| | Risk Register |
| No. | Risk | Description | Category | Root Cause | Triggers | Potential Responses | Risk Owner
(select from Microsoft Project Resource Sheet) | Probability
(High, Med, Low) | Impact Assessment
(High, Med, Low) | Reason for Impact Assessment Selection | Status |
| R1 | Project Team Selection | May not get functional management support for project team member assignments to the project | Planning | Not enough coordination with functional management | Poor lateral communication | | | Medium | | | Open |
| R2 | Senior management Approval of Plans | May not get senior management buy-in on other plans | Planning | Not enough coordination with senior management | Poor upward communication | | | Low | | | Open |
| R3 | Server owner requirements definition | May not be able to accurately define server requirements due to implementation of new technologies | Executing-Web Site Concept | Not enough technical documentation available from server hardware suppliers | Inadequate supplier support | | | Medium | | | Open |
| R4 | Registration for classes and programs design undefined | May not be able to accurately design "Registration for classes and programs" modules due to complex algorithm requirements | Executing-Web Site Design | Programmer/ Analyst unfamiliar with algorithm | Increased Programmer/Analyst anxiety | | | Low | | | Open |
| R5 | "Develop registration for classes and programs" code incomplete | "Develop registration for classes and programs" code completion may be delayed | Executing-Web Site Development | Programmer/ Analyst unfamiliar with algorithm | Delay in completing code walkthroughs | | | High | | | Open |
| R6 | Verification Testing delayed | Verification Testing delayed due to errors in code regression testing | Executing-Web Site Development | Code incompatibilities | Test Plans unapproved | | | High | | | Open |
| R7 | Uncooperative Users | Users may not cooperate and be difficult during training | Executing-Roll Out | No plan for conflict management | Poor team dynamics | | | Low | | | Open |
| R8 | Support process definition | May be challenges defining the technical support processes | Executing-Support | Support team unfamiliar with new software product line | New intranet software products causing anxiety with field support personnel | | | Medium | | | Open |
| R9 | Customer not willing to hold formal customer review | Customer may refuse to hold formal customer review due to unavailability or product issues | Controlling | Lack of communication from Customer | Customer not communicating and/or not committing to "formal customer review" date | | | High | | | Open |
| R10 | Customer not willing to hear final presentation | Customer may refuse to hear final presentation due to unavailability or product issues | Closing | Lack of communication from Customer | Customer not communicating and/or not committing to "final presentation" date | | | Low | | | Open |