Inzinerine Ekonomika-Engineering Economics, 2014, 25(5), 538–548

Finding a New Way to Increase Project Management Efficiency in Terms of Time

Reduction

Seweryn Spalek

Silesian University of Technology

Gliwice, Poland

E-mail. [email protected]

http://dx.doi.org/10.5755/j01.ee.25.5.8419

There are three basic constraints called ‘the golden triangle’ in each project: time, budget and scope. Researchers and

practitioners are trying to find a way to increase the efficacy of the project’s outcomes in terms of shortening the project’s duration, lowering budgetary costs and meeting the scope. Although several publications have been written on that topic,

there is still no common solution in place. However, more in-depth research related to the specific type of projects or

industries is being conducted and this paper seeks to incorporate additional knowledge into that contemporary field.

Furthermore, this is of growing importance in modern, turbulent times, where the expectations of profiting from lessons

learned are ever increasing.

Following the current market demands, in the article a new, innovative approach is proposed to manage the expectation

that future projects will have a shorter duration. Therefore, the idea of creating specific roadmaps is proposed, which

should help the decision makers improve the efficacy of project management in the company, where the process of such

improvement is measured using the maturity levels assessment concept.

Based on the world-wide quantitative studies in the construction, information technology and machinery industries,

specific roadmaps for each industry were determined. The purpose of these roadmaps is to indicate the most effective

investment sequence in the increase of project management maturity, which should result in a decrease of future projects’ duration. Moreover, discussions on the limitations of such investments are examined.

Keywords: Investment, Time pressure, Company, Projects, Improvement, PM, Implementation of Strategies, Knowledge,

Innovation.

Introduction

Three of the world’s most recognized Latin words,

“Citius, Altius, Fortius,” meaning “Faster, Higher,

Stronger”, have been the Olympic motto since 1894. At the

time: Pierre de Coubertin proposed the motto, having

borrowed it from his friend Henri Didon, a Dominican priest who taught sport close to Paris (IOC, 2007, p. 5).

These three words encourage the athlete to give his or

her best during competition. To better understand the

motto, we can compare it with the Olympic creed: “The

most important thing in life is not the triumph, but the

fight; the essential thing is not to have won, but to have

fought well.” Together, the Olympic motto and the creed

represent an ideal that Coubertin believed in and promoted

as an important life lesson that could be gained from

participation in sport and the Olympic Games: that giving

one’s best and striving for personal excellence was a worthwhile goal. It is a lesson that can still be applied

equally today, not just to athletes but to each one of us

(IOC, 2007, p. 5).

Modern project management has its roots (Lenfle and

Loch, 2010, p. 33) in the atomic bomb Manhattan project

(Morris, 1994, p. 18) and the ballistic missile projects,

Atlas and Polaris (Kerzner, 2013). The term “modern

project management” is used by some authors and relates

mostly to the project management approach started in the

1950s and continuing through today (Chen et al., 2011;

Hill, 2004; Lenfle & Loch, 2010; Shenhar, 2001).

Remarkably, from the very beginning of contemporary

project management, projects were, and continue to be,

under similar time pressure (Campos Silva et al., 2012;

Chen et al., 2012; Griffin, 1993, 1997; Herroelen & Leus,

2005; Omorede et al., 2013; Radziszewska-Zielina, 2010; Zavadskas et al., 2010). Kach and colleagues (2012, p.

377) state: The speed of technological change and

shortened product life cycles have made the time-to-market

requirements for developing new products increasingly

stringent (Kessler and Chakrabarti, Langerak et al., 2010;

Heightened competitive forces have motivated many firms

to move their new products through the design and

manufacturing pipeline at a faster rate, encouraging greater

focus on accelerated development and compressed time

lines (Prasnikar & Skerlj, 2006; Wright et al., 1995).

The above statement for NPD (new product development) projects can be applied to most projects,

whatever their nature. In our current, turbulent times, the

pressure of time seems to increase to an ever greater

extent. Project managers and their teams experience

similar pressure to athletes: to beat the record and to go

faster and faster. The first word, “Citius”, of the Olympic

hendiatris1 seems to dominate projects managed by

1 Hendiatris is a figure of speech in which three words are used to

emphasize one idea, for example, Wine, women, and song. Hendiatris is

often used to create mottos for organizations; for example, The motto at

West Point is “Duty, Honor, Country.” see K. Wilson and J. Wauson, the

AMA handbook of business writing: the ultimate guide to style, grammar,

Inzinerine Ekonomika-Engineering Economics, 2014, 25(5), 538–548

- 539 -

companies today. The majority of project stakeholders

(executives, sponsors, clients, managers) expect new

projects to be completed faster than ever.

Moreover, companies are always careful about

spending money. Therefore, they also want to know

where to invest their typically limited funds. This issue

also arises when deciding where to invest to shorten the

time of future projects.

This paper gives new insight into the dilemma of where and when to invest limited company funds to

achieve the best approach to time reduction of future

projects.

(R)evolution in Managing Projects

Project management has evolved throughout history.

This evolution has occurred mostly due to the tools and

techniques applied to single projects and the gradual

improvement of human resource management (Avots,

1969). This situation lasted until the 1990s, when the number of projects executed by companies increased.

Moreover, companies’ operating environments became

turbulent (Keil & Mahring, 2010). Furthermore, the

influence of project outcomes on the success of an entire

company increased (Baron & Hannan, 2002). As a result,

companies placed a greater emphasis on project

management. To speed up time-to-market, companies

experienced increased pressure to reduce the duration of

projects. The existing methods for reducing the time of

ongoing single projects (e.g., application of modern

scheduling techniques supported by computer technology)

(Brucker et al., 1999; Iacovou & Dexter, 2004) are significant; however, they are no longer sufficient. A new,

more efficient and revolutionary approach to managing

companies’ portfolios of projects was needed (Cooper et

al., 1999). This need generated new approaches for how to

better manage projects to face the new challenges

appearing in multi-project (Hofman, 2014), dynamic

environments (Spalek, 2013). Accordingly, new concepts

in project management were introduced, focusing on

project environment and knowledge management (del

Cano and de la Cruz, 2002; Ethiraj et al., 2005;

Neverauskas and Stankevicius, 2008; Pemsel & Wiewiora, 2013). Among these concepts is the idea of assessing the

maturity level of project management in the company

(Cooke-Davies, 2007; Fraser et al., 2003; Spalek, 2014;

Tan et al., 2011).

Assessing Maturity: the Purpose

To gain competitive advantage in executing projects,

companies wanted to know how well they manage projects

while taking into consideration different aspects

influencing the effective execution of projects (Kerzner,

2013; Rudzianskaite-Kvaraciejiene et al., 2010). The

assessment outcomes should note the areas for potential improvement (Ahmad et al., 2013).

This expectation can be fulfilled by project

management maturity assessment. There are several

existing models of maturity assessment; however, their

main purpose remains the same: to identify weak and

usage, punctuation, construction, and formatting (New York: American

Management Association, 2010, p. 216).

strong areas in an organization (Belt et al., 2009). By

knowing its strengths and weaknesses, a company can

undertake actions to improve activities related to the

management of projects, resulting in an increased maturity

level and improved project outcomes.

The majority of existing models assess project

management maturity level on a scale from 1 to 5, where 1

represents the lowest and 5 the highest level (Khoshgoftar

& Osman, 2009). The assessment is performed in different areas related to project management. Therefore, the

assessment results in a matrix with maturity scores and

testing areas (Spalek, 2011).

Increasing Maturity: the Investment in the Future

It is critical to understand that an increase of maturity

level will mostly benefit future projects. Increasing by one

maturity level up also has some impact, however limited,

on existing projects. Because the planning phase in each

project is crucial (Wyrozebski & Spalek, 2014), the biggest

possible improvements are associated with future projects.

There is even a well–known quotation saying2:

“Show me how your project starts and I can tell you how it will end.”

If the level of maturity is increased, e.g., from level 1

to 2, the outcomes of that action will be beneficial in new

projects. For existing projects, it will usually be too late to

have an impact.

Therefore, the decision to assess and then increase the

project management maturity level in a company is an

investment in future projects.

Investment “in maturity” is time consuming and

money intensive; therefore, to achieve the highest possible

time reduction of future projects, it is crucial to decide where and when (in which sequence) a company

investment should be placed. Moreover, a company’s

investment funds are often very limited, making the issue

even more important. Therefore, it is essential for

companies today to have a road map guiding decision

makers on the following topic:

“In which areas and in what sequence should limited

funds be most effectively invested in my company?”.

The Research Method

The prediction of the future is a complex issue (Glenn

& Gordon, 2003), often involving various methods and

techniques, and thus has a wide record in

publications.(Booth, 2006; Galbraith & Merrill, 1996;

Lacher et al., 1995; Landeta, 2006; Onkal et al., 2013).

To predict reduction of the future time of projects, questionnaire-based cross-impact analysis was used

following the ideas presented by Fabiana Scapolo and Ian

Miles (2006, p. 680–681). The method included the

following steps:

 choosing the object of studies;

 selection of subject to study;

 choosing the experts to participate;

 gathering the data using questionnaires;

 data analysis and conclusions.

2 Author unknown, also exists as: “Show me how your project starts and I

can tell you how it will finish” or “Show me how your project starts and I

show you how it will end”.

Seweryn Spalek. Finding a New Way to Increase Project Management Efficiency in Terms of Time Reduction

- 540 -

Three Industries: Construction, Information

Technology and Machinery The research presented in this article was part of a

larger effort supported by the National Science Centre, focusing on world-wide studies of maturity in project

management in the chosen industries. The overall research

was designed in two major steps.

The first step was to conduct quantitative empirical

studies on project management maturity levels in three types

of industries: machinery, construction and information

technology. Data from 447 global companies, mostly

medium- and large-sized ones, was collected. Ninety-eight

per cent of them earned over € 2,000,000 per year, and 99,5

% of them employed over 49 people.

The second step, which is discussed in this study, was

designed to investigate the relationship between the increase in maturity level in project management and the

predicted duration of forthcoming projects.

The Assessment

For the purpose of this study, a model was used that

assesses the company’s project management maturity in

four areas (Spalek, 2011):

 methods (M) (Gary et al., 2011; Ji & Sedano, 2011);

 human resources (HR) (Levin, 2010; McDonough, 2000);

 project environment (E) (Elbanna, 2013; Killen & Kjaer, 2012);

 knowledge management (KM) (Basu, 2014; Gasik, 2011).

The description of the maturity assessment areas is

shown in table 1.

Table 1

Project Management Maturity Assessment Areas

ID Area Description

1. Human Resources staffing, career paths, motivation, training, team work

2. Methods (incl. Tools &

Techniques)

methods, tools, techniques and means used for project planning and execution; risk, requir ements, scope, costs, time

and quality management

3. Environment organizational structures, top management support, stakeholders’ management, company culture

4. Knowledge Management lessons learned approach, gathering data and experience for on-going operations and future references

In the applied project management maturity model the

results of the assessment are reported from level 1 to 5:

 LEVEL 1: Initial;

 LEVEL 2: Standardized;

 LEVEL 3: Appliance;

 LEVEL 4: System Management;

 LEVEL 5: Self-improvement. The experts were asked to express their opinion on an

increase of maturity level by one increment (from 1 to 2,

from 2 to 3, etc.) and how it influences the time reduction

of future projects in their companies. The possible impact

was measured on a scale from 1 to 5, as shown in table 2.

The assessment was made separately in each testing area.

Table 2

The Impact on Time Reduction on Future Projects

Impact Level Description

1 No influence

2 1–10 % 3 11–20 % 4 21–30 % 5 over 30 %

In our study, the experts were practitioners from the

investigated companies. The invitation to participate in this

study was sent to 308 chosen experts as a follow-up to the

major global study on project management maturity. The

experts were chosen based on the demographic information obtained in the first step of the overall research. They were

experienced managers that had at least five years of

experience and possessed a deep knowledge of the projects

executed in their companies. Moreover, the invitations

were sent to experts from companies that reported a

maturity level of at least 2 in each of the testing areas.

The response rate was 63 %. Such a high rate was

obtained as there were individually approached named

persons who expressed, in the first step of overall research,

their willingness to participate in the second step of the

studies. Non-response bias was tested by comparing the demographic data of participating and non-participating

experts. No significant difference was found, proving that

survey respondents represent the overall sample accurately.

Results and Discussion

Data from 39 information technology, 48 construction

and 107 machinery industry global companies was

collected. The reliability of data was checked using

Cronbach’s alpha, resulting in a value of over 0,9 in each

testing area. Data analysis using mean, median and mode values

was performed. The equality of variances was tested using

Levene's test and the equality of means using a t-test, and

satisfactory results were obtained as the significance for

Levene’s test was greater than 0,05. Additionally,

Spearman's rho correlation coefficients and factor analysis

using rotated component matrix were calculated for further

rigid data analyses. The data analysis was performed using

Statistical Package for the Social Sciences (IBM SPSS

build V21.0.0).

The results revealed differences in the predicted

impact of change in maturity level on the duration of future projects. This level of impact depended on the specific

change in the designated area of assessment (e.g., a change

from level 1 to 2 in the knowledge management area) and

varied between industries.

The Impact on Future Projects: by Maturity Area

and Type of Industry

The data analysis revealed that the dispersion of the

acquired data is low; consequently, the mean value was

chosen to explain the results. Using the mean value allows

Inzinerine Ekonomika-Engineering Economics, 2014, 25(5), 538–548

- 541 -

the results to be presented more clearly, without going into

deep statistical details and allows the development of a

full, more comprehensive picture. The mean values of

impact on the future projects are shown in table 3.

The Impact on Future Projects by Industry (CONS, IND, IT) and Change of Maturity Level in the Areas of Methods (M), Human Resources (HR), Project Environment (E) and

Knowledge Management (KM).

Table 3

Statistics (Mean Value of Impact on Future Projects)

M

1–2

M

2–3

M

3–4

M

4–5

HR

1–2

HR

2–3

HR

3–4

HR

4–5

E

1–2

E

2–3

E

3–4

E

4–5

KM

1–2

KM

2–3

KM

3–4

KM

4–5

CONS 3,96 3,96 3,21 2,46 3,96 3,96 3,21 2,46 3,21 3,21 2,46 1,71 3,21 3,21 2,46 1,71

IND 3,88 3,88 3,16 2,44 3,88 3,88 3,16 2,44 3,16 3,16 2,44 1,72 3,16 3,16 2,44 1,72

IT 3,90 3,90 3,15 2,41 3,90 3,90 3,15 2,41 3,87 3,87 3,13 2,38 3,87 3,87 3,13 2,38

The impact on future projects depends on the type of

industry. The highest impact levels (3,96) were observed

for the change from level 1 to 2 and from 2 to 3 in the methods (M) and human resources (HR) areas in the

construction industry (CONS). The lowest impact (1.71)

also appeared in the construction industry; however, it was

observed in the areas of environment (E) and knowledge

management (KM) for the change of maturity from level 4

to 5. Note, in each type of the studied industries, the

potential impact on future projects is the highest if the

company is at the initial (1) or standardized (2) level of

maturity in project management and wants to increase it by

going one level up. This observation is true for each

assessment area: methods, human resources, environment

and knowledge management. When a company reports already having appliance (3)

or system management (4), maturity levels and wants to

increase it by one level, the impact on future projects’

duration subsequently decreases. However, this reduction

is greater in the construction and machinery industries than

in information technology companies. Therefore, which

project management maturity area the company should first

invest funds in to reduce the future project’s duration

depends on the type of industry. Moreover, the investment

sequence depends on the current level of maturity in the

company in each testing area, meaning that for a chosen industry, one should consider a different roadmap, showing

where and in which sequence the investment in project

management maturity should be placed.

Different Industries, Different Approach?

This study on the influence of the increase of project

management maturity on future projects’ time reduction was focused on three types of industries:

 Construction, one of the “world present” sectors that has projects that are, to some extent, inherited in its

long history. The projects associated with these sectors are

described and considered by numerous authors (Davies et

al., 2009; Dominguez et al., 2009).

 Information Technology (IT), the companies of which are admittedly spread throughout the globe. The IT

projects are described and discussed for many different

types, such as agile (Thomke and Reinertsen, 1998) or

Internet projects (Mahadevan, 2000).

 The machinery industry, which operates in the background of the above two industries as well as many

others, is present in many countries and is a backbone

industry for the other sectors. Therefore, its importance for

the global economy is very high. However, a limited amount

of research in this particular sector can be found in the

literature. The examples are mostly qualitative case studies describing new product development (NPD) practices

(Ahmad et al., 2013; Huang et al., 2004; Matsui et al.,

2008), which are crucial for machinery industry companies.

The Investment Road Map: The Idea

Based on the factor analysis (as shown in Table 4), a

road map is proposed showing the investment path in

maturity areas, which should result in the biggest pay-offs

in reduction of time in future projects. Analysing the

groups of factors in the table, the proposed roadmaps for

the companies was built. This road map operates in the

areas of methods and techniques (M), human resources

(HR), project environment (E) and project knowledge management (KM), as well as the associated change in

level of maturity (e.g., from 2 to 3), which is noted, for

example, as follows: M 2–3 (the change in maturity from

level 2 to 3 in the area of methods and techniques).

In general, note that at the beginning of the road map,

the investment has the biggest impact on the duration of

future projects and subsequently decreases along the way.

Table 4

Factor Analysis

Rotated Component Matrixa,b

Component

1 2 3

M2-3 ,964 ,245 -,088

HR1-2 ,964 ,245 -,088

HR2-3 ,964 ,245 -,088

M1-2 ,964 ,245 -,088

HR3-4 ,953 ,265 ,146

E1-2 ,953 ,265 ,146

KM2-3 ,953 ,265 ,146

KM1-2 ,953 ,265 ,146

E2-3 ,953 ,265 ,146

M3-4 ,953 ,265 ,146

M4-5 ,719 ,253 ,648

HR4-5 ,719 ,253 ,648

E3-4 ,719 ,253 ,648

KM3-4 ,719 ,253 ,648

KM4-5 -,019 ,093 ,992

E4-5 -,019 ,093 ,992

Extraction Method: Principal Component Analysis.

Rotation Method: Varimax with Kaiser Normalization.

a. BRANCH=CONS; b. Rotation converged in 18 iterations

Rotated Component Matrixa,b

Component

1 2 3

HR1-2 ,964 ,250 -,074

HR2-3 ,964 ,250 -,074

Seweryn Spalek. Finding a New Way to Increase Project Management Efficiency in Terms of Time Reduction

- 542 -

Rotated Component Matrixa,b

Component

1 2 3

M1-2 ,964 ,250 -,074

M2-3 ,964 ,250 -,074

E2-3 ,945 ,265 ,191

KM2-3 ,945 ,265 ,191

E1-2 ,945 ,265 ,191

M3-4 ,945 ,265 ,191

KM1-2 ,945 ,265 ,191

HR3-4 ,945 ,265 ,191

KM4-5 -,102 ,049 ,990

E4-5 -,102 ,049 ,990

KM3-4 ,641 ,226 ,733

HR4-5 ,641 ,226 ,733

M4-5 ,641 ,226 ,733

E3-4 ,641 ,226 ,733

Extraction Method: Principal Component Analysis.

Rotation Method: Varimax with Kaiser Normalization.

a. BRANCH=IND; b. Rotation converged in 18 iterations.

Rotated Component Matrixa,b

Component

1 2 3

HR1-2 ,947 ,148 ,272

HR2-3 ,947 ,148 ,272

M1-2 ,947 ,148 ,272

M2-3 ,947 ,148 ,272

KM2-3 ,934 ,190 ,297

E2-3 ,934 ,190 ,297

E1-2 ,934 ,190 ,297

KM1-2 ,934 ,190 ,297

HR3-4 ,817 ,227 ,519

M3-4 ,817 ,227 ,519

E3-4 ,783 ,284 ,543

KM3-4 ,783 ,284 ,543

HR4-5 ,288 ,327 ,891

M4-5 ,288 ,327 ,891

E4-5 ,254 ,387 ,872

KM4-5 ,254 ,387 ,872

Extraction Method: Principal Component Analysis.

Rotation Method: Varimax with Kaiser Normalization.

a. BRANCH=IT; b. Rotation converged in 9 iterations.

The Investment Road Map: Construction Industry

The construction sector is one of the largest industries

traditionally associated with using project management.

The proposed road map revealed that the biggest pay-off is

associated with an increase of maturity level from 1 to 2

and from 2 to 3 in the methods (M 1–2, M 2–3) and human

resources areas (HR 1–2, HR 2–3).

The road map can be described in the following four

steps: Step One

Assuming that the company is at an initial (1) maturity

level in all areas, the first step in investment should be an

increase of maturity in the methods (M) and human

resources areas (HR) until they reach the level 3.

Step Two

Then, in the second step, the investment should be

placed in gradually reaching level 3 in the environment and

knowledge management areas (E 1–2, E 2–3, KM 1–2,

KM 2–3), and the increase in methods and human

resources should continually increase until they reach level

4 (HR 3–4, M 3–4). Step Three

The third step should include activities improving the

maturity in the environment and knowledge management

areas until they report level 4 (E 3–4, KM 3–4) and the

methods and human resources areas until level 5 (M 4–5,

HR 4–5).

Step Four

Finally, in the fourth step, the increase should be from

level 4 to 5 in the environment and knowledge

management areas (E 4–5, KM 4–5).

Figure 1 shows the investment road map for the construction industry.

Figure 1. Investment road map for the construction industry

M 1–2,

M 2–3,

HR 1–2,

HR 2–3

E 1–2,

E 2–3,

KM 1–2,

KM 2–3,

HR 3–4,

M 3–4

E 3–4,

KM 3–4,

M 4–5,

HR 4–5

E 4–5,

KM 4–5

STEP 1 STEP 2 STEP 3 STEP 4

Inzinerine Ekonomika-Engineering Economics, 2014, 25(5), 538–548

- 543 -

Comparing Steps in Construction Companies: the

Reduction of Impact

Remarkably, if assuming that in the first step, the impact

on reduction of time of future projects is 100, then in the

second step, it equals 81; in the third, 62; and in the fourth,

43.

This information is useful for investments in a specific

company, as companies in the same industry differ from one

another. After performing the first step, the total investment and detailed impact on a project’s duration can be measured.

Then, knowing the predicted reduction of impact, one can

estimate the possible outcomes in the second step toward the

investment effort and decide if it is worth it to proceed. The

same approach can be performed before step three and four.

Following this advice means, of course, that time gaps are

needed between successive steps to reassess the situation.

The Investment Road Map: Information Technology

After construction, the second industry traditionally

associated with the project management sector is

information technology (IT). Moreover, both industries

report a long project management application history.

The investment road map for information technology

consists of six steps.

Step One

In step one, the investment in increasing project

management maturity levels should be performed to go from

level 1 to 2 and from 2 to 3 in the methods and human

resources areas (M 1–2, M 2–3, HR 1–2, HR 2–3).

Step Two

After the first investments, the company should consider

investments to increase the level of maturity from 1 to 2 and

then from 2 to 3 in the remaining two areas: environment

and knowledge management (E 1–2, E 2–3, KM 1–2, KM

2–3).

Step Three In the third step, the project management maturity level

should be increased from 3 to 4 in the methods and human

resources areas (M 3–4, HR 3–4).

Step Four

In this step, as in step three, one goes up from level 3 to

4 in the environment and knowledge management areas (E

3–4, KM 3–4).

Step Five

The fifth step is designated for improvement in the

methods and human resources areas from level 4 to 5 (M 4–

5, HR 4–5).

Step Six In the last step, the investment should be placed to

increase the maturity level from 4 to 5 in the areas of

environment and knowledge management (E 4–5, KM 4–5).

Figure 2 shows the investment road map for information

technology companies.

Figure 2. Investment road map for information technology companies

Comparing Steps in IT Companies: The Reduction of

Impact

The highest potential impact on future projects in the

IT industry occurs when investing in the areas indicated in

the first step and then gradually decreases.

Assuming that the impact in the first step equals 100,

the impact on future projects’ duration of investment in step two is 99. Accordingly, in step three, the duration is

81; in step four, 80; in step five, 62; and, finally, in step

six, 61.

Despite a relatively greater number of steps in

comparison to the construction industry, the differences

between some pairs of steps (1 and 2, 3 and 4, 5 and 6) are

small. Thus, the decision to continue the investment after

each step is of a different nature than in the construction

industry where differences are bigger.

The Investment Road Map: Machinery Industry The products of the machinery industry are the

machines, tools, parts and devices used by the other

industries. This industry, like construction and IT, also has

a wide representation among companies world-wide.

M 1-2,

M 2-3,

HR 1-2,

HR 2-3

E 1-2,

E 2-3,

KM 1-2,

KM 2-3

M 3-4,

HR 3-4

E 3-4,

KM 3-4

STEP 1 STEP 2 STEP 3 STEP 4

M 4-5,

HR 4-5

STEP 5 STEP 6

E 4-5,

KM 4-5

Seweryn Spalek. Finding a New Way to Increase Project Management Efficiency in Terms of Time Reduction

- 544 -

However, a limited amount of project management related

research exists for this sector.

The investment in project management maturity in the

machinery industry should be considered in the following

four steps:

Step One

In the first step, the investment in an increase of

maturity levels from 1 to 2 and, successively, from 2 to 3

should be considered in the areas of methods and human resources (M 1–2, M 2–3, HR 1–2, HR 2–3).

Step Two

The next investments should be focused on further

increases in the methods and human resources areas up to

level 4 and, in parallel, they should be focused on further

increases in the areas of environment and knowledge

management from levels 1 to 3 (M 3–4, HR 3–4, E 1-2, E

2–3, KM 1–2, KM 2–3).

Step Three

In step three, an increase of project management

maturity up to level 4 is advised in the environment and

knowledge management areas (E 3–4, KM 3–4).

Additionally, investment in the methods and human areas

is suggested until they reach level 5 (M 4–5, HR 4–5).

Step Four This final step is dedicated to the environment and

knowledge management areas to reach a level 5 of project

management maturity (E 4–5, KM 4–5).

Figure 3 shows the investment road map for the

machinery industry.

Figure 3. Investment road map for the machinery industry

Comparing Steps in Machinery Industry Companies:

the Reduction of Impact

If one assumes that the possible impact on future

project time reduction in the machinery industry equals 100

as a result of performing step 1, the execution of step 2 will

thus result in an impact level of 81. For steps 3 and 4, there

is a further reduction of impact to 64 and 44, respectively.

After performing each step and comparing the effort

undertaken to the reported project outcomes, this

information can be used to decide whether to continue with

further investments in increasing maturity levels.

Conclusions

The Traditional vs. Agile Approach to Managing

Projects

The outcomes for the construction and machinery

industries are alike, whereas the results of the study in

information technology companies differs. This could be

the result of similarities between the type of projects

undertaken by both the construction and machinery

industry and the different projects undertaken by IT companies. The construction and machinery industry

companies execute projects in a more traditional approach,

whereas IT projects have a greater tendency to migrate

toward agility in project management. The concepts of

traditional vs. agile approach in project management are

widely discussed by (Fernandez & Fernandez, 2008;

Shenhar & Dvir, 1996). That contrast would explain the

major differences between the proposed investment

roadmaps that are associated with either a more traditional

or agile approach to project management.

Construction and Machinery: the Traditional

Approach

In the traditional approach, the general advice is to

invest gradually in all four areas of maturity with some advance investment in project management standards, tools

and techniques and in the competencies of people involved

in projects. The investment in company structures

supporting project execution or project knowledge

management areas should be considered in direct relation

to progress in the methods and human resources areas.

Information Technology: The Agile Approach

Agility, as defined by its founders3, is less focused on

strict methods and tools and more on knowledge flow,

creating an appropriate working environment and team

building processes (Dingsoyr et al., 2012). Therefore,

3 see: http://agilemanifesto.org/; accessed November 2013.

M 1–2,

M 2–3,

HR 1–2,

HR 2–3

E 1–2,

E 2–3,

KM 1–2,

KM 2–3,

HR 3–4,

M 3–4

KM 4–5

E 4–5

E 3–4,

KM 3–4,

M 4–5,

HR 4–5

STEP 1 STEP 2 STEP 3 STEP 4

Inzinerine Ekonomika-Engineering Economics, 2014, 25(5), 538–548

- 545 -

explaining why the investment in that type of project

should be performed gradually and in parallel in each of

the following areas: methods, human resources,

environment and knowledge management.

Although this study is limited to three industries, the

suggested roadmaps can be used by other industries as

well, especially by a wide range of manufacturing

companies (NAICS, 2012). A company can choose a road

map by assessing the similarities of the projects being executed to construction and machinery or IT projects.

However, for some sectors, such as healthcare (Adler et

al., 2003) or education (Palacios-Marques et al., 2013),

more studies are needed to develop their specific road

maps systems.

Continuous Improvement? Not Necessary!

The majority of academics and practitioners think that

continuous improvement is vital for a company’s

operations and its survival in the turbulent market. This

approach is also a noticeable concept of increasing project

management maturity levels as a continuous process,

which should result in reaching the highest maturity level

in all assessment areas.

However, based on existing studies of maturity

(Becker et al., 2009; Grant & Pennypacker, 2006; Mullaly

&Thomas, 2010; Pasian, 2011; Rohrbeck, 2010), the vast

majority of companies today report, on average, the second or third level of maturity in different industries and

assessment areas. Therefore, more effort is put into

discussing how the company should proceed with maturity

improvement to achieve “the top.” However, some doubts

exist if “the top” is even obtainable as there is a risk that

assessment criteria can be changed over time as project

management develops further. The first signs of such an

approach are described in the model proposed by PMI

(2008), in which no levels of maturity are defined. Instead,

maturity is measured using a best practices list, which is

continuously expanded by the PMI. This approach results

in a “never ending” continuous effort to increase project management maturity in the company.

Continuous improvement, however appropriate in

theory, cannot always be the best solution for a company.

As our study revealed, the impact of the increase of

maturity on the reduction of future projects decreases over

subsequent levels of maturity. The biggest impact occurs

at the very beginning when a company is making its first

steps on the road map. Then, the impact decreases by more

than 50 % in the traditional approach to project

management (represented by construction and machinery

industries) and by approximately 40 % in the agile approach (represented by information technology

companies). This brings into the question whether

continuous improvement in maturity is effective for the

company in terms of invested funds and achieved

outcomes.

Therefore, there should be time breaks in between

steps on the investment road map to measure, ex post4, the

4 The translation from Latin means "after the fact". The use of historical

returns has traditionally been the most common way to predict the

probability of incurring a loss on any given day. Ex-post is the opposite of

real impact of the increase in project management maturity

on the recorded project’s time reduction.

Based on this study, one knows the size of the

predicted decrease of impact in the next step for traditional

and agile projects. Therefore, one can compare possible

benefits with the estimated effort needed to continue with

the next step on the road map. As a result, one can

conclude that the investment in further progress in project

management maturity does not pay off and the limited company’s investment funds can be spent on other more

promising and vital company activities.

Limitations and Future Directions

The research is limited to three types of industries,

represented by 194 organisations with 107 belonging to

machinery, 48 to construction and 19 to IT companies. In quantitative analysis, the size of this sample, especially of

the latter two industries, can be assumed to be rather small.

Therefore, definitive conclusions and generalisations

supporting the outcomes of our study should await a larger

sample, especially of IT and construction industries.

The method of the prediction of the costs of

forthcoming projects by investigating experts’ opinions is

constrained by the quality of the respondents’ judgment, as

is the case in all surveys of experts. Generally, predicting

future outcomes is an extremely difficult issue (Glenn &

Gordon, 2003). However, it was a conscious decision to use this method, despite its limitations, to advance the

current stage of knowledge.

Some of the limitations of the study can be

strengthened to show the directions for future research.

The mainstream method would be to investigate the other

industries for which projects are a vital part of their

operations with the same method. Therefore, follow-up

research could be dedicated to the automotive, aerospace

or mining sectors.

Moreover, a study on the relationship between

different investment types and an increase in maturity level

would be advised. It would also be desirable for a new study to investigate the direct influence of different types

of investments on projects’ outcomes.

It may also be worth considering research into

checking whether project management is not

geographically sensitive, as the other recent studies on

project management performance areas suggest.

The results of this study advance the current state of

knowledge in the project management area. However, the

problem of linking investments in project management to

outcomes for an entire company is complex. Hence, the

considerations presented in the paper provide a better understanding of this complexity in the area of project

duration and could be a trigger point for further studies of

other types of project outcomes.

Acknowledgments

This work was supported by the National Science

Centre grant.

ex-ante, which means "before the event". Source:

http://www.investopedia.com/ retrieved on November 2013.

Seweryn Spalek. Finding a New Way to Increase Project Management Efficiency in Terms of Time Reduction

- 546 -

References

Adler, P. S., Riley, P., Kwon, S. W., Signer, J., Lee, B., & Satrasala, R. (2003). Performance improvement capability:

Keys to accelerating performance improvement in hospitals. California Management Review, 45(2).

http://dx.doi.org/10.2307/41166163

Ahmad, S., Mallick, D. N., & Schroeder, R. G. (2013). New Product Development: Impact of Project Characteristics and

Development Practices on Performance. Journal of Product Innovation Management, 30(2), 331–348.

http://dx.doi.org/10.1111/j.1540-5885.2012.01002.x

Avots, I. (1969). Why Does Project Management Fail. California Management Review, 12/1, 77–82.

http://dx.doi.org/10.2307/41164208

Baron, J. N., & Hannan, M. T. (2002). Organizational blueprints for success in high-tech start-ups: Lessons from the

Stanford Project on emerging companies. California Management Review, 44(3). http://dx.doi.org/10.2307/41166130

Basu, R. (2014). Managing quality in projects: An empirical study. International Journal of Project Management, 32(1),

178–187. http://dx.doi.org/10.1016/j.ijproman.2013.02.003

Becker, J., Knackstedt, R., & Poppelbuss, J. (2009). Developing Maturity Models for IT Management - A Procedure

Model and its Application. Business & Information Systems Engineering, 1(3).

Belt, P., Oiva-Kess, A., Harkonen, J., Mottonen, M., & Kess, P. (2009). Organisational maturity and functional

performance. International Journal of Management and Enterprise Development, 6(2), 147–164.

http://dx.doi.org/10.1504/IJMED.2009.022624

Booth, H. (2006). Demographic forecasting: 1980 to 2005 in review. International Journal of Forecasting, 22(3), 547–

581. http://dx.doi.org/10.1016/j.ijforecast.2006.04.001

Brucker, P., Drexl, A., Mohring, R., Neumann, K., & Pesch, E. (1999). Resource-constrained project scheduling: Notation,

classification, models, and methods. European Journal of Operational Research, 112(1), 3–41.

http://dx.doi.org/10.1016/S0377-2217(98)00204-5

Campos Silva, D. D., Santiago, L. P., & Silva, P. M. S. (2012). Impact of Premature Information Transfer on Cost and Development Time of Projects. IEEE Transactions on Engineering Management, 59(4), 692–704.

http://dx.doi.org/10.1109/TEM.2012.2187661

Chen, B., Liou, F. M., & Huang, C. P. (2012). Optimal Financing Mix of Financially Non-Viable Private-Participation

Investment Project with Initial Subsidy. Inzinerine Ekonomika-Engineering Economics, 23(5), 452–461.

Chen, Y. Q., Liu, J. Y., Li, B., & Lin, B. (2011). Project delivery system selection of construction projects in China.

Expert Systems with Applications, 38(5), 5456–5462. http://dx.doi.org/10.1016/j.eswa.2010.10.008

Cooke-Davies, T. (2007). Project Management Maturity Models. In P. W. G. Morris and J. K. Pinto (Eds.), Wiley Guide to

Managing Projects (pp. 1234–1255). Hoboken, NJ, USA: John Wiley & Sons. http://dx.doi.org/10.

1002/9780470172391.ch49

Cooper, R. G., Edgett, S. J., & Kleinschmidt, E. J. (1999). New product portfolio management: Practices and performance.

Journal of Product Innovation Management, 16(4), 333–351. http://dx.doi.org/10.1016/S0737-6782(99)00005-3

Davies, A., Gann, D., & Douglas, T. (2009). Innovation in Megaprojects: Systems Integration At London Heathrow

Terminal 5. California Management Review, 51(2). http://dx.doi.org/10.2307/41166482

del Cano, A., & de la Cruz, M. P. (2002). Integrated methodology for project risk management. Journal of Construction

Engineering and Management-Asce, 128(6), 473–485. http://dx.doi.org/10.1061/(ASCE)0733-9364(2002)128:6(473)

Dingsoyr, T., Nerur, S., Balijepally, V., & Moe, N. B. (2012). A decade of agile methodologies: Towards explaining agile

software development. Journal of Systems and Software, 85(6). http://dx.doi.org/10.1016/j.jss.2012.02.033

Dominguez, D., Worch, H., Markard, J., Truffer, B., & Gujer, W. (2009). Closing the Capability Gap: Strategic Planning

For The Infrastructure Sector. California Management Review, 51(2). http://dx.doi.org/10.2307/41166479

Elbanna, A. (2013). Top management support in multiple-project environments: an in-practice view. European Journal of

Information Systems, 22(3), 278–294. http://dx.doi.org/10.1057/ejis.2012.16

Ethiraj, S. K., Kale, P., Krishnan, M. S., & Singh, J. V. (2005). Where do capabilities come from and how do they matter? A study in the software services industry. Strategic Management Journal, 26(1), 25–45.

http://dx.doi.org/10.1002/smj.433

Fernandez, D. J., & Fernandez, J. D. (2008). Agile Project Management - Agilism Versus Traditional Approaches. Journal

of Computer Information Systems, 49(2), 10–17.

Fraser, P., Farrukh, C., & Gregory, M. (2003). Managing product development collaborations - a process maturity

approach. Proceedings of the Institution of Mechanical Engineers Part B-Journal of Engineering Manufacture,

217(11), 1499-1519. http://dx.doi.org/10.1243/095440503771909890

Galbraith, C. S., & Merrill, G. B. (1996). The politics of forecasting: Managing the truth. California Management Review,

38(2). http://dx.doi.org/10.2307/41165831

Inzinerine Ekonomika-Engineering Economics, 2014, 25(5), 538–548

- 547 -

Gary, K., Enquobahrie, A., Ibanez, L., Cheng, P., Yaniv, Z., Cleary, K., Kokoori, S., Muffih, B., & Heidenreich, J. (2011).

Agile methods for open source safety-critical software. Software-Practice & Experience, 41(9).

http://dx.doi.org/10.1002/spe.1075

Gasik, S. (2011). A Model of Project Knowledge Management. Project Management Journal, 42(3), 23–44.

http://dx.doi.org/10.1002/pmj.20239

Glenn, J. C., & Gordon, T. J. (2003). Futures Research Methodology. Washington D.C.: The United Nations University.

Grant, K. P., & Pennypacker, J. S. (2006). Project management maturity: An assessment of project management capabilities among and between selected industries. IEEE Transactions on Engineering Management, 53(1), 59–68.

http://dx.doi.org/10.1109/TEM.2005.861802

Griffin, A. (1993). Metrics for Measuring Product Development Cycle Time. Journal of Product Innovation Management,

10(2), 112–125. http://dx.doi.org/10.1016/0737-6782(93)90003-9

Griffin, A. (1997). The effect of project and process characteristics on product development cycle time. Journal of

Marketing Research, 34(1), 24–35. http://dx.doi.org/10.2307/3152062

Herroelen, W., & Leus, R. (2005). Project scheduling under uncertainty: Survey and research potentials. European Journal

of Operational Research, 165(2), 289–306. http://dx.doi.org/10.1016/j.ejor.2004.04.002

Hill, G. M. (2004). Evolving the project management office, a competency continuum. Information Systems Management,

21(4), 45–51. http://dx.doi.org/10.1201/1078/44705.21.4.20040901/84187.6

Hofman, M. (2014). Models of PMO functioning in a multi-project environment. Procedia - Social and Behavioral

Sciences, 119, 46–54.

Huang, X. L., Soutar, G. N., & Brown, A. (2004). Measuring new product success: an empirical investigation of Australian SMEs. Industrial Marketing Management, 33(2), 117–123. http://dx.doi.org/10.1016/S0019-

8501(03)00034-8

Iacovou, C. L., & Dexter, A. S. (2004). Turning around runaway information technology projects. California Management

Review, 46(4). http://dx.doi.org/10.2307/41166275

IOC (2007). The Olympic symbols, 2nd ed.. The Olympic Museum: International Olympic Committee.

Ji, F., & Sedano, T. (2011). Comparing Extreme Programming and Waterfall Project Results. IEEE.

Kach, A., Azadegan, A., & Dooley, K. J. (2012). Analyzing the successful development of a high-novelty innovation

project under a time-pressured schedule. R & D Management, 42(5), 377–400.

Keil, M., & Mahring, M. (2010). Is Your Project Turning into a Black Hole?. California Management Review, 53(1).

http://dx.doi.org/10.1525/cmr.2010.53.1.6

Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling (11 ed.). Hoboken,

NJ: John Wiley & Sons.

Kessler, E. H., and Chakrabarti, A. K. (1996). Innovation speed: A conceptual model of context, antecedents, and

outcomes. Academy of Management Review, 21(4), 1143–1191.

Khoshgoftar, M., & Osman, O. (2009). Comparison of Maturity Models. New York: IEEE.

Killen, C. P., & Kjaer, C. (2012). Understanding project interdependencies: The role of visual representation, culture and process. International Journal of Project Management, 30(5), 554–566. http://dx.doi.org/10.1016/ j.ijproman.

2012.01.018

Kowalska-Styczen, A., & Sznajd-Weron, K. (2012). Access to information in word of mouth marketing within a cellular

automata model. Advances in Complex Systems, 15(8), 17 http://dx.doi.org/10.1142/S0219525912500804

Lacher, R. C., Coats, P. K., Sharma, S. C., & Fant, L. F. (1995). A Neural-Network for Classifying the Financial Health of a Firm. European Journal of Operational Research, 85(1), 53–65. http://dx.doi.org/10.1016/0377-2217(93)E0274-2

Landeta, J. (2006). Current validity of the Delphi method in social sciences. Technological Forecasting and Social

Change, 73(5), 467–482. http://dx.doi.org/10.1016/j.techfore.2005.09.002

Langerak, F., Griffin, A., & Hultink, E. J. (2010). Balancing Development Costs and Sales to Optimize the Development

Time of Product Line Additions. Journal of Product Innovation Management, 27(3), 336–348.

http://dx.doi.org/10.1111/j.1540-5885.2010.00720.x

Lenfle, S., & Loch, C. (2010). Lost Roots: How Project Management Came to Emphasize Control over Flexibility and

Novelty. California Management Review, 53(1), 32–55. http://dx.doi.org/10.1525/cmr.2010.53.1.32

Levin, G. (2010). Interpersonal skills for Portfolio, Program, and Project Managers: Management Concepts.

McDonough, E. F. (2000). Investigation of factors contributing to the success of cross-functional teams. Journal of

Product Innovation Management, 17(3), 221–235. http://dx.doi.org/10.1016/S0737-6782(00)00041-2

Mahadevan, B. (2000). Business models for Internet-based E-commerce: An anatomy. California Management Review,

42(4). http://dx.doi.org/10.2307/41166053

Seweryn Spalek. Finding a New Way to Increase Project Management Efficiency in Terms of Time Reduction

- 548 -

Matsui, Y., Abdallah, A. B., Sato, O., & Kitanaka, H. (2008). International Comparison of Manufacturing Practices and

Performance.

Mian, A., Takala, J., & Kekale, T. (2008). Role of Organizational Culture for Knowledge Sharing in Projects. 2008

Portland International Conference on Management of Engineering & Technology, Vols 1-5, 962–968.

Morris, P. W. G. (1994). The Management of Projects. London: Thomas Telford. http://dx.doi.org/10.1680/mop.16934

Mullaly, M. E., & Thomas, J. (2010). Re-thinking project management maturity. Paper presented at the PMI Research and

Education Conference, Washington, D.C.

NAICS. (2012). North American Industry Classification System Washington, DC: U.S. Census Bureau.

Neverauskas, B., & Stankevicius, V. (2008). Project Management: Research and Studies at the Faculty of Economics and Management of Kaunas University of Technology. Inzinerine Ekonomika-Engineering Economics(4), 59–66.

Omorede, A., Thorgren, S., & Wincent, J. (2013). Obsessive passion, competence, and performance in a project

management context. International Journal of Project Management, 31(6), 877–888. http://dx.doi.org/10.

1016/j.ijproman.2012.09.002

Onkal, D., Sayim, K. Z., & Gonul, M. S. (2013). Scenarios as channels of forecast advice. Technological Forecasting and

Social Change, 80(4), 772–788. http://dx.doi.org/10.1016/j.techfore.2012.08.015

Palacios-Marques, D., Cortes-Grao, R., & Carral, C. L. (2013). Outstanding knowledge competences and web 2.0

practices for developing successful e-learning project management. International Journal of Project Management,

31(1), 14–21. http://dx.doi.org/10.1016/j.ijproman.2012.08.002

Pasian, B. L. (2011). Project management maturity: a critical analysis of existing and emergent contributing factors (pp.

266). Sydney: Faculty of Design, Architecture and Building, University of Technology.

Pemsel, S., & Wiewiora, A. (2013). Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31–42 http://dx.doi.org/10.1016/j.ijproman.2012.03.004

PMI. (2008). Organizational Project Management Maturity Model (OPM3®), Knowledge Foundation - 2nd Edition (pp.

204). Newtown Square, PA, USA: Project Management Institute.

Prasnikar, J., & Skerlj, T. (2006). New product development process and time-to-market in the generic pharmaceutical

industry. Industrial Marketing Management, 35(6), 690–702. http://dx.doi.org/10.1016/j.indmarman.2005.06.001

Radziszewska-Zielina, E. (2010). Analysis of the Impact of the Level of Partnering Relations on the Selected Indexes of

Success of Polish Construction Enterprises. Inzinerine Ekonomika-Engineering Economics, 21(3), 324–335.

Rohrbeck, R. (2010). Towards A Maturity Model For Organizational Future Orientation. Academy of Management

Proceedings, 2010(1), 1–6.

Rudzianskaite-Kvaraciejiene, R., Apanaviciene, R., & Butauskas, A. (2010). Evaluation of Road Investment Project

Effectiveness. Inzinerine Ekonomika-Engineering Economics, 21(4), 368–376. Scapolo, F., & Miles, I. (2006). Eliciting experts' knowledge: A comparison of two methods. Technological Forecasting

and Social Change, 73(6), 679–704. http://dx.doi.org/10.1016/j.techfore.2006.03.001

Shenhar, A. J. (2001). One size does not fit all projects: Exploring classical contingency domains. Management Science,

47(3), 394–414. http://dx.doi.org/10.1287/mnsc.47.3.394.9772

Shenhar, A. J., & Dvir, D. (1996). Toward a typological theory of project management. Research Policy, 25(4), 607–632.

http://dx.doi.org/10.1016/0048-7333(95)00877-2

Spalek, S. (2011). Managing projects in an industrial environment. An overview of the project management maturity

models. Paper presented at the 16th Annual International Conference on Industrial Engineering Theory, Applications

and Practice – IJIE, Stuttgart, Germany.

Spalek, S. (2013). Improving Industrial Engineering Performance through a Successful Project Management Office.

Inzinerine Ekonomika-Engineering Economics, 24(2), 88–98. Spalek, S. (2014). Does Investment in Project Management Pay Off? Industrial Management & Data Systems, 114(5),

832–856. http://dx.doi.org/10.1108/IMDS-10-2013-0447

Tan, W. P., Sauser, B. J., & Ramirez-Marquez, J. E. (2011). Analyzing Component Importance in Multifunction

Multicapability Systems Developmental Maturity Assessment. IEEE Transactions on Engineering Management,

58(2), 275–294. http://dx.doi.org/10.1109/TEM.2010.2071877

Thomke, S., & Reinertsen, D. (1998). Agile product development: Managing development flexibility in uncertain

environments. California Management Review, 41(1). http://dx.doi.org/10.2307/41165973

Wilson, K., & Wauson, J. (2010). The AMA handbook of business writing : the ultimate guide to style, grammar, usage,

punctuation, construction, and formatting. New York: American Management Association.

Wright, R. N., Rosenfield, A. H., & Fowell, A. J. (1995). Report on Federal Research in Support of the US Construction

Industry. Washington, DC.: National Science and Technology Council.

Wyrozebski, P., & Spalek, S. (2014). An Investigation of Planning Practices in Select Companies. Management and

Production Engineering Review, 5(2), 78–87. http://dx.doi.org/10.2478/mper-2014-0020

Zavadskas, E. K., Turskis, Z., Ustinovichius, L., & Shevchenko, G. (2010). Attributes Weights Determining Peculiarities

in Multiple Attribute Decision Making Methods. Inzinerine Ekonomika-Engineering Economics, 21(1), 32–43.

The article has been reviewed.

Received in October, 2014; accepted in December, 2014.

Copyright of Engineering Economics is the property of Engineering Economics and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.