Project Mgnt Essay

profilebentleymarie22
US_Census_FDCA_Case_Study_V1.0.pdf

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   1  

Failed  Project  Case  Study  –  The  United  States  2010  Decennial   Census  –  Field  Data  Collection  Automation  (FDCA)   A  Project  Management  case  study  by  Calleam  Consulting  Ltd  

Synopsis     Efforts  to  develop  more  efficient  ways  to  conduct  the  USA’s  decennial  national  census  get  derailed  when   a  project  to  introduce  handheld  computing  devices  turns  sour.    Despite  the  promise  of  improved   efficiency  and  cost  savings,  requirements  and  technical  performance  issues  identified  through  dress   rehearsals  bring  deep  seated  management  problems  to  a  head.    The  resulting  problems  force  the   Census  Bureau  to  abandon  core  components  of  the  program.    The  resulting  redesign  and  associated   increase  in  the  need  for  manual  labour  to  conduct  the  census  adds  $3B  in  costs  to  the  execution  of  the   2010  census.    

Background     It’s  an  administrative  task  on  the  grandest  of  scales.    Taking  ten   years  to  plan,  a  full  year  to  execute  and  months  of  analysis  to   complete,  the  decennial  census  of  the  United  States  of  America  is   a  mind  boggling  undertaking.    Requiring  the  participation  of  every   adult  living  in  the  United  States  and  drawing  on  the  efforts  of  1.3   million  temporary  workers  [1],  the  2010  decennial  census  was  the   United  States  largest  peacetime  mobilization.     Under  Article  1,  Section  2  of  the  US  constitution  a  census  of  all   persons  living  in  the  United  States  must  be  conducted  once  every   ten  years.    The  data  collected  becomes  a  critical  element  in  the   planning  of  both  government  and  private  activities.    Among  other   things,  census  data  is  used  to  allocate  seats  in  the  US  House  of   Representatives  and  for  the  annual  allocation  of  $182B  in  federal   funds  to  states  [2].    Given  the  money  involved  and  the  data’s  role   in  establishing  the  political  map  of  America,  accuracy  of  the  data   collected  is  of  paramount  concern.     The  task  of  producing  accurate  data  is  the  mandate  of  the  US   Census  Bureau.    Located  in  the  Washington  DC  area  the   department  oversees  the  census’s  multi-­‐billion  dollar  budget  and   manages  a  suite  of  programs  that  contribute  to  the  preparation   and  execution  of  the  census.     Planning  for  the  2010  census  stated  as  early  as  year  2000.    One  of   the  first  steps  in  the  process  was  an  examination  of  the  outcomes  of  the  2000  census  and  the  problems   that  had  been  encountered  along  the  way.    The  resulting  lessons  left  planners  with  two  immediate   problems.    

Y e a r 2 0 0 0 U S N a t i o n a l C e n s u s a t a g l a n c e 1. More than 300 million people

counted 2. 1.5 billion pieces of paper handled 3. 398 million forms Printed and

handled 4. 20 million maps processed 5. 5.8 million phone enquiries from the

public answered 6. 5 million square feet of space in

more than 500 locations across the USA rented

7. 860,000 temporary positions created & staffed by more than 500,00 workers

8. 16,000 phone lines , 15,000 PCs, 1,300 servers and 165 high speed optical scanners installed

9. 42 million in person interviews conducted with those who failed to submit mail-in census forms.

Source: Presentation to the Industry Advisory Council Executive – J. Waite, Mar 17, 2005

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   2  

The  first  was  a  matter  of  cost.    Even  allowing  for  inflation,  the  cost  of  the  census  was  rising   disproportionately  with  the  growth  in  population.    In  year  2000  adjusted  dollars,  the  $6.5B  cost  of  the   year  2000  census  was  double  that  of  the  1990  census  and  for  the  2010  census  costs  were  forecast  to  rise   to  between  $10B  and  $12B  [3].    The  rising  costs  were  drawing  the  attention  of  the  US  Congress  and  the   Bureau  was  asked  to  find  ways  of  reducing  costs.     The  second  issues  concerned  process.    The  increasing  population  and  its  growing  diversity  were   stretching  the  limits  of  the  census  as  it  had  traditionally  been  designed.    Both  the  1990  and  2000  census   had  encountered  difficulties  and  the  accuracy  of  the  data  produced  was  increasingly  being  called  into   question.    Despite  improvements  made  for  the  year  2000  census,  a  2001  report  by   PricewaterhouseCoopers  estimated  that  6  million  people  had  been  missed  and  3.6  million  had  been   double  counted  [4].    

The  Field  Data  Collection  Automation  Project   The  task  of  addressing  the  issues  fell  on  the  shoulders  of  Associate  Director  and  Chief  Operating  Officer   for  the  2010  decennial  census,  Preston  “Jay”  Waite.    Waite  was  a  career  officer  in  the  Census  Bureau   and  in  2001  he  was  assigned  full  and  direct  responsibility  for  overseeing  the  preparations  for  the  2010   census.    Waite  had  extensive  experience  within  the  Census  Bureau  and  in  all  regards  had  the  experience   and  training  to  be  considered  an  expert  in  census  taking  [5].     Soon  after  taking  office,  Waite  recognized  that  if  the  Bureau  was  to  meet  its  goals,  the  existing  paper   based  census  needed  to  be  redesigned.  He  recognised  that  increasing  the  level  of  automation  used   during  the  census  could  simultaneously  improve  accuracy  and  reduce  costs.    Despite  his  own  admitted   lack  of  technical  knowledge  [6]  Waite  decided  to  equip  the  bureau’s  525,000  field  workers  with  GPS   enabled,  on-­‐line,  handheld  computing  devices  instead  of  the  traditional  clipboard  and  paper.    Significant   portions  of  the  census  workload  could  then  be  automated,  processes  could  be  streamlined  and  the  data   recorded  could  be  more  readily  integrated  into  the  necessary  databases.     The  handheld  devices  were  to  be  used  for  two  primary  functions,      

1. The  pre-­‐census  address  canvassing  activity  in  which  census  workers  check  the  location  of  each   home  in  the  USA  so  that  the  Census  Bureau’s  master  address  list  can  be  verified  

2. The  post  census  Non-­‐Response  Follow-­‐Up  (NRFU)  interviews  that  needed  to  be  conducted  with   individuals  who  fail  to  respond  to  the  mail-­‐in  survey  forms.  

  In  principle  the  concept  made  sense,  GPS  would  improve  accuracy  in  the  agency’s  address  database  and   efficiencies  could  be  gained  when  locating  the  millions  of  people  needed  to  be  contacted  during  NRFU.     In  large  part  those  efficiencies  were  to  come  from  the  fact  that  field  workers  could  be  fed  real-­‐time   updates  when  a  non-­‐responder  mailed  in  a  late  response.    This  would  make  interviews  more  efficient   and  cut  down  on  the  wasted  effort  spent  contacting  people  who  missed  the  original  cut-­‐off  date,  but   had  submitted  a  late  response.    Given  the  number  of  people  sending  in  forms  late,  the  benefits  were   judged  to  be  considerable.     To  implement  his  ideas,  Waite  initiated  a  program  designed  to  leverage  the  new  technology.    The   program  represented  one  of  the  most  ambitious  programs  of  change  in  the  Bureau’s  history.    Between   the  years  2001  and  2004  Bureau  staff  worked  on  establishing  the  overall  business,  logical  and  physical  

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   3  

architectures  for  the  redesigned  census  [7,  8,  9].    One  of  the  most  critical  elements  in  the  program  was  a   project  titled  the  Field  Data  Collection  Automation  project  (FDCA).    The  FDCA  project  was  focused  on  the   deployment  of  handheld  devices  and  the  development  of  systems  to  support  the  address  canvassing   and  NRFU  functions.      Included  in  the  FDCA  project  scope  were;    

1. Acquisition  of  the  handheld  devices   2. Development  of  software  to  support:  address  canvassing,  workflow  management  for  field  

workers  (such  as  assignment  of  people  needing  to  be  contacted  as  part  of  NRFU  and  tracking  of   progress)  and  on-­‐line  forms  to  allow  data  collected  from  non-­‐responders  to  be  uploaded  

3. Operations  infrastructure  for  regional  and  local  census  offices  including  services  such  as   logistics,  training,  and  help  desk  support  for  12  regional  centers,  more  than  450  local  census   offices,  and  up  to  500  000  field  staff  [11]  

  Costs  were  estimated  to  be  $800  million  and  the  associated  systems,  processes  and  procedures  were  to   be  ready  for  initial  field  testing  in  2004  and  full  operational  testing  in  the  2006  dress  rehearsal.      

Chronology  of  the  FDCA  project    

Table  1  –  FDCA  timeline      

2010  US  Census  Field  Data  Collection  Automation  Timeline    

2001   Jay  Waite  is  appointed  Associate  Director  for  the  Decennial  Census.   2001   Waite  decides  that  handheld  computing  devices  will  be  used  for  address  canvassing  and  

NRFU  activities.    Process  of  redesigning  census  processes  to  leverage  technology  is   initiated.  

2002  -­‐  2003   Based  on  commercially  available  systems,  an  in-­‐house  prototype  is  created  by  the   Census  Bureau’s  Technologies  Management  Office.  

Feb  2004   Prototype  is  tested  during  initial  field  testing.    Significant  problems  are  identified   including:  Inability  to  handle  the  large  amounts  of  data  being  processed,  system  freezes,   data  transmission  problems,  memory  overload  and  difficulties  with  mapping  features.     Following  a  review  the  Census  Bureau  determines  that  it  lacks  the  necessary  technical   capabilities  or  management  resources  to  create  a  fully  functional  system  [11].  

4  Mar  2004   MITRE  corporation  (an  independent  not-­‐for-­‐profit  technical  consultant)  is  engaged  to   prepare  an  independent  assessment  on  the  feasibility  of  using  handheld  devices.  

28  Jul  2004   Based  on  research  and  observations  of  the  prototype  in  field  testing,  MITRE  completes   an  “Independent  Assessment  of  the  Use  of  Handheld  Computers  for  the  2010  Decennial   Census”.    Report  indicated  handheld  computing  is  feasible,  but  significant  risks  exist  [10].  

Jul  –  Oct   2004  

MITRE  assists  the  Census  Bureau  in  creating  a  FDCA  Statement  of  Work  for  use  in   tendering.    MITRE  also  develops  plans  and  procedures  for  an  FDCA  Project  Management   Office  (PMO)  [10].  

Jan  2005   In  part  due  to  slow  progress,  the  FDCA  project  is  reorganized.    Responsibility  for  FDCA  is   transferred  from  the  Field  Directorate  to  the  Decennial  Census  Directorate.    A  new   Project  Manager  is  assigned  and  a  Project  Management  Office  (PMO)  established  [11].  

Jan  2005   MITRE’s  support  to  the  FDCA  program  is  cancelled  after  the  new  Project  Manager  is  

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   4  

appointed  [10].   Feb  2005     MITRE  is  re-­‐engaged  but  only  to  prepare  an  independent  cost  estimates  for  the  FDCA  

project  [10].   Feb  2005   The  Census  Bureau  begins  initial  information  exchange  with  potential  suppliers  [11].   Apr  –  May   2005  

Pre-­‐solicitation  notice  and  draft  solicitation  paperwork  are  published  [11].  

Jun  2005   The  final  Request  For  Proposal  (RFP)  is  published  [11].   May  2005  –   Jan  2006  

Logical  and  physical  architectures  for  the  FDCA  system  are  developed  along  with  initial   project  management  plans  (risk  management,  communications  plan,  etc)  [7,  8,  9].  

Sep  2005  –   Jan  2006  

Qualified,  interested  parties  work  with  the  Census  Bureau  to  [11]  to  develop  prototypes   of  the  proposed  system  as  part  of  the  bidder  evaluation  process.  

30  Mar  2006   $595M  contract  is  signed  with  Harris  Corp  of  Melbourne,  Florida  to  supply  525,000   devices  and  develop  the  software.    Work  begins  on  detailed  requirements  analysis.  

Mar  2007   Harris  reports  “previously  established  milestones  &  budgets  were  at  risk  due  to  the   unanticipated  number  of  actual  requirements  emerging  from  detailed  requirements   decomposition”.    In  response  Census  Bureau  re-­‐engages  MITRE  and  requests  they   perform  a  “Red  Team”  analysis  of  the  FDCA  program  [10].      

Apr  2007   Address  canvassing  dress  rehearsal  shows  that  the  devices  suffer  from  performance,   data  transmission  and  stability  problems  (problems  not  dissimilar  to  those  encountered   during  the  2004  testing).    In  addition,  the  Bureau  determines  that  the  system  does  not   fully  meet  its  functional  needs.    

Apr  2007   MITRE  is  asked  to  assess  the  functionality  of  the  devices  and  their  performance.   6  Jun  2007   “Red  Team”  report  is  published.    Report  establishes  that  “FDCA  is  at  significant  risk  of  

cost  and  schedule  overruns  and  omission  of  essential  requirements  unless  major   changes  are  made  quickly”.    Report  firmly  establishes  that  problems  are  the  fault  of  the   government  and  not  Harris  [10].  

29  Nov  2007   MITRE  meets  with  Waite  and  his  superior  (Census  Bureau  Deputy  Director)  to  review   status.    Meeting  notes  are  leaked  revealing  that  there  is  no  integrated  plan,   communications  have  broken  down,  parties  are  unsure  of  the  requirements  and  that  on   the  Bureau’s  side  the  project  “lacks  a  leader  with  the  experience,  stature  or  passion  to   make  FDCA  successful”  [13].  

16  Jan  2008   The  Bureau  refocuses  themselves  and  Harris  is  provided  with  a  list  of  400  new  or   changed  requirements  for  the  handheld  devices.  

6  Feb  2008   Census  Bureau  Director  steps  in  and  forms  an  FDCA  Risk  Reduction  taskforce.    Taskforce   identifies  mitigation  strategies  and  ultimately  recommends  handheld  devices  be   dropped  from  NRFU  and  that  work  be  started  on  the  design  of  systems  needed  to   support  a  paper  based  NRFU.  

5  Mar  2008   Following  a  review  the  Government  Accountability  Office  designates  the  FDCA  project  as   being  at  “High  Risk”  of  failure.  

3  Apr  2008   The  US  House  of  Representatives  is  informed  of  the  failure  and  the  Bureau’s   recommendation  that  paper  based  non-­‐response  follow-­‐up  be  conducted.    An  additional   $3B  in  funding  is  requested.  

15  Apr  2008   Waite  is  replaced  by  Arnold  Jackson  who  instigates  regular  meetings  between   stakeholders  and  arranges  for  Harris  and  Census  staff  to  collocate  into  a  single  office   space  to  improve  communications  on  the  remaining  parts  of  the  project  (address   canvassing).  

23  Apr  2008   Waite  retires  from  the  Census  Bureau.  

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   5  

Causes  of  the  failure     On  the  surface  automation  of  a  census  appears  to  be  a  relatively  simple  task.    Despite  the  high  number   of  people  involved  and  the  geographical  distribution  of  the  work,  a  census  is  largely  an  exercise  in  the   collection  of  relatively  simple  sets  of  data.    Waite  himself  used  to  say  in  public  presentations  that   although  the  census  involved  large  numbers  of  people,  the  actual  census  processes  themselves  are   relatively  simple  [2].    Even  following  the  debacle,  a  Senior  Vice  President  at  MITRE,  echoed  the   sentiment  saying  "I've  been  part  of  complex  technology  programs  and  this  is  not  one  of  them...this  is   not  hard  to  do"  [14].         Of  course  complexity  is  relative  to  the  level  of  prior  experience  an  organization  has  with  such  projects   and  to  the  Census  Bureau  the  change  from  a  paper  based  system  to  a  technology  enabled  one   represented  the  type  of  large  project  that  they  had  not  previously  experienced.    Through  the  years  2001   and  2008,  the  Census  Bureau  began  to  understand  that  the  changes  they  were  making  were  significantly   more  challenging  that  they  had  first  perceived  them  to  be.    Following  the  collapse  of  the  program  in   April  2008,  when  asked  by  House  Appropriations  subcommittee  chairman  U.S.  Rep.  Alan  Mollohan  (D-­‐ W.Va.)  the  source  of  the  problems,  Waite  responded  “It  was  clear  to  me  that  there  wasn’t  sufficient   scepticism”  [15].     Waite’s  succinct  response  provides  the  key  to  understanding  the  causes  of  failure.    Despite  the  simplicity   of  the  processes  in  question,  moving  from  paper  to  handheld  computing  still  involved  major  challenges.     While  those  challenges  were  all  technically  achievable,  they  still  needed  to  be  adequately  understood   and  managed  through  to  conclusion  if  the  project  were  to  be  a  success.    Based  on  the  information   available  in  the  public  domain,  and  Waite’s  own  comments,  it  appears  that  the  management  of  the   Bureau  fell  into  the  trap  of  assuming  that  because  the  business  processes  themselves  were  simple,  the   project  itself  should  be  relatively  simple  too.    That  attitude  set  the  context  within  which  management   approached  the  project  and  resulted  in  a  series  of  mistakes  that  ultimately  snowballed  in  a  catastrophe.         At  the  time  the  failure  was  made  public  in  2008,  press  reports  focused  on  two  issues  as  being  the  root   causes  of  the  failure;  a  failure  to  establish  effective  communications  between  stakeholders  in  the   Census  Bureau  and  the  project  team  at  Harris  and  the  Bureau’s  failure  to  stabilize  a  firm  requirements   baseline.    Such  mistakes  were  clearly  avoidable.    Given  that  the  system  was  simply  the  automation  of  an   existing  paper  based  process,  the  requirements  were  indeed  knowable  had  sufficient  emphasis  been   placed  on  proper  requirements  elicitation.    In  addition,  had  proper  governance,  control  and  tracking   processes  been  put  in  place  effective  communications  could  have  been  established.     Information  available  from  the  leaked  MITRE  meeting  notes  and  the  US  Government  Accountability   Office  (GAO)  indicate  that  the  problems  went  beyond  those  two  basic  causes  and  included  [6,  13,  17]:    

1. Failure  in  the  early  years  of  the  project  to  establish  an  appropriate  governance  structure  that   would  bring  control  to  the  project  and  provide  management  with  visibility  so  that  issues  could   be  surfaced  and  addressed  early,  

2. Failure  to  put  in  place  a  Project  Manager  with  the  appropriate  experience  of  large-­‐scale  systems   development  projects,  

3. The  organization’s  inability  to  establish  clear  lines  of  authority  for  decision-­‐making,   4. Ineffective  business  analysis  (the  failure  to  establish  the  connections  between  operational  needs  

and  system  requirements),  

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   6  

5. Failure  to  establish  system  performance  requirements  (and  associated  acceptance  criteria)  or  to   develop  tests  to  ensure  those  benchmarks  could  be  achieved  by  the  systems  being  developed,  

6. The  Project  Manager’s  failure  to  build  an  effective  project  schedule  and  to  integrate  the  dates   for  work  in  the  Census  Bureau  with  those  for  work  being  done  by  Harris,  

7. Failure  to  perform  a  technical  or  operational  risk  analysis  early  enough  in  the  project,  and,     8. The  failure  to  take  the  lessons  learned  from  the  2004  field  trials  and  to  manage  those  as  risks  

during  the  full  scale  development  efforts  undertaken  by  Harris.    

A  failure  to  heed  the  warnings   As  well  as  the  general  Project  Management  issues  outlined  above,  the  FDCA  case  study  also  raises   another  important  question;  why  did  the  Bureau  fail  to  heed  the  many  warnings  that  were  issued  along   the  way?    Dress  rehearsals  and  tests  physically  demonstrated  that  there  were  very  real  problems.    As  for   many  large  federal  governmental  projects,  the  performance  and  status  of  the  project  was  also   monitored  by  the  GAO.    Through  their  published  reports  and  testimony  to  congress  the  GAO  continually   warned  of  project’s  serious  problems.    The  themes  that  emerged  from  those  early  warnings  closely   matched  the  eventual  causes  that  lead  to  the  failure.    Among  the  themes  raised  through  those  reports   were  the  fact  that  [16];  

1. The  Bureau  needed  to  define  specific  measurable  performance  requirements  for  the  handheld   mobile  computing  device  

2. The  Bureau  needed  to  develop  an  integrated  and  comprehensive  plan  to  control  costs  and   manage  the  project  

3. The  Bureau  needed  to  maintain  diligent  oversight  of  its  contractors;  and     4. The  Bureau  needed  to  strengthen  its  systems  testing  and  risk  management  activities.    

Many  of  these  warnings  given  to  the  Bureau  were  quite  specific  and  spelled  out  precisely  where  the   problem  areas  were.    Among  the  earliest  warnings  were  the  following  comments  published  following  an   evaluation  of  the  2004  field  testing  [17]:    

“Transmission  problems  and  inadequate  help  desk  support  were  the  main  reasons  for  the  serious   disruption  of  the  NRFU  operation  and  will  require  the  design  of  alternative  approaches  for  future   tests  and  the  2010  Census.  …  Census  needs  to  plan  contingencies  for  essential  NRFU   components,  like  transmissions,  whose  failure  would  jeopardize  field  operations.  …       Although  contracting  can  help  bring  the  necessary  system  and  software  development  expertise   and  management  discipline,  Census  still  faces  tremendous  challenges  in  capturing  lessons   learned  from  the  2004  and  subsequent  tests;  defining  complete  and  verifiable  system   requirements;  preparing  the  solicitation;  selecting  a  competent  contractor;  and  overseeing  the   contract  so  that  systems  are  fully  developed,  tested,  and  finalized  before  operations  begin.”  

  Similar  warnings  and  lengthy  reports  detailing  the  issues  were  published  in  2005,  2006  and  2007.     Although  documents  from  GAO  note  that  Census  Bureau  staff  had  acknowledged  the  issues,  clearly  the   issues  were  never  adequately  addressed.    Due  to  the  failure  of  the  Bureau  to  take  the  necessary   corrective  actions  the  GAO  escalated  the  issues  in  2008  by  designating  the  project  as  “high-­‐risk”.    While   management’s  underestimation  of  the  complexity  of  the  project  when  it  first  began  may  be  partially  

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   7  

understandable  (in  light  of  the  fact  that  the  business  processes  being  automated  were  relatively  simple),   failing  to  heed  the  warnings  that  were  published  along  the  way  is  harder  to  comprehend.     The  publically  available  documents  do  not  tell  us  why  the  Bureau  failed  to  heed  the  warnings.    As  a   result,  some  conjecture  is  required.    From  my  own  experience  I’ve  seen  a  number  of  projects  in  which   warnings  were  given,  but  the  senior  management  responsible  failed  to  take  action.    Sometimes  that  was   because  they  lacked  confidence  in  the  group  raising  the  concerns.    Other  times  it  has  been  because   there  are  so  many  fires  burning  that  they  didn’t  have  the  time  to  fully  comprehend  the  seriousness  of   the  issues  being  raised.  Oftentimes  I’ve  seen  management  rationalize  their  way  out  of  the  situation.  To   do  they  that  reject  any  criticisms  raised  and  convince  themselves  that  critics  are  naysayers  or  simply   trying  to  protect  their  own  reputations  rather  than  giving  credible  advise.    For  example,  managers   sometimes  take  the  attitude  that  auditors  are  raising  concerns  simply  to  justify  their  existence  and  that   any  concerns  they  raise  are  overstated  “just  in-­‐case”.     As  it  stands  the  real  reasons  the  Bureau  failed  to  take  appropriate  corrective  actions  remains  unknown.     Was  it  because  they  were  too  busy  fire-­‐fighting  to  sit  back  and  see  the  big-­‐picture  unfolding  around   them?    Was  it  a  lack  of  faith  in  the  GAO’s  capabilities  that  lead  the  Bureau  to  dismiss  their  advise?  Or  did   the  Bureau  simply  not  know  how  to  implement  the  recommendations?  We  don’t  currently  know.     Maybe  with  time  more  information  will  be  made  available  and  we  can  filling  in  the  missing  gap.    

Conclusions  and  recommendations   The  FDCA  project  illustrates  what  is  perhaps  the  most  classic  of  the  classic  mistakes  in  Project   Management:  The  under-­‐estimation  of  complexity  (click  link  for  additional  examples).    Although  the   business  process  being  implemented  by  FDCA  were  relatively  simple,  the  introduction  of  technology   introduced  layers  of  risk  and  complexity  that  had  not  been  present  in  the  paper  based  system  (data   transmission,  security,  systems  performance,  etc).    In  a  distributed  computing  environment  such  as   FDCA  (especially  one  that  needed  to  be  used  across  the  full  geography  of  the  USA)  such  challenges  can   be  very  considerable.    Based  on  the  actions  the  Census  Bureau  took  it  appears  that  the  full  scale  of  that   challenge  was  only  understood  after  considerable  effort  had  already  been  expended  and  a  good  portion   of  the  available  time  used  up.    Those  delays  directly  resulted  in  the  project  being  placed  under  schedule   pressure  and  that  pressure  may  well  have  resulted  in  the  failure  to  establish  the  project  requirements   sufficiently  before  initiating  the  tendering  process.   Beyond  that  fundamental  mistake  the  case  study  also  raises  questions  as  to  why  Waite  failed  to   establish  an  effective  governance  and  leadership  structure  until  it  was  clear  the  project  was  already   getting  into  trouble.    A  Project  Management  Office  (PMO)  was  put  in  place,  but  it  was  not  done  until  Jan   2005.    By  that  time  the  Bureau  had  already  tried  to  complete  the  project  themselves  and  the   requirements  and  RFP  were  already  underway.    In  his  role  as  Chief  Operating  Officer  for  the  census  he   would  have  been  too  senior  to  actively  manage  the  project  himself.    His  responsibility  was  to  establish  a   valid  management  structure  within  which  the  project  could  be  properly  controlled.  Had  an  effective   structure  been  in  place  from  the  project’s  inception  in  2001  it  is  likely  that  many  of  the  problems  could   have  been  avoided  and  those  issues  that  did  arise  would  have  had  someone  to  take  care  of  them  rather   than  being  ignored  for  so  many  years.         Again  the  Census  Bureau  is  not  alone  in  making  this  mistake.    The  failure  to  establish  appropriate   governance  structures  (click  for  examples)  is  another  common  theme  seen  in  many  project  failures.    In  

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   8  

part  the  causes  of  such  failures  often  comes  down  to  a  lack  of  training.    As  managers  rise  up  the  ranks   they  tend  to  take  responsibility  for  larger  and  larger  projects.    Unfortunately  few  organizations  provide   training  to  their  managers  in  how  to  deal  with  these  projects  and  each  manager  is  left  to  invent  their   own  set  of  governance  process.    Managers  who  have  a  background  in  delivering  large  projects  often   have  a  good  sense  for  what  to  do.    Managers  who  come  from  the  operational  side  of  the  organization   often  lack  Project  Management  experience  and  as  a  result,  fail  to  see  what  steps  they  need  to  take  in   order  to  establish  control  over  their  projects.    Waite  had  a  background  as  a  statistician  (more  of  a   technical  subject  matter  role)  and  in  operations,  but  a  review  of  available  information  about  his   background  does  raise  questions  as  to  whether  he  had  sufficient  Project  Management  experience  to   know  how  to  create  an  effective  governance  structure  for  a  project  of  this  type  (i.e.  one  with  a   significant  IT  component).    If  he  did,  the  conclusion  we  must  draw  is  that  he  did  not  use  that  knowledge   in  this  particular  project  for  some  reason.    What  seems  more  likely  is  that  he  lacked  the  required   knowledge  and  hence  didn’t  see  the  need  to  address  such  management  issues  until  the  weaknesses  in   the  project  caused  the  project  to  collapse  in  2008.     The  case  study  suggests  that  all  Senior  Managers  should  be  provided  training  in  how  to  establish   governance  over  a  project  and  what  it  takes  to  make  a  project  a  success.    Senior  executives  are  often  the   ones  sponsoring  projects  and  in  that  role  they  have  ultimate  responsibility  for  ensuring  they  have  set  the   project  on  the  road  to  success.    To  do  that  effectively  Senior  Managers  need  to:  know  the  basic   ingredients  needed  for  a  successful  project,  they  need  to  know  what  skills  and  knowledge  to  look  for  in   the  Project  Managers  they  appoint  and  they  need  to  understand  their  part  in  making  a  project  a  success.     In  addition,  they  need  to  have  enough  knowledge  to  be  able  to  adequately  oversee  their  Project   Managers  and  to  be  able  to  tell  if  a  Project  Manager  is  doing  an  effective  job  or  is  out  of  their  depth.     Sadly  few  organizations  provide  such  training  and  as  a  result  many  organizations  unwittingly  leave   themselves  open  to  similar  risks.     As  a  final  recommendation  the  case  study  suggests  that  Senior  Managers  need  to  heed  the  warnings   from  the  “singing  canaries”.    In  most  project  failures  there  are  warnings  and  signs  of  distress  that  are   apparent  long  before  the  final  coup-­‐de-­‐grace  occurs.    Staff  may  be  expressing  concerns,  milestones  may   be  getting  missed,  auditors  may  be  sounding  the  alarm  or  there  may  just  be  a  sense  that  the  project  is   not  under  proper  control.    In  their  role  as  project  sponsor  Senior  Managers  overseeing  projects  need  to   carefully  tune  themselves  into  these  warnings  and  recognise  when  the  warnings  are  genuine  signs  of   problems  rather  than  just  background  chatter  that  the  Project  Manager  is  able  to  deal  with  themselves.     Failing  to  see  the  signs  or  choosing  to  ignore  them  (as  happened  in  the  FDCA  project)  represents  a  lost   opportunity  to  take  corrective  actions  sufficiently  early.     At  the  end  of  the  day  the  2010  US  Census  did  of  course  go  ahead  and  the  herculean  administrative  task   was  completed  successfully.    Waite’s  vision  was  only  partially  realized  (the  system  was  used  for  address   canvassing,  but  not  for  NRFU)  so  the  mighty  pen,  paper  and  clipboard  continued  to  play  its  role.    The   underlying  business  need  for  accuracy  and  efficiency  still  exists  and  it  is  likely  that  the  team  planning  the   2020  census  will  need  to  revisit  the  NRFU  piece  once  again.    Hopefully  this  time  round  they  can  learn  the   lessons  and  land  a  successful  project  in  time  for  the  dress  rehearsals  to  begin  again.   Robert Goatham Principal Calleam  Consulting  Ltd Sessional Instructor University of British Columbia Director Wideman Education Foundation Aug 2012

US  2010  Census  –  Why  Projects  Fail  Case  Study  -­‐  Calleam  Consulting  Ltd  

V1.0   ©  Copyright  20012  Calleam  Consulting  Ltd,  all  rights  reserved   9  

Calleam  Consulting  Ltd   Calleam  Consulting  is  a  training  and  consulting  organization  specializing  in  the  fields  of  Project   Management  and  Project  Leadership.  A  provider  of  training  content  and  educational  services,  Calleam   works  with  leading  Universities,  academic  institutions  and  private  organizations  to  delivery  high  quality   training  programs  that  meet  the  needs  of  today's  fast  paced  businesses.    Specializing  in  online  learning,   Calleam  uses  cautionary  tales  from  past  failed  projects  to  help  organizations  prepare  for  the  challenges   they  will  face  tomorrow.    Visit  us  at  Calleam  Consulting  Ltd.   Footnote  

1. As  I’m  writing  this  case  study  I’ve  been  watching  the  unfolding  story  of  the  G4S  security  shambles  at  the   London  2012  Olympic  Games.    While  not  a  technology  project,  the  G4S    does  still  have  some  parallels  to   the  Census  Bureau.    Again  it’s  a  relatively  simple  project  (hire,  train  and  deploy  security  guards),  but  once   more,  the  scale  of  the  project  and  its  distributed  nature  have  proven  to  be  more  complex  than  G4S  seems   to  have  realized.  

References       [1]  For  2010  Census,  counting  gets  tougher  –  H.  El  Nasser  –  USA  Today,  8  Oct  2008   [2]  2010  Census  Planning  and  Development  –  P.  Jay  Waite,  Associate  Director  for  Decennial  Census  –  Industry  

Advisory  Council  Executive  Luncheon,  Washington,  DC    -­‐  17  Mar  2005   [3]  2000  Census  Lessons  Learned  for  Planning  a  More  Cost-­‐Effective  2010  Census    –  Government  Accountability  

Office,  Oct  2002   [4]  PricewaterhouseCoopers  projects  $4.1  billion  federal  funding  loss  in  31  states,  $3.6  billion  for  58  counties  –  US  

Census  Monitoring  Board  press  release,  7  Aug  2001   [5]  Jay  Waite  Bio,  Census  Bureau  website,  19  Apr  2007   [6]  Features  on  the  Brink  –  A.  Holmes  –  Government  Executive,  15    Jul  2007     [7]  2010  Census  Architecture,  Volume  II:  Physical  Architecture,  Version  1.0  –  Jan  31,  2006   [8]  2010  Census  Business  Architecture,  Version  1.0  –  Census  Bureau,  3  Oct  2003   [9]  2010  Census  Architecture,  Version  1.1  –  Census  Bureau,  24  Aug  2004   [10]  2010  Census:  Progress  on  the  Development  of  the  Field  Data  Collection  Automation  (FDCA)  Program  and  the  

Decennial  Response  Integration  System  (DRIS)  –  MITRE,  9  Apr  2008   [11]  Final  inspection  report  OSE-­‐17368,  US  Department  of  Commerce,  Inspector  General  Report,  Aug  2005     [12]  House  Committee  on  Oversight  and  Government  Reform  and  the  Subcommittee  on  Information  Policy,  

Census,  and  National  Archives  ,  April  9,  2008,  2010  Census:  Progress  on  the  Development  of  the  Field  Data   Collection  Automation  (FDCA)  Program  and  the  Decennial  Response  Integration  System  (DRIS),  J.  Providakes,   Ph.D.  Senior  Vice  President  and  General  Manager  Center  for  Enterprise  Management  The  MITRE  Corporation  

[13]  Talking  points  for  Meeting  with  Jay  Waite,  November  29,  2007  -­‐  MITRE   [14]  Mismanagement,  not  technology,  caused  Census  handheld  trouble,  auditors  say  –  G.  Nagesh  ,  April  9,  2008   [15]  U.S.  Census  post-­‐mortem:  An  absence  of  scepticism  –    Patrick  Thibodeau,  Computerworld.com  blog  April  04,  

2008     [16]  Chronology  of  Warnings  about  the  Census  Bureau’s  Field  Data  Collection  Automation  System  –  Rep.  H.  

Waxman,  Chairman,  Committee  on  Oversight  and  Government  Reform,  undated   [17]  Department  of  Commerce,  Office  of  Inspector  General,  U.S.  Census  Bureau  —  Improving  our  Measure  of  

America:  What  the  2004  Census  Test  Can  Teach  Us  in  Planning  for  the  2010  Decennial  Census  (Sept.  2004)   (OIG-­‐16949).