Unit 2 Assignment
Objective: Unit 2 Written Assignment - Weekly topics: Expected time for activities/ Outline of an information systems plan
I: Time estimates (10 points)
Calculate the expected time for the following activities.
|
Activity |
Optimistic Time |
Most Likely Time |
Pessimistic Time |
Expected Time |
|
A |
3 |
7 |
11 |
|
|
B |
5 |
9 |
13 |
|
|
C |
1 |
2 |
9 |
|
|
D |
2 |
3 |
16 |
|
|
E |
2 |
4 |
18 |
|
|
F |
3 |
4 |
11 |
|
|
G |
1 |
4 |
7 |
|
|
H |
3 |
4 |
5 |
|
|
I |
2 |
4 |
12 |
|
|
J |
4 |
7 |
9 |
|
II: Project diagrams (20 points)
A project has been defined to contain the following list of activities along with their required times for completion.
|
Activity No. |
Immediate Activity |
Time (weeks) |
Predecessors |
|
1 |
Collect requirements |
3 |
|
|
2 |
Analyze processes |
2 |
1 |
|
3 |
Analyze data |
2 |
2 |
|
4 |
Design processes |
6 |
2 |
|
5 |
Design data |
3 |
3 |
|
6 |
Design screens |
2 |
3,4 |
|
7 |
Design reports |
4 |
4,5 |
|
8 |
Program |
5 |
6,7 |
|
9 |
Test and document |
7 |
7 |
|
10 |
Install |
2 |
8,9 |
Specific tasks for exercise II project diagrams.
1. Draw a network diagram for the activities.
2. Construct a Gantt chart for the project.
3. Calculate the earliest expected completion time.
4. Show the critical path.
III. Preliminary outline of an information systems plan (20 points)
· Create a preliminary outline of an information systems plan.
· Choose a company that you are familiar with (or research one that you are note).
· Follow the “Outline of an information systems plan” shown in and complete a short information systems plan for the organization you chose.
· Write at least one brief paragraph for each of the seven categories in the outline.
FIGURE 4-15 Outline of an information systems plan
Located in: Hoffer, J, George, J, Valacich, J (2016). Modern Systems Analysis and Design. Upper Saddle River, NJ. Prentice Hall