Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

2013 The Clute Institute Copyright by author(s) Creative Commons License CC-BY 227

The Improvement Project

Of Science Construction PLC Mert Erer, Marmara University, Turkey

ABSTRACT

This case is designed to be an introduction to preparing improvement projects for insolvent

companies. After reading this text and answering the questions for discussion, the students

understand 1) the major aspects that should be highlighted in an improvement project, 2) the links

between the reasons for bankruptcy and countermeasures, and 3) the links between the planned

measures and their representation in financial statements.

Keywords: Insolvency; Improvement Project; Bankruptcy Code

INTRODUCTION

he Turkish Execution and Bankruptcy Code allows insolvent companies to apply to the commercial

court and propose a project for restructuring its debts and strengthening its financial status. If the

project is found to be serious and feasible by the court expert, the bankruptcy will be postponed for

one year.

This postponement is very important for insolvent companies, since the postponement of the decision

prevents the initiation of execution proceedings or suspends the pending execution proceedings until the end of the

postponement. Consequently, the plan plays a vital role for insolvent companies by allowing them to continue their

operations and emerge from bankruptcy.

THE CASE

Science Construction PLC offers design, project development, equipment provision, project financing and

contracting services for highways, roads, tunnels and viaducts. The most important customers of the company are

Istanbul, Ankara, Ismir, Bursa, and Kocaeli Metropolitan Authorities and the General Directorate of Highways. The

company sells asphalt to these customers and paves the roads under their authority.

The asphalt production capacity of the company is 520,000 tonnes per year. The headquarters is located in

Istanbul. There are five active construction sites in three different cities. The company owns a license for removing

equipment domestically that is valid until June 2014 as well as ISO 9001:2009 for its quality management system

and OHSAS 18001:2008 for occupational health and safety management standards.

REASONS FOR BANKRUPTCY

Effects Of The Global Financial Crisis

The main reason for the bankruptcy is the ongoing financial crisis that began in 2008. Throughout the

financial crisis, local demand shrank drastically, the possibility of finding financial resources became limited, and

the cost of credit and credit guarantees rose. As a result, the company had difficulties preserving its profitability and

maintaining the cash balance.

Public investments and the budget of metropolitan authorities were also decreased due to inadequate

resources. As a company whose client base was primarily in the public sector, the effects of the crisis were

significant.

T

Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

228 Copyright by author(s) Creative Commons License CC-BY 2013 The Clute Institute

Problems in Collecting Receivables

The company experienced problems collecting its receivables from the metropolitan authorities in a timely

fashion. The receivables could only be collected between seven to nine months after billing. This delay resulted in

the necessity of finding additional financial resources to settle short-term debts. Additional financial resources were

created either by selling the receivables to factoring companies, by discounting progress bills, or by taking bank

credits. The financing cost of selling receivables was 15%, it was 13% for discounting progress bills and between 11

to 16% for bank credits.

If payment terms are delayed when buying materials and equipment, in order to delay cash outflows, the

prices rise. Consequently, the profitability is diminished and the long-term cash flow is damaged .

Differences in The Development Of Costs And Contract Prices

Selling asphalt to metropolitan authorities constitutes the largest proportion of revenues. The tenders are

issued in February and March and production takes place between May and November. The price difference

between the date of securing the contract and the delivery date is reflected in the progress payments at the level of

the producer’s price index (PPI) according to the Public Procurement Law. In 2010, in particular, the PPI remained

substantially below the increase in asphalt prices. The development of asphalt prices and the PPI are shown in Table

1. The raw material prices for the company rose by 18% between May and November 2010, but the PPI announced

by the Statistical Institute was 7% for the same period. The production costs rose, but the company could not secure

a price increase to match the difference.

Table 1: The Development Of Asphalt Prices And The PPI

Date Raw Material Unit Price * (TRY/t)

21.05.2010 50/70 Asphalt Price 710.00

13.11.2010 50/70 Asphalt Price 837.00

21.05.2010 70/100 Asphalt Price 702.00

13.11.2010 70/100 Asphalt Price 829.00

* Prices of the Ismit Refinery, VAT not included.

Asphalt Price Increase Rate (50/70) 17.9%

Asphalt Price Increase Rate (70/100) 18.1%

Producer’s Price Index 7.0%

STRENGTHS AND WEAKNESSES OF THE COMPANY

The strengths of the company can be summarised as:

• Over 20 years of experience in the sector • Trust in the brand Science Construction because of successfully completed major contracts • Good relationships with the Istanbul and Ankara Metropolitan Authorities and administration of the

General Directorate of Highways

• Business Experience Certificate given by the Authorities which enables the company to participate in tenders up to 95,000,000.00 TRY

• Licence for removing equipment domestically so that transportation of materials and equipment can be handled by the company

• One of the best equipment pools in Turkey and qualified staff to use the equipment

The weaknesses of the company are:

• Problems in collecting receivables • Short-term debt burden with high financing costs • Huge difference between the increase in production costs and the increase in contract values • Problems in cost control

Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

2013 The Clute Institute Copyright by author(s) Creative Commons License CC-BY 229

FINANCIAL ANALYSIS

The current ratios are 0.95, 0.90 and 0.82 for the years 2008, 2009 and 2010, respectively. The current ratio

is under the industry average of 1.20 and has been decreasing for three consecutive periods. The working capital of

the company has also been negative in the last three periods. Thus, the company does not have sufficient current

assets to cover its short-term debt. This gap has been financed by assuming more short-term debt. The leverage of

the company was 5.65 in 2010. Since the leverage is high, the risk premium of the company is also high, which

leads to higher interest rates for bank credits.

High short-term debt accumulated over the years and high interest rates put substantial pressure on the

company limiting its ability to make decisions. The company plans to substitute the short-term debt with equity in

order to correct this unhealthy financial condition.

Although the revenues are increasing, operating profit and net income have deteriorated over the last three

periods. The primary reason is that the increase in cost of services sold was more than the increase in revenues. The

cost of services sold increases since the price of raw materials rises. Permanent measures will be taken in order to

minimize costs and keep the company running.

MEASURES TO BE TAKEN

Payments From The Shareholders

Capital Increase

The issued capital will be increased by 2,000,000.00 TRY by March 2011 and 500,000.00 TRY will be paid

in the same month. The remaining 1,500,000.00 TRY will be paid in three equal terms in 2011 and 2012. The

payment dates are shown in the Cash Flow Statement.

Collecting Receivables from the Shareholders

Shareholder F. K. will pay his total debt of 1,876,564.72 TRY in three equal terms in February, August and

December 2011. Shareholder, Hisal Moving PLC, will pay 300,000.00 TRY in 2011 and 350,000.00 TRY in 2012.

Cost Cutting

Cuts in Production Costs

Raw Materials

Purchase price for crushed stone is 14 TRY. The purchase price consists of the price of the crushed stone

(6.50 TRY) and transport costs (7.50 TRY). Starting in 2011, the company will handle the transportation with its

own vehicles and cut transport costs by 3.00 TRY. The cost of raw materials is given in Table 2.

Table 2: Cost Cutting for Raw Materials per Unit

Raw

Material

Amount per

Unit

Current Purchase Price per

Unit (TRY)

Current Amount

(TRY)

Planned Purchase Price per

Unit (TRY)

Planned Amount

(TRY)

Crushed

Stone 1.0000 14.00 14.00 11.00 11.00

Bitumen

50/70 0.0447 843.00 37.68 843.00 37.68

Fuel oil 5.5000 1.44 7.92 1.44 7.92

Gas oil 1.0000 2.62 2.62 2.62 2.62

Total 62.22 59.22

Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

230 Copyright by author(s) Creative Commons License CC-BY 2013 The Clute Institute

Direct Labour

* There were 102 employees at the beginning of 2010. Some unqualified personnel were dismissed and the number

of staff was reduced to 86 as of January 2011. In the coming periods, the work force will be organised according to

the number and value of contracts the company secures.

* The employees that do not work due to underproduction will be given unpaid leave of absence for the period.

Thus, the salaries and the subsidiary costs (e.g. meals, services) will decrease.

Production Overheads

* Weekly budgets will be prepared in order to control the consumption of indirect materials. No consumption above

the caps set by the budget will be authorised.

General Overheads

* The number of vehicles used by the management will be decreased in order to reduce the maintenance, insurance,

and fuel costs.

* The purchase of consumables will be centralised and credit cards given to the management will be collected so

that an efficient cost control can be achieved.

* The night lighting of the headquarters and the construction sites will be removed. A saving in energy costs of up to

50% can be realised by replacing the costly lighting with halogen lamps, as can be seen in Table 3.

Table 3: Energy Cost Savings

Plant Energy Costs before 2011

(monthly, actual, TRY)

Energy Costs after 2011

(monthly, planned TRY)

Anticipated Energy Cost

Savings (monthly)

HQ 667.88 320.58 347.30

Construction Site_1 2,671.53 1,442.63 1,228.90

Construction Site_2 2,385.30 1,168.79 1,216.50

Construction Site_3 1,908.24 961.76 946.48

Construction Site_4 858.71 446.53 412.18

Construction Site_5 1,049.53 503.77 545.77

Total 9,541.19 4,844.06 4,697.13

Revenues

* Infrastructure investments are gathering speed since the municipal elections are near. Ankara Metropolitan

Authority contracted 950,000 tonnes of asphalt in 2011. The company has 25% market share in the Ankara district.

Hence, it can be assumed that at least 230,000 tonnes will be obtained by the company in the following period. With

contracts from other authorities, the company expects a sales volume of 265,000 tonnes.

* The company expects the market volume of the private sector to shrink by 5%, thus the sales volume of 20,000

tonnes in 2010 will be reduced to 19,000 tonnes.

PROFORMA FINANCIAL STATEMENTS

Proforma Income Statement

Proforma income statements is shown in Table 4. The profitability will be 11.06% in 2011 and 9.18% in 2012.

Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

2013 The Clute Institute Copyright by author(s) Creative Commons License CC-BY 231

Table 4: Proforma Income Statement

01.01.-31.03. 01.01.-30.06. 01.01.-30.09. 01.01.-31.12. 2012

Revenues 1 5,488,000.00 18,210,500.00 31,499,500.00 37,705,900.00 39,591,195.00

(Cost of Services Sold) 2 (4,737,270.44) (15,166,742.12) (24,206,782.97) (30,566,013.24) (32,705,634.17)

Gross Profit 750,729.56 3,043,757.88 7,292,717.03 7,139,886.76 6,885,560.83

(General Administrative

Expenses) 3 (62,742.53) (218,236.13) (370,616.85) (523,197.58) (559,821.41)

Profit from On-going

Operations 687,987.03 2,825,521.75 6,922,100.18 6,616,689.18 6,325,739.42

(Financing Costs) 4 (389,938.74) (679,877.48) (910,198.35) (1,090,519.23) (1,199,571.15)

(Financial Leasing Costs) 5 (358,944.98) (691,035.84) (1,023,126.69) (1,355,217.54) (1,490,739.29)

Profit (60,896.69) 1,454,608.43 4,988,775.14 4,170,952.41 3,635,428.98

1. Revenues from new contracts and the relevant costs are shown in Table 5. Most of the sales will be made to

the public sector. The costs are based on the calculations in “Raw Materials”.

Table 5: Revenues From New Contracts

01.01.-31.03. 01.01.-30.06. 01.01.-30.09. 01.01.-31.12.

Revenues 2011

(from new contracts) 0.00 8,145,900.00 18,274,400.00 24,480,800.00

Amount (t) 0.00 9,500.00 19,000.00 19,000.00

Revenues - Private Sector (TRY) 0.00 818,900.00 1,637,800.00 1,637,800.00

Amount (t) 0.00 85,000.00 193,000.00 265,000.00

Revenues – Public Sector (TRY) 0.00 7,327,000.00 16,636,600.00 22,843,000.00

Costs 2011

(from new contracts) 0.00 5,596,668.00 12,555,488.00 16,819,616.00

Amount (t) 0.00 9,500.00 19,000.00 19,000.00

Costs - Private Sector (TRY) 0.00 562,628.00 1,125,256.00 1,125,256.00

Amount (t) 0.00 85,000.00 193,000.00 265,000.00

Costs – Public Sector (TRY) 0.00 5,034,040.00 11,430,232.00 15,694,360.00

Profit (TRY) 0.00 2,549,232.00 5,718,912.00 7,661,184.00

2. Cost of services sold consists of raw materials, direct labour, construction site expenses and cost of vehicles

and equipment used in the production. The latter two comprise the overhead costs. Cost of services sold is

shown in Table 6.

Table 6: Cost of Services Sold

01.01.-31.03. 01.01.-30.06. 01.01.-30.09. 01.01.-31.12.

Raw Materials 0.00 5,596,668.00 12,555,488.00 16,819,616.00

Direct Labour 3,413,771.40 7,082,285.80 8,081,351.80 9,080,417.80

Overheads 1,323,499.04 2,487,788.32 3,569,943.17 4,665,979.44

Total 4,737,270.44 15,166,742.12 24,206,782.97 30,566,013.24

3. General administrative expenses consist of office expenses and the cost of vehicles used by management.

Water, energy, telephone, gas, internet connection, heating, cable television, cleaning and representation

expenses make up the office expenses. General administrative expenses are shown in Table 7.

Table 7: General Administrative Expenses

01.01.-31.03. 01.01.-30.06. 01.01.-30.09. 01.01.-31.12.

Office Expenses 54,942.53 202,636.13 348,116.85 493,597.58

Other 7,800.00 15,600.00 22,500.00 29,600.00

Total 62,742.53 218,236.13 370,616.85 523,197.58

4. Financing costs consist of interest costs of bank credits taken for the purchase of construction equipment

and other bank credits, as can be seen from Table 8.

Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

232 Copyright by author(s) Creative Commons License CC-BY 2013 The Clute Institute

Table 8: Financing Costs

01.01.-31.03. 01.01.-30.06. 01.01.-30.09. 01.01.-31.12.

Equipment Nr. 64973 56,301.38 112,602.74 168,904.12 225,205.51

Caterpillar Nr. 298573 18,547.37 37,094.73 46,024.23 54,953.73

Total (Credits for Equipment) 74,848.75 149,697.47 214,928.35 280,159.24

Interest payments 313,500.00 527,000.00 690,500.00 804,000.00

Transaction costs 810.00 1,620.00 2,430.00 3,240.00

Commission Fee 780.00 1,560.00 2,340.00 3,120.00

Total (Other Credits) 315,090.00 530,180.00 695,270.00 810,360.00

Total 389,938.75 679,877.47 910,198.35 1,090,519.24

5. Interest costs for financial leases are shown in Table 9.

Table 9: Financial Leasing Costs

01.01.-31.03. 01.01.-30.06. 01.01.-30.09. 01.01.-31.12.

Equipment_9675 84,514.60 169,029.19 253,543.79 338,058.38

Equipment_84963 93,590.28 187,180.56 280,770.83 374,361.11

Equipment_2367 93,448.85 160,043.57 226,638.29 293,233.01

Equipment_16789 87,391.26 174,782.52 262,173.78 349,565.04

Total 358,944.99 691,035.84 1,023,126.69 1,355,217.54

Proforma Cash Flow Statement

The proforma cash flow statement is shown in Table 10. Cash inflows from previous contracts result from

the completed operations in Kocaeli and Ismir. The claims will be collected in March and August. The payments for

crushed stone, fuel oil and gas oil are made three months after delivery, whereas the payment for bitumen 50/70 is

made in the month of the delivery.

Table 10: Cash Flow Statement

01.01.-31.03. 01.01.-30.06. 01.01.-31.09. 01.01.-31.12. 2012

Asphalt sales 4,390,400.00 15,446,480.00 28,288,896.00 35,822,499.20 37,611,635.25

Previous contracts 1,400,000.00 1,400,000.00 3,000,000.00 3,000,000.00 0.00

Shareholders (collecting receivables) 925,521.57 925,521.57 1,551,043.15 2,176,564.72 350,000.00

Capital increase 500,000.00 500,000.00 500,000.00 1,000,000.00 1,000,000.00

Total Cash Inflows 7,215,921.57 18,272,001.57 33,339,939.15 41,999,063.92 38,961,635.25

Cost of services sold (cash) 4,016,885.36 11,175,182.18 19,435,857.60 27,404,243.76 29,108,014.41

Repayment of debts (previous periods) 1,700,000.00 4,650,000.00 8,250,000.00 9,070,000.00 5,720,000.00

Repayment of bank credits 972,162.00 1,944,324.00 2,916,486.00 3,798,648.00 2,199,571.15

Financial leasing payments 149,560.41 437,492.01 863,794.80 1,428,468.77 1,490,739.29

Total Cash Outflows 6,838,607.77 18,206,998.19 31,466,138.40 41,701,360.53 38,518,324.85

Net increase (decrease) in cash and cash

equivalents 377,313.80 65,003.39 1,873,800.75 297,703.39 443,310.40

BUDGET CONTROL

The budget will be measured quarterly to ensure targets are met. The budget will be managed mainly by

controlling the development of expenses since they are easier to affect by economy measures than revenues.

Tolerance rate for budget control is set at three percent. If a three percent positive or negative variance is

identified in budgeted revenues or expenses, the reasons for the variance will be analysed thoroughly.

Once the reasons for the variance are identified, appropriate measures will be taken to correct the variance

or if the variance cannot be corrected, the budget will be revised.

Journal of Business Case Studies – May/June 2013 Volume 9, Number 3

2013 The Clute Institute Copyright by author(s) Creative Commons License CC-BY 233

CONCLUSION

Case studies showing the preparation of improvement projects for insolvent companies are very scarce, so

this case fills an important gap. This case was prepared for students to show that the improvement project should

include reasons for insolvency, planned measures, and their timing. Furthermore, the financial effects of the

measures to be taken should also be shown by preparing budgets and proforma financial statements in order to

emphasise the seriousness and the feasibility of the project.

QUESTIONS FOR DISCUSSION

1. What could Science Construction PLC have done in order to avoid bankruptcy?

2. Assume that you are a debtor of Science Construction PLC and the company has given you this project. Is

there any additional financial or non-financial information that you would like to receive? What would you

like to see in an improvement project as a debtor?

3. What problems could Science Construction PLC face when they implement the measures explained in the

project? What should management do to execute the project effectively?

4. The project has to be approved by the court in order to get a bankruptcy postponement. The court expert

writes a report on the project if the plan is serious and feasible. Assume that you are the court expert for the

improvement project of Science Construction PLC. What would you write in your report?

AUTHOR INFORMATION

Mert Erer is an Associate Professor of Accounting at Marmara University. He primarily teaches international

financial reporting and financial analysis. He has published in the areas of financial reporting, corporate governance

and corporate restructurings. E-mail: [email protected]