Project Plan
Week 3 – Project WBS Feedback for Team Assignment Team: Team 2 – Projecteers Feedback:
• You are on the right track with your WBS but you omitted several key elements and others need to be updated/expanded.
• I highlighted those in the comments below.
• When building the WBS, you need to think of it as a roadmap for the work that needs to be done. The key is to include everything in a logical flow that can become a schedule in the future.
• Please make changes to your MS Project file to reflect the input below.
• You may use any part of my WBS or substitute mine as the starting point for the Week 4 assignment.
• Please email me if you have any questions.
For level 2 WBS tasks, please refer to the chart above. 1.0 Manage Project:
• Change the summary task to “Manage Project”. It should not be called “Initial Planning”
• You included some PM tasks, but please ensure you’ve accounted for all of these tasks.
Task Name Duration
Manage Project 1 day?
Project Charter 1 day
Create Charter 1 day
Charter Signed 1 day
Project Management Plan 1 day?
Create Draft 1 day?
Revise Project Management Plan 1 day?
Finalize Project Management Plan 1 day
Direct & Manage Project Work 1 day
Manage Vendors 1 day
Manage Project Team 1 day
Manage Stakeholders 1 day
Manage PM Knowledge 1 day
Monitor & Control Project Work 1 day?
Monitor Budget 1 day
Monitor Schedule 1 day?
Perform Integrated Change Control 1 day?
Manage Scope Changes 1 day
Update Scope 1 day?
• Move PM recurring tasks from “Develop Resource Plan” to this area. 2.0 Design IT Solution:
• You need to include a summary task to account for the system design of your upgrade.
• Add tasks to account for an IT solution design, such as:
Task Name Duration
Design IT Solution (Phase 1) 1 day?
Facilities Layout 1 day?
Dining Area 1 day?
Customer Service Area 1 day?
Admin Area 1 day?
Kitchen Area 1 day?
Network Design 1 day?
Wired Network Design 1 day?
Wireless Network Design 1 day?
Services Requirements 1 day?
Inventory 1 day?
Bookkeeping 1 day?
Website 1 day?
Online Ordering 1 day?
Card Processing 1 day?
Office Automation 1 day?
• You must have a plan before your can order equipment. 3.0 System Hardware:
• This area must account for POS terminals, ordering kiosks, and similar equipment.
• You need to account for vendor selection, ordering, shipping and receiving of equipment.
• The IT Solution summary task will be the key input to this section.
Task Name Duration
System Hardware (Phase 2a) 1 day
Hardware Acquisition 1 day
Determine Hardware Requirements 1 day
Select Hardware Vendor(s) 1 day
Order Hardware 1 day
Order Admin Workstations 1 day
Order Printers 1 day
Order POS Terminals 1 day
Order Ordering Kiosks 1 day
Order Payment Terminals 1 day
Receive Hardware 1 day
Receive Admin Workstations 1 day
Receive Printers 1 day
Receive POS Terminals 1 day
Receive Ordering Kiosks 1 day
Receive Payment Terminals 1 day
Hardware Installation 1 day
Install Admin Workstations 1 day
Install Printers 1 day
Install POS Terminals 1 day
Install Ordering Kiosks 1 day
Install Payment Terminals 1 day
4.0 System Software:
• You need to determine your requirements from the IT Solution section.
• You need to account for vendor selection and shipping.
• Account for other software as needed.
Task Name Duration
System Software (Phase 2b) 1 day?
Software Acquisition 1 day?
Determine Software Requirements 1 day?
Select Software Vendor(s) 1 day?
Order Software 1 day?
Receive Software 1 day?
Software Installation 1 day?
Admin Workstation Software 1 day?
Other Software 1 day?
5.0 IT Services:
• You need to determine what services you will need.
• You need to add tasks for IT services, such as:
Task Name Duration
IT Services (Phase 2c) 1 day?
Determine Services Requirements 1 day?
Broadband Internet 1 day?
Web Hosting 1 day?
Admin Services (MS365) 1 day?
Contract for Services 1 day?
Broadband Internet 1 day?
Web Hosting 1 day?
Admin Services 1 day?
• Website design should be included in this section.
• It is likely that a vendor will handle website design and implementation for you. 6.0 System Networking:
• You have some of these tasks in “System Installation”
• You can move those tasks into this section and add others as needed.
• This section needs a logical flow, such as:
Task Name Duration
System Networking (Phase 3) 1 day?
Networking Acquisition 1 day?
Determine Network Equipment Requirements 1 day?
Select Network Equipment Vendor(s) 1 day?
Order Network Equipment 1 day?
Receive Network Equipment 1 day?
Install Wired Network 1 day?
Plan Installation 1 day?
Install Wired Network Infrastructure 1 day?
Test Wired Network Infrastructure 1 day?
Install Wireless Network 1 day?
Plan Installation 1 day?
Install Wireless Network Infrastructure 1 day?
Test Wireless Network Infrastructure 1 day?
7.0 System Validation:
• The “System Implementation” task covers some of this.
• You need to handle testing and training separately.
• Expand your testing section to account for all equipment testing needed, such as:
Task Name Duration
System Validation (Phase 4) 1 day?
Develop Validation Plan 1 day?
Hardware Validation Plan 1 day?
Networking Validation Plan 1 day?
Software Validation Plan 1 day?
Services Validation Plan 1 day?
Conduct System Validation 1 day?
Hardware Validation 1 day?
Networking Validation 1 day?
Software Validation 1 day?
Services Validation 1 day?
8.0 System Transition:
• Move the training tasks to this section.
• Add user acceptance tasks.
Task Name Duration
System Transition (Phase 5) 1 day?
User Training 1 day?
Develop Training Plan 1 day?
Conduct User Training 1 day?
User Acceptance 1 day?
Develop UAT Plan 1 day?
Conduct UAT 1 day?
9.0 Post-Implementation Support:
• Add post-imp support.
Task Name Duration
Post-Implementation Support (Phase 6) 1 day?
Plan Post-Implementation Support 1 day?
Conduct Post-Implementation Support 1 day?