Provide responses to the following questions

1. You are providing a review of contractor bids for a component of your upcoming project.  What can be done to determine whether or not a vendor’s bid is reasonable?

Ans: To estimate whether the contractor’s bid is reasonable or not:

· The bid must affirm to all terms and conditions of the contract

· The bid must have a time period associated with it

· The bid must adhere to the legal formatting

· The bid must be fair and transparent

· The contractor is eligible to bid for the contract

2. Describe the conditions for which parametric, analogous and bottom up estimation techniques work best, and provide 2 examples in support of each method.

Ans: The conditions for which parametric, analogous and bottom up estimation techniques work best are:

· Analogous comparison is based on the past performance of the company and works on the history data.

1. A project needs to be undertaken where a similar project has been done in the past

2. A project which requires a high amount of reliance on the past performance of the company

· Parametric technique incorporates both historic as well as mathematical data.

1. From past experience, you know that the system takes 4 days to complete. You employ 3 more servers. So the project completion time reduces to its 25%

2. The project in which the mathematical analysis needs to be conducted on the past data

· Bottom up estimation: Also known as WBS approach, requires breaking a comple problem into simpler units

1. When the project scope is vast and so braking up the process is essential

2. Project requiring the highest level of accuracy

3. Why is a cost management plan important?  How does the plan benefit the project manager?

Ans: Cost management plan is important for keeping a track on the project budget and check for deviations. A project manager can use the cost management plan to address any kind of risks percolating in the project. The expenses of the project can be easily tracked with the help of the cost management plan.

http://www.cvc.nic.in/sites/default/files/3%20Tender%20Stage.pdf

https://4pm.com/2018/02/21/project-estimating-technique-use

Part 2 Budget Estimating (30 points)

Using the same scenario from the previous unit on scheduling, create a time-phased budget for the following project.  Prepare a figure like Exhibit 10.9, CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project.  

Assume the following hourly rates:

Alcides $45 / hr.

Joan $50 / hr.

 

Activity ID

Activity

Immediate Predecessor

Duration in days

Resource

Work Hours per Day

A

Evaluate freezers

 

2

Alcides

6

B

Chart temperatures

 

6

Joan

4

C

Review service record

 

2

Alcides

 

D

Consult with HVAC engineer

A, B, C

3

Alcides

 

E

Develop construction plan

D

10

Joan

 

F

Complete IC assignment

E

2

Alcides

 

G

Complete ROI analysis

E

5

Joan

 

H

Conduct regulatory review

E

4

Joan

 

I

Obtain construction approval

F, G, H

2

Alcides

Ans: Below is the answer enlarge the image and do the answer in the excel sheet and also make sure you add tables to the table.

https://media.cheggcdn.com/media%2Fd44%2Fd4435682-4849-48e1-b9c7-b736ebc9b253%2FphplwVwnA.png

3: You are the project manager for a process improvement project for Company XYZ.    Prepare a figure like Exhibit 10.9 that illustrates the weekly and cumulative costs for the resource-leveled project. 

Hint: To accomplish this exercise, you’ll need to create a project schedule in MS Excel (or by hand), create resource assignments, assign costs to each resource, and assign the resources to each task.  Some resource leveling will be required. 

In this project, you have 3 employees: Ann, Becky and Clive.  Each person is limited to the amount of time allocated to your project.  Ann and Becky are available 30 hours/week; Clive is available 20 hours/week.  There hourly rates are: Ann: $60/hour; Becky: $35/hour; and Clive: $50/hour.

 

WBS

Activity

Immediate Predecessor

Estimated Duration in weeks

Resource

1

 Process Improvement Project

 

 

 

1.1

 Operational definition

 

 

 

1.1.1

 Research literature

 

3

Becky

1.1.2

 Identify and define terms

1.1.1

1

Ann

1.1.3

 Obtain approval of definition

1.1.2

2

Clive

1.2

 Target Selection

 

 

 

1.2.1

 Solicit partners for pilot

 

2

Ann

1.2.2

 Hold brainstorming meeting

1.2.1

2

Becky

1.2.3 

 Identify characteristics of targets

1.2.2, 1.3.1

1

Ann

1.2.4

 Obtain approval of partners

1.2.3, 1.1.2, 1.3.4

1

Clive

1.3

 Question set

 

 

 

1.3.1

 Identify process group members

 

2

Clive

1.3.2

 Develop question set

1.2.3

4

Ann

1.3.3

 Prototype and validate question set

1.3.2

3

Becky

1.3.4

 Add partners

1.3.1, 1.2.1

3

Becky

1.4

 Pilot process

 

 

 

1.4.1

 Schedule with target audience

1.2.4

2

Becky

1.4.2

 Conduct beta test

1.3.4, 1.2.4

2

Clive

1.4.3

 Process feedback from target audience

1.4.2

2

Ann

1.4.4

 Conduct pilot

1.4.3

2

Clive

1.4.5

 Analyze results

1.4.4

2

Clive

 

Mechanics (10 points)

Part 1 responses should be presented in a question-response format.  Use Arial font with 11 point. There is no word limit.

Your Instructor will use Turn-it-in to ensure your paper is authentic work.  To avoid plagiarism, see the course home page for more information and use the Purdue Online Writing Lab to learn how to paraphrase, summarize and cite the references you use in all academic writing assignments.

Parts 2 and 3 Use MS Excel (MS Project is not acceptable) to create the budget estimate and present it similar to Exhibit 10.9.  Show intermediate steps (schedule, resource schedule assignments, resource-leveled schedule and any other elements needed to create the time-phased budget estimate.

Ans :

WBS

Activity

Immediate Predecessor

Estimated Duration in weeks

Duration In Days

Resource

hours

week hours

Price

StartDate

EndDate

weekly Cost

Cumulatuve Cost

1.1.1

Research literature

3

21

Becky

30

90

35

Sep

22-Sep

3150

                    3,150

1.1.2

Identify and define terms

1.1.1

1

7

Ann

30

30

60

Sep

29-Sep

1800

                    4,950

1.1.3

Obtain approval of definition

1.1.2

2

14

Clive

20

40

50

Sep

13-Oct

2000

                    6,950

1.2.1

Solicit partners for pilot

2

14

Ann

30

60

60

Sep

15-Sep

3600

                  10,550

1.2.2

Hold brainstorming meeting

1.2.1

2

14

Becky

30

60

35

Sep

29-Sep

2100

                  12,650

1.2.3

Identify characteristics of targets

1.2.2, 1.3.1

1

7

Ann

30

30

60

Sep

6-Oct

1800

                  14,450

1.2.4

Obtain approval of partners

1.2.3, 1.1.2, 1.3.4

1

7

Clive

20

20

50

Oct

20-Oct

1000

                  15,450

1.3.1

Identify process group members

2

14

Clive

20

40

50

Sep

15-Sep

2000

                  17,450

1.3.2

Develop question set

1.2.3

4

28

Ann

30

120

60

Oct

3-Nov

7200

                  24,650

1.3.3

Prototype and validate question set

1.3.2

3

21

Becky

30

90

35

Nov

24-Nov

3150

                  27,800

1.3.4

Add partners

1.3.1, 1.2.1

3

21

Becky

30

90

35

Sep

6-Oct

3150

                  30,950

1.4.1

Schedule with target audience

1.2.4

2

14

Becky

30

60

35

Oct

3-Nov

2100

                  33,050

1.4.2

Conduct beta test

1.3.4, 1.2.4

2

14

Clive

20

40

50

Oct

3-Nov

2000

                  35,050

1.4.3

Process feedback from target audience

1.4.2

2

14

Ann

30

60

60

Nov

17-Nov

3600

                  38,650

1.4.4

Conduct pilot

1.4.3

2

14

Clive

20

40

50

Nov

1-Dec

2000

                  40,650

1.4.5

Analyze results

1.4.4

2

14

Clive

20

40

50

Ded

15-Dec

2000

                  42,650

Aggregated Project Budget 45,000 650 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 1.4.5 1.4.4 1.4.3 1.4.2 42,650 5,050 0,950 1.3.4 4,650 1.2.4 17,450 450 650 1.2.1 0,550 6,950 1.1.1 1.1.2 1.1.3 1.2.1 1.2.2 1.2.3 1.2.4 1.3.1 1.3.2 1.3.3 1.3.4 1.4.1 1.4.2 1.4.3 1.4.4 1.4.5 StartDate 0 Duration 14 14 14 14 28 14 14 14 14 14 -Cumulative Cost 3,150 4,950 6,950 10,550 12,650 14,450 15,450 17,450 24,650 27,800 30,950 33,050 35,050 38,650 40,650 42,650