Plan Budget Management

Plan Budget Management

Part A

The following represent the resources needed in the home building project and the assigned costs.

Resources

Cost

Products and materials

$320,000

Construction plant, tools, and equipment

$250,000

Human resources

$240,000

Space and facilities

$150,000

Subcontractors

$90,000

Finance

$100,000

Permits

$10,000

Part B

The following represents the activities involved in the home building project and the resources needed to act.

Activities

Resource

cost

Preparation of drawing

Human resource

$3000

Estimation of material cost

Sub-contractor

$2000

Estimation of labor costs &contingencies

Sub-contractor and human resource

$1500

Preparation of a formal drawing of the project.

Human resource and subcontractors

$3000

Approval of the drawing from the authority.

Permits

$10,000

Marking the ground

Human resource

$100

Cleaning the marked ground

Human resource

$2,000

Marking the ground-based on accurate dimensions

Human resource

$800

Excavation

Construction plant, equipment, human resource, and subcontractors

$50,000

Compacting the ground

Construction plant, equipment, and human resource

$105,000

Putting solid bases on which footing can be placed.

Product and materials, human resource

$100,000

Footing replacement

Product and materials, human resources, construction equipment

$80,000

Shuttering

Construction equipment, human resource

$79,000

Footing concrete

Construction equipment, subcontractors, human resource, product, and materials

$150,000

Column costing

Construction equipment, human resources, subcontractors, products, and materials

$190,000

Constructing the base of the wall

Human resources, product, and materials, construction equipment

$100,000

Wall construction

Human resource, product, and materials

$60,000

Reinforcing openings using cement concrete

Human resource, product, and materials

$100,000

Pouring the roof slab

Human resources, product, and materials, construction equipment

$150,000

Fixing doors and windows

Human resource, product, and materials

$60,000

Fixing electrical works

Subcontractors, human resources, products, and materials

$40,000

Fixing plumbing work

Subcontractors, human resources, products, and materials

$50,000

Tiles laying

human resource, product, and materials

$35,000

Painting

Subcontractors, human resources, products, and materials

$90,000

Terrace waterproofing

Subcontractors, human resources, products, and materials

$45,000

Part 3

The following is a representation of the cumulative budget for the activities.

Activities

Resource

cost

Preparation of drawing

Human resource

$3000

Estimation of material cost

Sub-contractor

$2000

Estimation of labor costs &contingencies

Sub-contractor and human resource

$1500

Preparation of a formal drawing of the project.

Human resource and subcontractors

$3000

Approval of the drawing from the authority.

Permits

$10,000

Marking the ground

Human resource

$100

Cleaning the marked ground

Human resource

$2,000

Marking the ground-based on accurate dimensions

Human resource

$800

Excavation

Construction plant, equipment, human resource, and subcontractors

$50,000

Compacting the ground

Construction plant, equipment, and human resource

$105,000

Putting solid bases on which footing can be placed.

Product and materials, human resource

$100,000

Footing replacement

Product and materials, human resources, construction equipment

$80,000

Shuttering

Construction equipment, human resource

$79,000

Footing concrete

Construction equipment, subcontractors, human resource, product, and materials

$150,000

Column costing

Construction equipment, human resources, subcontractors, products, and materials

$190,000

Constructing the base of the wall

Human resources, product, and materials, construction equipment

$100,000

Wall construction

Human resource, product, and materials

$60,000

Reinforcing openings using cement concrete

Human resource, product, and materials

$100,000

Pouring the roof slab

Human resources, product, and materials, construction equipment

$150,000

Fixing doors and windows

Human resource, product, and materials

$60,000

Fixing electrical works

Subcontractors, human resources, products, and materials

$40,000

Fixing plumbing work

Subcontractors, human resources, products, and materials

$50,000

Tiles laying

human resource, product, and materials

$35,000

Painting

Subcontractors, human resources, products, and materials

$90,000

Terrace waterproofing

Subcontractors, human resources, products, and materials

$45,000

Total

$506,400