders identified

May 2

Completed

Erica and Joe

Project charter signed

May 10

Completed

Erica

Project kick-off meeting held

May 13

Completed

Erica

Went very well

Planning

Team contract signed

May 13

Completed

Erica

Scope statement completed

May 27

Completed

Erica

WBS completed

May 31

Completed

Erica

List of prioritized risks completed

June 3

Completed

Erica

Reviewed with sponsor and team

Schedule and cost baseline completed

June 13

Completed

Erica

Executing

Survey and analysis completed

June 28

Erica

Poor response so far!

Intranet site design completed

July 26

Kevin

Project benefits measurement completed

August 9

Erica

User inputs collected

August 9

Jessie

Articles completed

August 23

Jessie

Templates and tools completed

September 6

Erica

Ask the Expert completed

September 6

Michael

User Requests feature completed

September 6

Cindy

Links completed

September 13

Kevin

Intranet site construction completed

October 4

Kevin

Intranet site testing completed

October 18

Cindy

Intranet site promotion completed

October 25

Erica

Intranet site roll-out completed

October 25

Kevin

Monitoring and Controlling

Progress reports

Every Friday

All

Closing

Final project presentation completed

October 27

Erica

Sponsor sign-off on project completed

October 27

Joe

Final project report completed

October 28

Erica

Lessons-learned reports submitted

November 1

All

Enlarge Table

Human resource issues often occur during project execution, especially conflicts. At several of the team meetings, Erica could see that Michael seemed to be bored and often left the room to make phone calls to clients. She talked to Michael about the situation, and she discovered that Michael was supportive of the project, but he knew he could only spend a minimal amount of time on it. He was much more productive outside of meetings, so Erica agreed to have Michael attend a minimal number of project team meetings. She could see that Michael was contributing to the team by the feedback he provided and his leadership on the Ask the Expert feature for the intranet site. Erica adjusted her communication style to meet his specific needs.

Another problem occurred when Cindy was contacting potential suppliers for software to help with the Ask the Expert and User Requests features. Kevin wanted to write all of the software for the project himself, but Cindy knew it made better business sense to purchase these new software capabilities from a reliable source. Cindy had to convince Kevin that it was worth buying some software from other sources.

Cindy also discovered that their estimate of $10,000 was only about half the amount they needed for software services. She discussed the problem with Erica, explaining the need for some custom development no matter which supplier they chose. Erica agreed that they should go with an outside source, and she asked their sponsor to approve the additional funds. Joe agreed, but he stressed the importance of still having the system pay for itself within a year.

Even near the beginning of the project, Erica had tapped Joe for help when the team received a low response rate to their survey and requests for user inputs. Joe sent an e-mail to all of JWD Consulting’s consultants describing the importance of the project. He also offered five extra vacation days to the person who provided the best examples of how they used tools and templates to manage their projects. Erica then received informative input from the consultants. Having effective communication skills and strong top management support are essential to good project execution.

Best Practice

One way to learn about best practices in project management is by studying recipients of PMI’s Project of the Year award. The Quartier International de Montréal (QIM), Montreal’s international district, was a 66-acre urban revitalization project in the heart of downtown Montreal. This $90 million, five-year project turned a once unpopular area into a thriving section of the city with a booming real estate market, and has generated $770 million in related construction. Clement Demers, PMP®, was the director general for the QIM project. He said the team “took a unique project execution approach by dividing work into packages that allowed for smaller-scale testing of management techniques and contract awards. Benefiting from experience gained in each stage, managers could then adjust future work segments and management styles accordingly.”

Other strategies that helped the team succeed included the following:

· The team identified champions in each stakeholder group to help inspire others to achieve project goals.

· The team’s communications plan included a website dedicated to public concerns.

· There were two-day reviews at the beginning of each project phase to discuss problems and develop solutions to prevent conflict.

· Financial investors were asked for input to increase their stake in the project.

· The team recognized the value of hiring high-quality experts, such as architects, engineers, lawyers, and urban planners. They paid all professionals a fixed price for their services and paid their fees quickly.

· Another Canadian firm won the Project of the Year award in 2014. The CA $1.3 billion AP60 Phase 1 Project produced an upgraded aluminum smelting facility in Jonquiere, Quebec. In 2013, the Adelaide desalination project in Adelaide, Australia, won the award. This project, which supplies water during times of drought, was completed early and within 1 percent of its AU$1.4 billion budget. The 2017 award went to the U.S. firm Washington River Protection Solutions, LLC for their work on the Hanford Double Shell Tank AY-102 Recovery Project. The project involved removing and transferring nuclear waste to a double-shell tank for safe storage. The project closed ahead of scheduled and over 8 percent under budget. See PMI’s website for more information on award criteria and winners.