Project Management IV Research Paper
Towards improved port capacity investment decisions under uncertainty: a real options approach Matteo Balliauw , Hilde Meersman , Eddy Van de Voorde and Thierry Vanelslander
Department of Transport and Regional Economics, Faculty of Business and Economics, University of Antwerp, Antwerp, Belgium
ABSTRACT Port activity plays an important role in facilitating international trade. Sufficient capacity is indispensable for a port to attract flows to a region and retain them. The capacity decision is the result of a trade-off between investment and waiting costs. Traditional methods to value expansion projects do not deal adequately with managerial flexibility in the face of uncertainty from different sources in the complex port environment. In this paper, real options (RO) models are identified as an alternative method to making project valuations and investment decisions, as they attribute the correct value to managerial flexibility under uncertainty. In order to be able to build and use such RO models for port capacity investment decisions, the sources and implications of uncertainty in the port and the different RO model specifications need to be understood. To this end, both the literature about uncertainty in the port context and the literature about real options models are reviewed in order to provide researchers who want to build their own decision-making models, with the necessary knowledge of both fields. The review makes clear that the complex interactions in and competition between the logistics chains and their actors coming together in ports have significant impacts on port capacity. Uncertainty is also caused by uncertain international trade flows and changes in legislation following new technologies and environmental impacts. An analysis of the components of some general RO models shows how the options of flexible output, investment size and timing are valued by RO models in a setting with demand uncertainty. Moreover, the review presents researchers with insights in how to deal with cooperative and competitive interactions in the chain, time to build, cyclical markets and legislation changes. It also shows how to value the expansion and the phased investment options. The new insights resulting from this review are subsequently combined in a framework that serves as a guideline to build RO models for port capacity investments. Finally, an exemplifying application of the framework is used to build an actual port capacity investment decision model.
ARTICLE HISTORY Received 25 May 2016 Accepted 30 November 2018
KEYWORDS Port capacity; investment; valuation; decision making; real options; uncertainty
© 2018 Informa UK Limited, trading as Taylor & Francis Group
CONTACT Matteo Balliauw [email protected] Department of Transport and Regional Economics, Faculty of Business and Economics, University of Antwerp, Prinsstraat 13, 2000 Antwerp, Belgium
TRANSPORT REVIEWS 2019, VOL. 39, NO. 4, 531–552 https://doi.org/10.1080/01441647.2018.1556228
1. Introduction
Ports perform important activities to facilitate the international transportation of goods and international trade, such as cargo handling and storage (Blonigen & Wilson, 2008). Sufficient capacity is required in ports to perform port operations effectively and efficien- tly. In addition, since ports create value for the economy, too little capacity could result in GDP declines and freight delays in the region (De Langen, Turró, Fontanet, & Caballé, 2018). In a port and in transportation in general, it is even more important than in a pro- duction environment to have the optimal amount of capacity installed, since the transport service is not storable (de Weille & Ray, 1974).
When deciding on the optimal capacity in a port, an important trade-off between two cost components needs to be considered. On the one hand, investment costs are the expenses for expansion and maintenance of the capacity in place. This cost is positively related to the amount of capacity. On the other hand, congestion costs are incurred by the transporting firm that has to wait in the port due to bottlenecks. As shown by Blau- wens, De Baere, and Van de Voorde (2016) and De Borger, Proost, and Dender (2008), the value of time for a ship waiting can be high and forms an important part of the gen- eralised cost of the maritime logistics chain. Such congestion costs can be avoided by additional capacity, since it decreases the probability of waiting (Macário, 2014). Of course, also other solutions are possible, such as congestion pricing (Zhang, 2007).
A mismatch between demand and capacity can result in periods of scarcity or overca- pacity. Underinvestment could result in congestion and costly waiting times with a result- ing loss in social welfare in the form of lost consumer surplus. Overinvestment could lead to overcapacity at high investment costs. Nevertheless, overcapacity is often encountered as a result of the large investment size and long lead-times (Meersman & Van de Voorde, 2014a). Overcapacity may also exist in a port to reduce the attractiveness of a competitor’s investment option, known in the literature as entry deterrence (Huberts, Huisman, Kort, & Lavrutich, 2015). Prices may be lowered in the case of overcapacity to attain the desired capacity utilisation rate (Meersman, Van de Voorde, & Vanelslander, 2010; Xiao, Fu, & Zhang, 2013). The possibility of periods of imbalance indicates the importance of a joint analysis of the amount of available capacity, the amount and timing of the capacity expan- sion and the level of the output price (Strandenes, 2014).
Port capacity investment decisions involve considerable risk and uncertainty for the investing port actors, such as port authorities, terminal operating companies (TOC) and gov- ernments (Kakimoto & Seneviratne, 2000b; Musso, Ferrari, & Benacchio, 2006). They arise from many sources: different economic decisions taken by many logistics actors in competi- tive logistics chains; unpredictable income from trade, uncertainty about the amount of sea- borne traffic and possible resulting congestion; uncertainty about new technological, environmental, politicaland legal developments (Giuliano, 2007; Meersman, 2005).Variability and uncertainty, risk and managerial flexibility are not taken into account fully in traditional valuation methods such as net present value (NPV) and internal rate of return (IRR) analyses (Anda, Golub, & Strukova, 2009; Trigeorgis, 1996). Hence, the objective of this paper is to discern a methodology that is able to correctly value and decide about port capacity invest- ment decisions under uncertainty and construct a framework to further develop this meth- odology. We review the relevant literature and risk factors in the next section, since all of these elements need to be taken into account in port capacity investment decisions.
532 M. BALLIAUW ET AL.
As opposed to the NPV method, real options (RO) models offer a more appropriate method to value flexible investments under uncertainty and make better investment decisions, as is discussed in Section 3. To this end, RO models use stochastic calculus and dynamic programming to optimise an objective function (such as the value of the firm), including a random term with respect to the investment decision variables (Dixit & Pindyck, 1994). The disadvantages of the method are however its complexity, the need for data and parameter and function estimations. Its current applications to ports are limited. Some of the existing RO applications in a transportation context are discussed in Section 4. In order to allow building RO models to decide about port capacity invest- ment decisions, building blocks and characteristics of general existing RO models relevant to the port context are reviewed in Section 5. The insights from the reviews of both the port uncertainty and the RO modelling domain are combined in Section 6.1 in a port capacity investment RO modelling framework. This framework offers an overview that will support researchers and practitioners in model building, since insights in both the port context and RO models are indispensable for them. Section 6.2 uses the framework to elaborate a port capacity investment decision model under uncertainty. The final section concludes with the major findings of this review and presents some suggestions for future research.
2. Sources of uncertainty affecting port capacity investment decisions
Many sources of uncertainty are present in the port context. This section reviews the rel- evant port uncertainty-related literature in order to provide insights in the current state-of- the-art. Later on, these insights will be included in RO models.
The sources of uncertainty in a port can be classified under three categories: (i) the com- petitive position of a port in a global logistics chain, (ii) global evolutions in international trade and (iii) technological evolutions, increased environmental considerations and resulting changes in legislation. In order to link the sources of uncertainty to the actors in the entire logistics chain, Figure 1 represents the logistics chain. The different risks are grouped per activity in the logistics chain. Additionally, the actors per activity are dis- played on top, to allow linking the risks at the bottom to the respective actors. The inter- action of actors induces additional uncertainty and risks. Nonetheless, forwarders often intervene in this maritime logistics chain by coordinating different steps of the shipping process, resulting in the elimination of many direct contacts between shippers and different shipping lines (Meersman & Van de Voorde, 2014a). This might at times lead to a reduction of uncertainty. Finally, general and unforeseen uncertainties that can have an influence on investment projects, such as tsunamis, earthquakes or terrorist attacks, are not discussed in further detail in this paper.
2.1. Competitive position of the port: global logistics chains
Ports are part of global logistics chains with a number of actors involved. These chains are multimodal, as it is necessary to switch between different transport modes (e.g. road, rail and maritime transport). This induces internal variability and risks to the significant demand and external risk, that are already present in the economic environment (Vilko & Hallikas, 2012). Decisions of one actor in the chain can have major implications for the
TRANSPORT REVIEWS 533
other actors (Heaver, 2011; Slack & Frémont, 2005; Verhoeven, 2015). At first sight, they may seem insignificant but subsequently, they might cause a chain reaction creating bottle- necks that affect the competitive position of a port negatively (Panayides, 2006; Rodrigue & Notteboom, 2009; Van Der Horst & De Langen, 2008). Variability moreover complicates the decisions taken by the different owners in the chain (Cucchiella & Gastaldi, 2006). Finding out the most vulnerable links in the chain can help to efficiently manage these chains wherein goods are to be transported and the information is to be shared. In order to steer the chain, cooperation and communication are vital (Vilko & Hallikas, 2012).
In the port, many different intertwined actors come together and influence the decisions taken there (Coppens et al., 2007; Verhoeven, 2015). The relationships between these actors can be rather complex (Estache, 2001), as they might have different, conflicting objectives and an unequal distribution of power between them. This complicates specifying the objective functions of the port capacity investment decision makers (Xiao, Ng, Yang, & Fu, 2012). As Van de Voorde and Vanelslander (2009) state, for example, the concession policy is for the port authority one of the few instru- ments to express their negotiation power over TOC’s. The negotiated concession fee needs to be taken into account in the objective functions. Moreover, shipping companies have strong decision power in the maritime chain too, since they decide the ports of call for large throughput volumes. Their organisational structure is changing towards more concentration (Kauppila, Martinez, Merk, & Benezec, 2016). In addition, shipping lines may invest in dedicated terminals, in order to reduce waiting times by preventing being served on a first come, first served basis (Heaver, Meersman, & Van de Voorde, 2001). This reduction of port and hinterland congestion is an objective of both the ship- ping company and the TOC. As a result, the impact on port capacity needs to be con- sidered (Meersman et al., 2010; Strandenes, 2014).
The question could be raised whether port authorities aspire cost minimisation or profit maximisation, or even a different objective (Chang, Tongzon, Luo, & Lee, 2012). The
Figure 1. Actors and risks in the maritime logistics chain. Source: own composition, based on Meers- man and Van de Voorde (2014a), Meersman et al. (2010), Vanelslander (2014), Vilko and Hallikas (2012), Cucchiella and Gastaldi (2006), and Koetse and Rietveld (2012).
534 M. BALLIAUW ET AL.
objectives of a port authority are influenced and complicated by their mixed ownership structure and competition inside and between ports (Cullinane, Teng, & Wang, 2005). As Suykens and Van de Voorde (1998) indicate, not only private, but also public money plays an important role in port ownership. Xiao et al. (2012) define a multiple objective function to deal with the different actors in the port. Different weighted objectives are combined for the private and public actors involved. A private investor aims at maximising profit:
p = (p − c)q − chK, (1) with p the unit price, c the unit cost, q the output quantity, ch the capital holding cost of one unit of capacity (to hold capacity in place, e.g. through maintenance) and K the total available capacity, which forms the upper bound of q. A local government looks at the sum of this profit and the spill-over effects (lq, with l a constant scale factor) for the local economy. Finally, a central government additionally includes total consumer surplus in its value function. The objectives of the different actors are then weighted and summed in a global objective function which is to be maximised. Delay D, caused by congestion, is defined by a function of the capacity utilisation rate q/K: D = jf(q/K), with j a constant scale factor. It is included in the analysis as a user cost. Xiao et al. (2012) find that a higher share of ownership for the private investor results in lower capacity investments and higher prices. Indeed, when positive spill-over effects of port business are not taken into account, capacity investment will be lower (Asteris, Collins, & Jones, 2012).
The weights of the different objectives in this approach are defined by the share of ownership of the different parties in the port. This is a good first approximation when voting power is directly related to the shares of ownership of the different parties. In some ownership structures (e.g. a majority shareholder or public-private partnerships) or when dealing with dominating parties, however, this approach might not be a correct representation of the decision-making process. In such a case, only the objectives of the decision makers with influence need to be retained.
Also, competition has an impact on the chain (Notteboom & Yap, 2012). Competition does not only exist within one chain but also between different chains. At first, the different actors in the chain might compete internally to have the power to influence the decisions made in the chain (Meersman & Van de Voorde, 2014b). Second, different TOC’s and port authorities might compete to be part of a specific logistics chain. It is important to be part of the chain with the lowest generalised cost, because the goods are more likely to flow through this chain (Meersman & Van de Voorde, 2014a). This in turn leads to competition between different chains to actually have the lowest generalised cost and attract the highest possible throughput volumes. This competition induces extra uncertainty and risks in the port. To account for this competition between ports, many models use a competitive game with two or more ports (Saeed & Larsen, 2010; Xiao et al., 2012; Zhang, 2008; Zhuang, Luo, & Fu, 2014).
2.2. Global evolutions in international trade
The amount of throughput handled in a port depends on international trade in three ways. First, the total amount of trade plays an important role, and is influenced by the macro environment (see Figure 1). Future levels of world trade flows are very uncertain and
TRANSPORT REVIEWS 535
volatile, although they are expected to grow. Second, the geographical distribution of these trade flows can change, resulting in different routes for the ships. Finally, the com- position of trade and the selected transport modes can change too, influencing amongst others containerisation rates. This uncertainty in global trade has a negative impact on forecast accuracy. Accurate forecasts estimating future port demand are required to obtain valuable outcomes of NPV analyses, since they cannot accurately account for uncer- tainty (Blonigen & Wilson, 2008; Jacks & Pendakur, 2010; Kauppila et al., 2016; Meersman & Van de Voorde, 2014b). Oppositely, RO models valuing flexibility have the advantage of being able to explicitly account for the uncertainty (de Neufville, 2016).
2.3. Technological change: environmental and legal uncertainties
Technological and environmental developments are another prominent macro-environ- mental factor influencing the port. Asteris et al. (2012) describe ports as an industry facing numerous technological developments, internally as well as externally. Vessel size increases, new routes become available (e.g. through widening the Panama Canal, etc.) and the environmental impact of technology and the investment herein under uncer- tainty (e.g. LNG fuel) gain increasing attention (Acciaro, 2014a, 2014b; Kauppila et al., 2016; Verbruggen, 2008). Koetse and Rietveld (2012) prove that climate change can add to the risk encompassed in transport infrastructure investments. Next to transportation inducing climate change, there also exists an influence of climate change on transportation. More extreme weather conditions can pose a problem to different transportation modes, even more than a change in the average condition. An interesting example in this context is the change in the sea level, complicating certain port activities. This in turn could result in a modal shift, altering the demand for certain types of transport infrastructure and hence imposing a higher demand variability and risk.
Since technological and environmental impacts, but also safety and security gain more interest, new legislations are constituted to protect the goods traded, the workers and the port environment (Harrald, Stephens, & Rene vanDorp, 2004). Also, the environmental impact of ports on climate change can be addressed by governments imposing additional legislation. Furthermore, changes in labour regulations may induce additional risks (Barton & Turnbull, 2002).
3. Real options models to make better decisions under uncertainty
As opposed to the traditional valuation methods, RO models monetarily quantify the value of managerial flexibility to react to uncertainty in the best possible way. In this way, RO models do take the benefits of options of flexibility embedded in the project into account. Only when these options are included in project appraisal, the investment decision can be valued correctly. It is however important to point out that RO models should not be seen as a replacement for NPV with discounted cash flows. It is complemen- tary to it, because the value of a project can be calculated as the static NPV value plus the value of the real options present (Hu & Zhang, 2015; Van Putten & MacMillan, 2004).
Port capacity investment analysis is a field where RO can be a very powerful method- ology, as was already suggested by Juan, Olmos, Pérez, and Casasus (2001) and Herder, de Joode, Ligtvoet, Schenk, and Taneja (2011). RO show great potential to improve project
536 M. BALLIAUW ET AL.
valuation and decision making under uncertainty in large scale, complex, irreversible pro- jects involving long planning and construction periods and influenced by technological shifts and opposing objectives of different stakeholders involved (de Neufville, 2003). Port infrastructure investment projects have these characteristics (Vanelslander, 2014). Moreover, the port environment itself is complex, as shown by the review in Section 2. As a result, the value of these projects can be increased by means of flexible size and timing of the investments through flexible options embedded in the project elaboration (Hull, 2012). Ports that want to excel in a dynamic world need to incorporate options to allow reacting flexibly to changes. RO models attribute value to such flexibility (Taneja, 2013; Van Putten & MacMillan, 2004). Moreover, uncertainty is considered an opportunity, not a threat, because managers can adapt their strategies to internal and external changes. Literature even indicates that higher demand uncertainty results in larger capacity invest- ments (Dangl, 1999; Guthrie, 2012; Xiao et al., 2013).
An advantage of RO beyond its included flexibility and decision-making realism is the possibility of a stepwise elaboration of the mathematical model. Trigeorgis (2005) shows that RO can be approached as building blocks, where different options could be inter- related and interacting with each other. Some important options to be considered are the option to expand the project, possibly in stages; the option to defer (timing flexibility); the option to switch to other activities or good types handled; the option to adapt output levels; and the option to fully shut down operations. Such RO models are often expanded. In an initial stage, only one firm might be considered. In a following stage of the research, the model might be extended for example to more firms operating under competition (Aguerrevere, 2003; Xiao et al., 2013).
4. Real options in the transportation literature
Real options have been applied to many transportation investments, because they can deal very well with managerial flexibility under different sources of uncertainty. Those noted here relate to the maritime sector, to other modes and to environmental projects. When transportation infrastructure is financed by the public government, the social welfare function has to be maximised, complicating the analysis because now different variables have an impact on the value of the project (Szymanski, 1991). Chow and Regan (2010) exemplify this when applying RO to transportation network investments. Tibben-Lembke and Rogers (2006) in their paper show how financial options could be adopted as transportation options to hedge logistical contracts. Also in aviation, RO have been applied. Hu and Zhang (2015) for example have analysed airline investment decisions, whereas Xiao, Fu, Oum, and Yan (2017) and Xiao et al. (2013) have investigated airport expansion decisions under uncertainty. Interesting lessons with respect to the mar- itime and port context can be drawn from this field of study.
There have been many applications of RO to maritime investments. Bendall and Stent (2003, 2005, 2007) and Dikos (2008) show how investing in a new ship or maritime tech- nology can incorporate an option value. Bjerksund and Ekern (1995) discuss the value of mean-reverting cash flows through contingent claim analysis, applied to time charters in shipping. Sødal (2006) and Balliauw (2017) use RO to study entry and exit decisions in ship- ping markets. Rau and Spinler (2017), as an extension of Rau and Spinler (2016), discuss the performance of RO modelling in a cooperative container shipping game concerning
TRANSPORT REVIEWS 537
alliances. Moreover Sødal, Koekebakker, and Aadland (2008) use RO to value the option to switch operations in combination carriers. These examples confirm that RO models offer a good approach to valuing volatile and capital-intensive projects as in the maritime business (Kakimoto & Seneviratne, 2000a).
RO analysis has been used to evaluate alternative technologies dealing with environ- mental issues (Kim, Weiss, & Morel, 2009; Koetse & Rietveld, 2012). RO is well suited to dealing with the uncertainty associated with climate change and the effectiveness of tech- nological innovations (Acciaro, 2014a). RO demonstrates the option value in postponing the technological investments. However, adapting to climate change during regular main- tenance or retrofitting could be beneficial pro-active actions (Cullinane & Bergqvist, 2014).
5. Real options models to analyse port capacity investment decisions
This section’s review of RO models in the literature is the basis for developing models suit- able to the specific, complex port context with its considerable uncertainties. In order to model investment decisions as realistically as possible, without relying on too many sim- plifying assumptions, the relevant decision variables need to be included in the port model. Nevertheless, some variables need to be kept exogenous in order to have a solva- ble model with sufficient explanatory power. The included decision variables alter the out- comes of the model and the impact of uncertainty. For example, considering the timing and size of an investment together could be more realistic in some cases and would lead to results that differ from models with only one single decision variable.
5.1. The basic RO model of Dangl and its extensions
An initial RO model to decide about the size and timing of capacity investments is avail- able in Dangl (1999). His continuous time and continuous state model starts from the inverse demand curve
p(t) = X(t) − Bq(t), (2) with the following variables defined at time t: p(t) the price, X(t) the demand shift parameter that follows a Geometric Brownian Motion (GBM), B the inclination of the curve and q(t) the output quantity. The increment of a GBM is defined by
dX(t) = mX(t)dt + sX(t)dZ(t), (3) with μ the drift parameter, σ the volatility (a measurement of uncertainty) and Z a standard Wiener process. For convergence of the model, it is required that the risk-free discount rate r . m (Dixit & Pindyck, 1994). For the sake of clarity, we further on omit the time-depen- dency in our notation, e.g. p instead of p(t).
Dangl (1999) in his paper models a flexible firm, since the firm can choose its optimal output level, as long as it satisfies q = min {qopt,K}, as opposed to a non-flexible firm, with q [ {0,K}. Ports are typical examples of flexible firms, as operating at full capacity is in general an exception. According to Hagspiel, Huisman, and Kort (2016), a flexible firm will invest more than a non-flexible firm, proving that flexibility adds value to the firm.
538 M. BALLIAUW ET AL.
The cost of investment is given by
I = gK1, (4) with g a constant scale factor, K the total capacity and 1 , 1 to indicate economies of scale in investment outlays and to exclude infinitesimal expansion, which would have an infinite cost under the current specification. The profit p is equal to
p = (p − c(K))q, (5) where c(K) is the average operational cost, being dependent on the available capacity K. This function is a reduced version of the profit function used by Xiao et al. (2012) in Equation (1) for a port environment. The maximisation of this profit will lead to the optimal output qopt at each point in time, given X and K. Subsequently, Dangl (1999) maximises the value of the firm, given by the integral of the discounted expected future profit streams minus the investment cost. This forms the input of the option value maximisation. By using dynamic programming, an optimal invest- ment strategy (XT ,K) is found. It indicates the optimal timing, based on an investment threshold for the demand shift parameter, and the optimal amount of capacity. The main conclusion of the model is that an increase in uncertainty will lead to investing more, but later.
Bar-Ilan and Strange (1999) analyse the difference between lumpy and incremental investments. They confirm the findings of Dangl (1999), but only for lumpy investments, namely that uncertainty delays the investment and increases its size. Lumpy investments are defined by two properties: combinable investments and the presence of adjustment costs. Investments in port capacity are combinable, since adding a dock increases capacity. Moreover, there are adjustment costs in public infrastructure, such as planning costs (Szy- manski, 1991). It is exactly those costs that lead to the presence of economies of scale in the size of the investment. So indeed, investing in port capacity is considered lumpy, as adding a dock means increasing capacity by a big leap.
An extension to the model of Dangl (1999) is provided by Hagspiel et al. (2016), who adds a capital holding cost chK to the cost function of Dangl (1999). The resulting profit function is similar to the one of Xiao et al. (2012) in Equation (1). However, the typical port congestion and delays are still omitted. The new profit function is given by
p = (p − c(K))q − chK. (6)
5.2. Inclusion of port expansion in the model
A slightly different continuous time and state model to analyse the impact of economies of scale on the investment decision is presented by Guthrie (2012). It takes into account a firm that can undertake subsequent capacity expansion investments. For a port, this could be by means of adding a dock. The inverse demand curve used in this model is not linear, but has a constant price elasticity of demand (−1/a). It is given by
p(t) = X(t)q−a, (7) with X(t) again following a GBM, that could be adapted for risk-aversion by subtracting a risk premium.
TRANSPORT REVIEWS 539
The investment cost function I is given by
I = Dq1, (8) with 1 , 1, leading to economies of scale and preventing infinitesimal capital expansions. This investment cost function is similar to the one of Dangl (1999), although Guthrie (2012) sets g to 1 and uses for K the amount of capacity expansion Dq, hence being the difference between the new and previously installed capacity. Output in this case is always set at maximum capacity, because a<1 makes this the optimal decision in every circumstance. This is equivalent to the non-flexible firm of Hagspiel et al. (2016). Another element that is included in the model, is depreciation: dq = −zqdt, with z the depreciation rate. The objective function is the market value of the firm and is to be maximised.
The outcome of maximising the firm’s market value is a set of three decisions (ŷ0, k, ŷb). ŷ0 defines the initial capacity investment. k and ŷb define the subsequent capacity expan- sion strategy. k is the scale of each expansion (related to the current capacity level) and ŷb is the return on assets-threshold indicating the investment timing. It is calculated as pq/q1 = q1−a−1X, where q1 is the replacement cost of the assets in place. It is noteworthy to indicate that investing will decrease the actual value for ŷb through an increase of q.
The main conclusion of Guthrie (2012) is in line with the findings of Dangl (1999). Guthrie (2012) confirms that increased uncertainty will lead to larger investment outlays that are in turn less frequent.
5.3. The impact of time to build
As opposed to the previous model, Aguerrevere (2003) includes time to build in his RO model of capacity expansions. He uses the same demand curve as Dangl (1999). Aguerre- vere (2003) uses the demand function to explicitly study the resulting pricing decision for a chosen output level of a non-storable product. However, his cost function is different: c(q) = c1q + 12 c2q2, with q being flexible, but limited by the operational capacity available. As a result of flexible output, this model considers overinvestment in capacity less harmful than underinvestment. Indeed, there is an imbalance between the two sides of risk, as the capacity investment decision in combination with flexibility has to be considered rather as a determination of the maximal output threshold.
The investment cost in this model is given by Equation (4), with ɛ set to 1. This however excludes economies of scale in the investment size decision, leaving infinitesimal invest- ments possible under this cost function specification (Dangl, 1999). However, such invest- ments are not realistic in port capacity expansion, as they are characterised as large-scaled. A fixed investment cost should still be included in the function, as a preliminary study and a negotiation process with different parties involve a cost as well.
Time to build is modelled through three functions: O(t) represents the amount of capacity present at time t, N(t) is the amount of capacity that is under construction with lead time θ and K(t), the committed capacity, is the sum of the previous two. K(t) is non-decreasing over time, because of investment irreversibility and the omission of depre- ciation in the model.
An important insight of Aguerrevere (2003) is that capacity investments increase with uncertainty when time to build is included in the model. The same logic applies when the time lag increases. The results explain why expansion takes place even when the current
540 M. BALLIAUW ET AL.
capacity is not fully used. It also turns out that when capacity is fully used, the pricing behaviour as a result of increased demand will be entirely different. The price will rise much more following a demand increase than in the case when capacity is not fully used. As a result, a model like that of Aguerrevere (2003) could be used to quantify con- gestion pricing, which could be an important contribution to understanding the complex pricing strategy of a port.
5.4. Installing the project in stages
Building a new dock can be realised in different steps and should not necessarily be com- pleted at once. A well-known example is Maasvlakte 2 in Rotterdam, where the water basin and part of the terminals were realised in the first stage. In the second stage, the rest of the terminals can be build, but only when the additional capacity is required. Also, the port of Antwerp is considering expansion. Therefore, it considers digging a first phase of the Saef- tinghedock and develop the terminals around it (Timperman, 2017). When additional capacity is needed, the second phase can be installed, by further expanding this dock and its terminals.
An important advantage of the phased investment approach can be a shorter lead time to add extra capacity, because part of the project has already been realised. The downside of such a project however is that in general, a premium has to be paid in terms of a higher total investment cost. Stage 1 has an investment cost Is1, whereas Stage 2 involves Is2 and realising the project at once costs Il. Hence in reality, Is1 + Is2 . Il will hold.
A model that confronts lumpy and stepwise investment is provided by Chronopoulos, Hagspiel, and Fleten (2017). They confirm the findings of Kort, Murto, and Pawlina (2010) who work with exogenous capacities and who calculate a maximum cost premium (Is1 + Is2)/Il . 1 for which phased investment is more profitable. Chronopoulos et al. (2017) state that if the capacity of the project is determined ex-ante, lumpy investment is better under a high price uncertainty. If the final capacity is not fixed, stepwise invest- ment leads to a higher value and more capacity will be installed.
5.5. Game-theoretic approaches
Most of the previous models only consider the investment decision of one monopoly entity. In reality however, there is competition between ports and even within ports to attract cargo flows (Meersman et al., 2010). The preference of shipping goods to Western-Europe for instance through the port of Rotterdam or the port of Antwerp will be determined by the cost and the service provided by the port (i.e. transit time, the fre- quency of service for container lines, the amount of congestion, etc.), but also by switching costs (determined by existing contracts, the presence of liner-owned terminals and the speed of new information availability) (Veldman & Bückmann, 2003). The ports in the Hamburg-Le Havre range should hence not be considered monopoly ports. They are in competition for the same market or hinterland, like for example in De Borger et al. (2008). In this regard, Pallis, Notteboom, and De Langen (2008) and Saeed and Larsen (2010) look at port negotiations as a game. Because entities in the public sector can also be included in the analysis, sufficient transparency can be assumed. As a result, infor- mation asymmetry should not necessarily be included in the game.
TRANSPORT REVIEWS 541
When a game-theoretic approach is chosen, individual value functions have to be derived and the type of game has to be decided on. Dynamic programming can then be used to find the optimal decision (Azevedo & Paxson, 2014; Dixit & Pindyck, 1994; Huberts et al., 2015). Huisman and Kort (2015) discuss a model that analyses the initial investment decision of a leader and a follower firm. In a duopoly setting, they use a multi- plicative inverse demand function given by
p = X(1 − BQ), (9)
where X follows again a GBM and Q represents the total market output. This function is a special case of the one introduced by Dixit and Pindyck (1994). The authors find that in this case, overinvestment of the leader forces the follower to invest later and in less capacity. However, this model is not directly applicable to a competitive port setting. An important implication of this model is that the maximal output is limited to 1/B in order to prevent negative prices. This demand function could serve as a good first approximation. A linear demand function would however be better suited to analyse a market wherein potential demand growth is possible. Nevertheless, more sophisticated functions and their applica- bility should also be considered when developing port investment models.
Another important limitation of the model of Huisman and Kort (2015) lies in the number of competitors involved. As shown by Veldman and Bückmann (2003), in the Hamburg-Le Havre range, five ports are in competition. For this reason, modelling the port as an oligopoly, rather than as a duopoly could be a better alternative. Some examples are given by Azevedo and Paxson (2014). Aguerrevere (2009) finds in his model with an exogenously determined number of firms in the industry that with more companies in the market, the option to expand is exercised earlier. In order to analyse an n-firm game, Grenadier (2002) uses a constant elasticity demand function, equivalent to the one used by Guthrie (2012) in Equation (7). It is shown that the value of waiting is negatively correlated to the amount of competition, as a result of preemptive strategies. As stated before, competition between ports is not the only competitive element in the analysis of port capacity investments. Potentially conflicting interests in combination with a number of aligned objectives of the actors involved in the maritime logistics chain require a much more complex analysis in a new port investment model too.
Since ports are heterogeneous, this should be translated into asymmetric firms in an RO game model. Firms or ports could differ in terms of investment costs, revenues or pro- duction costs (Azevedo & Paxson, 2014). In addition, ports offer products or services that are not identical (e.g., different service levels or hinterland distances). Kamoto and Okawa (2014) present an RO model that allows for product differentiation, more specifi- cally in an innovative environment with a leader and follower entrant. Their inverse demand function of firm i is an extended version of the one used by Huisman and Kort (2015), since it involves a correction for the output of the other firm j, weighted by the amount of product similarity. The inverse demand function is given by
pi = X(1 − qi − dqj), (10)
with d [ [0,1] the differentiation parameter, taking the value of 1 in the case of perfect substitution and 0 in the case of perfect complementarity. By assuming a variable pro- duction cost of zero, the model of Kamoto and Okawa (2014) does not include scale
542 M. BALLIAUW ET AL.
effects, which however do play an important role in infrastructure and cargo handling in ports (Tovar & Trujillo, 2007).
5.6. Alternative uncertainty processes: cyclicality and changes in legislation
RO models frequently use a GBM as the stochastic process expressing uncertainty, also in transportation (Li & Cai, 2017; Lindsey & De Palma, 2014). This non-negative process allows uncertainty and drift to be set by two independent parameters, and its mathematical com- plexity is relatively limited (Schöne, 2014). However, as Dixit and Pindyck (1994) also indi- cate, alternatives exist to model different market patterns. Maritime markets typically follow a cyclical pattern, with cycles lasting about eight to ten quarters (Paflioti, Roumpis, Vitsounis, Tsamourgelis, & Bell, 2015; Stopford, 2009).
Ruiz-Aliseda and Wu (2012) built an RO model analysing the entry and exit decisions in such cyclical markets. Balliauw (2017) applied this model to study entry and exit decisions in shipping markets. To model cyclical markets, the traditionally used GBM is replaced by a discrete-time Markov process, defined by
dp = a(t)pdt, (11) with p the instantaneous profit at time t, and α the growth (a1) or decline (a2) rate. The probabilities of going from a growth phase to a decline phase and vice versa are given by
P(a(t + dt) = a2|a(t) = a1) = c1dt + o(dt), P(a(t + dt) = a1|a(t) = a2) = c2dt + o(dt).
{ (12).
Whereas a GBM is used to model a process showing a positive, negative or zero trend with some random variations, the Markov process can model different states in one model (e.g. growth and recession phases). Because of this, it is expected that capacity investments will be lower under this approach, since overcapacity in times of recession has a high cost.
Alternatively, Poisson or Jump processes are often used in models in order to represent the possibility of sudden changes, for example following a newly available technology in R&D or new legislation (Dixit & Pindyck, 1994; Weeds, 2002). In this case, the sudden change, called the event, results in a jump. Such a stochastic process is written as a Poisson differential equation:
dx = f(x,t)dt + g(x,t)dJ, (13) with fdt the non random evolution over time, g also a known function and dJ the incre- ment of the Poisson process:
dJ = 0, probability 1 − ndt, u, probability ndt.
{ (14)
Here, u is the size of the jump caused by the event and ν the main arrival rate of the event.
6. Towards a real options application in ports
Elements of RO models that could be adapted for use in a port environment have been linked to each other and to the port environment. The objective hereof is to enhance
TRANSPORT REVIEWS 543
port capacity investment decisions through our framework offering guidelines to build new RO models. This framework is applied in Section 6.2.
6.1. A framework to enhance port capacity investment decisions
The framework in Figure 2 combines the insights from the port uncertainty and RO models reviews. This framework visualises the different choices of components to be made when building a new model to decide on port capacity investments. First of all, decisions are to be made about the demand function for the output (i.c. port throughput). The mathemat- ical specification of the function and the way of including uncertainty in this function need to be considered. Possible alternatives include a GBM, a Markov process, a Poisson process, a binomial process (Smit, 2003), a uniform distribution (Xiao et al., 2013), a mean-reverting process (Dixit & Pindyck, 1994) or a vector autoregressive (VAR) process (Huisman, Kort, & Plasmans, 2007). Additionally, the inverse demand function should also account for the cost of congestion (Xiao et al., 2012). When more than one port needs to be considered, the inverse demand function should reflect competition between ports, with or without differentiated products.
A cost function for producing the output has to be selected as well. This function could be linear, quadratic or even of a higher degree in q. Besides a capacity-dependent variable cost, a capital holding cost could be added to the function. When a capital holding cost is included, investments to maintain the level of capacity are already accounted for. In that case, depreciation should not be included in the model. Next to the profit, also other benefits matter and could be included in the analysis. Different objectives can be com- bined by means of a weighted sum of these objectives. The sum of discounted profits and other benefits in each period of time minus the cost of investment together determine the value of the project. Other than the investment cost function of Dangl (1999), also a polynomial specification could be used, for example, a higher order term to account for
Figure 2. Comprehensive framework of RO models and its components. Source: own composition, based on Huberts et al. (2015), Xiao et al. (2012), Dangl (1999), Hagspiel et al. (2016), Guthrie (2012), Aguerrevere (2003), Ruiz-Aliseda and Wu (2012), Weeds (2002), and Chronopoulos et al. (2017).
544 M. BALLIAUW ET AL.
a limit to the project size. The value of the port authority’s project is the objective that needs to be maximised. A slightly different approach is maximising the market value of the port authority, as a function of the return on assets (Guthrie, 2012).
Other components that could be included are time to build, depreciation (when there is no capacity holding cost) and output flexibility. Finally, single-firm models can be expanded to game-theoretic models with more than one firm. The most appropriate spe- cification will depend on a number of factors, such as the port characteristics, uncertainties and the research objectives. The presented framework should support the selection of the best building blocks when developing new port capacity investment models (Trigeorgis, 2005). The framework will also help better understanding, categorising and comparing existing RO models.
6.2. Applying the framework
In order to illustrate a potential application of our framework, we analyse the investment decision of a port in new capacity. We start from a port that wants to maximise the reven- ues consisting of the sum of port dues and terminal handling prices. In such a port, the value of the firm comprises the combined objectives of the port authority and operators of the port (Meersman, Strandenes, & Van de Voorde, 2015; Strandenes & Marlow, 2000). Those two parties may coincide in one enterprise, like in the private port of Felixstowe, owned by the port operator Hutchison Port Holdings (World Bank & PPIAF, 2007). This single entity wants to maximise the stream of discounted profits minus the investment cost with respect to the investment timing (T ) and the capacity (K). The stream of profits is composed by the revenue (pq) minus the operational cost (a linear function in this initial setting) and the capital holding cost (see Figure 2). In the profit function, the concession payments are cancelled out, because this is an internal transfer from the TOC to the port authority and should not be considered here. This results in the following system of equations, which can be optimised through dynamic programming (Dixit & Pindyck, 1994):
max T,K
E ∫+1 0
e−r(T+t)p(T + t)dt − e−rTI(K) { }
,
p(t) = (p(t) − c)q(t) − chK, p(t) = p(X(t)
+ , q(t)
− , D(t)
− ),
dX(t) = mX(t)dt + sX(t)dZ(t), D(t) = D(q(t)
+ /K
) ,
0 ≤ q(t) ≤ K, I(K) = gK1.
⎧⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎨ ⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎪⎩
(15)
System (15) indicates that the price p from the inverse demand function is negatively related to the throughput quantity q and delay D and that it is positively related to a random shift parameter X. This parameter follows a GBM. Because congestion can result in a loss of potential demand (Jansson & Shneerson, 1982), the demand and congestion level are endogenised in our model. When congestion and delay increase, the
TRANSPORT REVIEWS 545
customers’ willingness to pay decreases, because they will incur the additional costs caused by congestion and delays. A possible shape of the positive relationship between the amount of waiting time delays D and the occupancy or utilisation rate q/K is visualised in Figure 3. D1 and D2 are two constants that are to be estimated empirically, using insights from queuing theory (Novaes, Scholz-Reiter, Silva, & Rosa, 2012). Additionally, the output is limited by capacity. Producing no output (q = 0) is also possible. The cost of investment I is initially based on the specification of Dangl (1999). When capacity expansions are studied, K has to be replaced by DK in the invest- ment cost function.
In infrastructure investment projects, demand and revenues are often overestimated, whereas costs are frequently underestimated. The latter could reduce the value of a project significantly. For this reason, we would like to suggest the inclusion of uncer- tainty both on the demand and cost side of the model (Van Putten & MacMillan, 2004). The latter could result in the inclusion of an additional state variable, with its own uncertainty. This would, however, complicate the analysis considerably, because the interaction between both distributions has to be included. This will in turn reduce the tractability of the model (Huisman et al., 2007). As a result, Monte-Carlo simulations might be needed.
The presented model from System (15) can be used to calculate an optimal investment threshold for X (expected to be reached at time T ), the amount of capacity K, the optimal throughput quantity q and price p for a port. When building new RO models, however, one always has to keep in mind the solution technique as well. A frequently used technique to solve RO models is dynamic programming. This technique is explained by Dixit and Pindyck (1994). However, often no analytical expression can be derived for the optimal
Figure 3. Positive relationship between delay and occupancy rate.
546 M. BALLIAUW ET AL.
values of some decision variables. Nevertheless, numerical solutions can be calculated and allow drawing conclusions on the dynamics of the model (Aguerrevere, 2003; Guthrie, 2012). In some cases, the optimum might also be approached by a good heuristic algor- ithm, but it does not guarantee reaching the actual global optimum. Azevedo and Paxson (2014) provide such an example in RO games. Cucchiella and Gastaldi (2006) also use a software package to solve their RO model. Furthermore, the RO analysis might be sim- plified by a binomial tree approach (Hu & Zhang, 2015) or a Monte-Carlo simulation to esti- mate some parameters involving processes characterised by uncertainty (Anda et al., 2009). Even spreadsheet approaches are available (de Neufville, 2006). This shows that the trade-off between the complexity and realism of the model on the one hand and the feasibility of the solution technique on the other hand, should be well considered when building RO models.
7. Conclusions
It is very important for a port to install the right amount of capacity, since undercapacity leads to congestion and waiting costs for the port users, while persistent overcapacity means that unnecessary investments and capital costs are incurred not only by the port authorities and private investors, but often also by the society. However, it is not easy to determine the optimal size of investments in port capacity, because a great deal of uncertainty has to be taken into account, especially because it often concerns large- scale, irreversible investment projects.
As ports are nodes in often long and complex logistics chains, they are subject to a wide range of uncertainties. It is necessary to account for the complex relationships between the maritime logistics chain actors, as well as uncertainty resulting from changes in global trade, technology, environmental factors, and the legal framework. Applying the traditional NPV in such a complex situation will in general lead to the wrong investment decision. In this case, RO models are a better alternative, since they specifically take into account the value of managerial flexibility under uncertainty. However, introducing all the different sources of uncertainty ports are facing in an RO model is not straightforward.
Starting from a review of these uncertainties and of the available RO models, we set up a framework which will help to categorise and apply RO models for port capacity invest- ments, taking into account the complex environment ports are operating in. Future RO models should include the relevant characteristics of the port or ports studied. This could, for instance, be achieved by selecting the most suited components from the pre- sented framework. The port RO models can be expanded even further, with major or minor additions, in order to include more and more of the complex relationships between the actors in the maritime logistics chain. This, however, requires an increasing number of assumptions about the specification of the underlying stochastic processes and their interactions; and the estimates of their variances. Moreover, RO models are only applicable in a limited range of parameter settings, because of convergence con- ditions. Due to the complex mathematics of RO, the main challenge will remain to find the right balance between on the one hand having an acceptable and reliable represen- tation of the port environment and on the other hand ending up with a tractable RO- based model.
TRANSPORT REVIEWS 547
Acknowledgments
The authors would like to thank Trevor Heaver, Siri Pettersen Strandenes, Peter Kort, Anming Zhang, Michele Acciaro and the participants of various conferences for their valuable comments to previous versions of this paper. All remaining errors are ours.
Disclosure statement
No potential conflict of interest was reported by the authors.
Funding
This work was supported by the Research Foundation Flanders (FWO) under a PhD grant.
ORCID
Matteo Balliauw http://orcid.org/0000-0003-1008-8109 Hilde Meersman http://orcid.org/0000-0002-1806-8965 Eddy Van de Voorde http://orcid.org/0000-0002-1868-2332 Thierry Vanelslander http://orcid.org/0000-0001-5213-3444
References
Acciaro, M. (2014a). Real option analysis for environmental compliance: LNG and emission control areas. Transportation Research Part D: Transport and Environment, 28, 41–50.
Acciaro, M. (2014b). A real option application to investment in low-sulphur maritime transport. International Journal of Shipping and Transport Logistics, 6(2), 189–212.
Aguerrevere, F. L. (2003). Equilibrium investment strategies and output price behavior: A real-options approach. The Review of Financial Studies, 16(4), 1239–1272.
Aguerrevere, F. L. (2009). Real options, product market competition, and asset returns. The Journal of Finance, 64(2), 957–983.
Anda, J., Golub, A., & Strukova, E. (2009). Economics of climate change under uncertainty: Benefits of flexibility. Energy Policy, 37(4), 1345–1355.
Asteris, M., Collins, A., & Jones, D. F. (2012). Container port infrastructure in north-west Europe: Policy- level modeling. Journal of Policy Modeling, 34(2), 312–324.
Azevedo, A., & Paxson, D. (2014). Developing real option game models. European Journal of Operational Research, 237(3), 909–920.
Balliauw, M. (2017). An analysis of entry and exit decisions in shipping markets under uncertainty. International Journal of Shipping and Transport Logistics, 9(5), 527–539.
Bar-Ilan, A., & Strange, W. C. (1999). The timing and intensity of investment. Journal of Macroeconomics, 21(1), 57–77.
Barton, H., & Turnbull, P. (2002). Labour regulation and competitive performance in the port transport industry: The changing fortunes of three major European seaports. European Journal of Industrial Relations, 8(2), 133–156.
Bendall, H. B., & Stent, A. F. (2003). Investment strategies in market uncertainty. Maritime Policy & Management, 30(4), 293–303.
Bendall, H. B., & Stent, A. F. (2005). Ship investment under uncertainty: Valuing a real option on the maximum of several strategies. Maritime Economics and Logistics, 7(1), 19–35.
Bendall, H. B., & Stent, A. F. (2007). Maritime investment strategies with a portfolio of real options. Maritime Policy and Management, 34(5), 441–452.
548 M. BALLIAUW ET AL.
Bjerksund, P., & Ekern, S. (1995). Contingent claims evaluation of mean-reverting cash flows in ship- ping. In L. Trigeorgis (Ed.), Real options in capital investment: Models, strategies, and applications (pp. 207–219). Westport, CT: Preager.
Blauwens, G., De Baere, P., & Van de Voorde, E. (2016). Transport economics (6th ed.). Antwerp: De Boeck.
Blonigen, B. A., & Wilson, W. W. (2008). Port efficiency and trade flows. Review of International Economics, 16(1), 21–36.
Chang, Y. T., Tongzon, J., Luo, M., & Lee, P. T. W. (2012). Estimation of optimal handling capacity of a container port: An economic approach. Transport Reviews, 32(2), 241–258.
Chow, J. Y. J., & Regan, A. C. (2010). Real option pricing of network design investments. Transportation Science, 45(1), 50–63.
Chronopoulos, M., Hagspiel, V., & Fleten, S. E. (2017). Stepwise investment and capacity sizing under uncertainty. OR spectrum, 39(2), 447–472.
Coppens, F., Lagneaux, F., Meersman, H. M., Sellekaerts, N., Van de Voorde, E., van Gastel, G., & Verhetsel, A. (2007, February). Economic impact of port activity: A disaggregate analysis – the case of Antwerp (Working paper document No. 110). National Bank of Belgium.
Cucchiella, F., & Gastaldi, M. (2006). Risk management in supply chain: A real option approach. Journal of Manufacturing Technology Management, 17(6), 700–720.
Cullinane, K., & Bergqvist, R. (2014). Emission control areas and their impact on maritime transport. Transportation Research Part D: Transport and Environment, 28, 1–5.
Cullinane, K., Teng, Y., & Wang, T. F. (2005). Port competition between Shanghai and Ningbo. Maritime Policy and Management, 32(4), 331–346.
Dangl, T. (1999). Investment and capacity choice under uncertain demand. European Journal of Operational Research, 117(3), 415–428.
De Borger, B., Proost, S., & Dender, K. V. (2008). Private port pricing and public investment in port and hinterland capacity. Journal of Transport Economics and Policy, 42(3), 527–561.
De Langen, P., Turró, M., Fontanet, M., & Caballé, J. (2018). The infrastructure investment needs and financing challenge of European ports (Report). European Seaports Organisation (ESPO). Retrieved from https://www.espo.be/media/Port%20Investment%20Study%202018_FINAL_1.pdf
de Neufville, R. (2003). Real options: Dealing with uncertainty in systems planning and design. Integrated Assessment, 4(1), 26–34.
de Neufville, R. (2006). Real options by spreadsheet: Parking garage case example. Journal of Infrastructure Systems, 12(2), 107–111.
de Neufville, R. (2016). Airport systems planning and design. In L. Budd & S. Ison (Eds.), Air transport management: An international perspective (pp. 61–78). Abingdon: Routledge.
de Weille, J., & Ray, A. (1974, September). The optimum port capacity. Journal of Transport Economics and Policy, 8(3), 244–259.
Dikos, G. (2008). Real options econometrics for aggregate tanker investment decisions. International Journal of Ocean Systems Management, 1(1), 31–44.
Dixit, A. K., & Pindyck, R. S. (1994). Investment under uncertainty. Princeton, NJ: Princeton University Press.
Estache, A. (2001). Privatization and regulation of transport infrastructure in the 1990s. The World Bank Research Observer, 16(1), 85–107.
Giuliano, G. (2007). The changing landscape of transportation decision making. Transportation Research Record: Journal of the Transportation Research Board, 2036(1), 5–12.
Grenadier, S. R. (2002). Option exercise games: An application to the equilibrium investment strat- egies of firms. Review of Financial Studies, 15(3), 691–721.
Guthrie, G. (2012). Uncertainty and the trade-off between scale and flexibility in investment. Journal of Economic Dynamics and Control, 36(11), 1718–1728.
Hagspiel, V., Huisman, K. J., & Kort, P. M. (2016). Volume flexibility and capacity investment under demand uncertainty. International Journal of Production Economics, 178, 95–108.
Harrald, J. R., Stephens, H. W., & Rene vanDorp, J. (2004). A framework for sustainable port security. Journal of Homeland Security and Emergency Management, 1(2), Article 12.
TRANSPORT REVIEWS 549
Heaver, T. (2011). Co-ordination in multi-actor logistics operations: Challenges at the port interface. In P. Hall, R. J. McCalla, C. Comtoisand & B. Slack (Eds.), Integrating seaports and trade corridors (pp. 155–170). London: Ashgate Publishing.
Heaver, T., Meersman, H., & Van de Voorde, E. (2001). Co-operation and competition in inter- national container transport: Strategies for ports. Maritime Policy and Management, 28(3), 293–305.
Herder, P. M., de Joode, J., Ligtvoet, A., Schenk, S., & Taneja, P. (2011). Buying real options – valuing uncertainty in infrastructure planning. Futures, 43(9), 961–969.
Hu, Q., & Zhang, A. (2015). Real option analysis of aircraft acquisition: A case study. Journal of Air Transport Management, 46, 19–29.
Huberts, N. F., Huisman, K. J., Kort, P. M., & Lavrutich, M. N. (2015). Capacity choice in (strategic) real options models: A survey. Dynamic Games and Applications, 5(4), 424–439.
Huisman, K. J. M., & Kort, P. M. (2015). Strategic capacity investment under uncertainty. The RAND Journal of Economics, 46(2), 376–408.
Huisman, K. J. M., Kort, P. M., & Plasmans, J. (2007). Investment in high-tech industries: An example from the LCD industry (SSRN Scholarly Paper No. ID 1026609). Rochester, NY: Social Science Research Network. Retrieved from http://papers.ssrn.com/abstract=1026609
Hull, J. (2012). Options, futures, and other derivatives (8th ed.). Boston, MA: Prentice Hall. Jacks, D. S., & Pendakur, K. (2010). Global trade and the maritime transport revolution. The Review of
Economics and Statistics, 92(4), 745–755. Jansson, J. O., & Shneerson, D. (1982). Port economics. Cambridge, MA: MIT Press. Juan, C., Olmos, F., Pérez, J. C., & Casasus, T. (2001). Optimal investment management of harbour
infrastructures. A real option viewpoint. 6th International conference on real options. Retrieved from http://realoptionorg.powweb.com/papers2002/juan_realoptions.pdf
Kakimoto, R., & Seneviratne, P. N. (2000a). Financial oment. Journal of Waterway, Port, Coastal, and Ocean Engineering, 126(6), 281–287.
Kakimoto, R., & Seneviratne, P. N. (2000b). Investment risk analysis in port infrastructure appraisal. Journal of infrastructure systems, 6(4), 123–129.
Kamoto, S., & Okawa, M. (2014). Market entry, capacity choice, and product differentiation in duopo- listic competition under uncertainty. Managerial and Decision Economics, 35(8), 503–522.
Kauppila, J., Martinez, L., Merk, O., & Benezec, V. (2016). Capacity to grow: Transport infrastructure needs for future trade growth (Report). International Transport Forum (ITF). Retrieved from https://www.itf-oecd.org/sites/default/files/docs/future-growth-transport-infrastructure.pdf
Kim, H. J., Weiss, M. B., & Morel, B. (2009). Real options and technology management: Assessing tech- nology migration options in wireless industry. Telematics and Informatics, 26(2), 180–192.
Koetse, M. J., & Rietveld, P. (2012). Adaptation to climate change in the transport sector. Transport Reviews, 32(3), 267–286.
Kort, P. M., Murto, P., & Pawlina, G. (2010). Uncertainty and stepwise investment. European Journal of Operational Research, 202(1), 196–203.
Li, S., & Cai, H. (2017). Government incentive impacts on private investment behaviors under demand uncertainty. Transportation Research Part E: Logistics and Transportation Review, 101, 115–129.
Lindsey, R., & De Palma, A. (2014). Cost recovery from congestion tolls with long-run uncertainty. Economics of Transportation, 3(2), 119–132.
Macário, R. (2014). Port capacity benchmarking: Leading or lagging? In T. Vanelslander & C. Sys (Eds.), Port business. Market challenges and management actions (pp. 61–78). Antwerp: University Press Antwerp.
Meersman, H. (2005). Port investments in an uncertain environment. Research in Transportation Economics, 13, 279–298.
Meersman, H., Strandenes, S. P., & Van de Voorde, E. (2015). Port pricing. In C. Nash (Ed.), Handbook of research methods and applications in transport economics and policy (pp. 329–342). Cheltenham: Edward Elgar Publishing.
Meersman, H., & Van de Voorde, E. (2014a). Port capacity extension – a trade-off between public investment and ship owner time losses. In R. Funck & W. Rothengatter (Eds.), Man, environment, space and time – economic interactions in four dimensions (pp. 377–394). Baden-Baden: Nomos.
550 M. BALLIAUW ET AL.
Meersman, H., & Van de Voorde, E. (2014b). Predicting the future: How to estimate future demand for port throughput and infrastructure use. In H. Meersman, E. Van de Voordeand & T. Vanelslander (Eds.), Port infrastructure finance (pp. 33–54). New York: Informa Law from Routledge.
Meersman, H., Van de Voorde, E., & Vanelslander, T. (2010). Port competition revisited. Review of Business and Economic Literature, 55(2), 210–233.
Musso, E., Ferrari, C., & Benacchio, M. (2006). Port investment: Profitability, economic impact and financing. Research in Transportation Economics, 16, 171–218.
Notteboom, T., & Yap, W. Y. (2012). Port competition and competitiveness. In W. K. Talley (Ed.), The Blackwell Companion to Maritime Economics (pp. 549–570). Informa Law from Routledge.
Novaes, A. G., Scholz-Reiter, B., Silva, V. M. D., & Rosa, H. (2012). Long-term planning of a container terminal under demand uncertainty and economies of scale. Pesquisa Operacional, 32(1), 55–86.
Paflioti, P., Roumpis, E., Vitsounis, T., Tsamourgelis, I., & Bell, M. (2015). Characterizing the cycle in sea- ports: An Australian case study. Proceedings of the IAME conference, August 2015, Kuala Lumpur, Malaysia.
Pallis, A. A., Notteboom, T. E., & De Langen, P. W. (2008). Concession agreements and market entry in the container terminal industry. Maritime Economics and Logistics, 10(3), 209–228.
Panayides, P. M. (2006). Maritime logistics and global supply chains: Towards a research agenda. Maritime Economics and Logistics, 8(1), 3–18.
Rau, P., & Spinler, S. (2016). Investment into container shipping capacity: A real options approach in oligopolistic competition. Transportation Research Part E: Logistics and Transportation Review, 93, 130–147.
Rau, P., & Spinler, S. (2017). Alliance formation in a cooperative container shipping game: Performance of a real options investment approach. Transportation Research Part E: Logistics and Transportation Review, 101, 155–175.
Rodrigue, J. P., & Notteboom, T. (2009). The terminalization of supply chains: Reassessing the role of terminals in port/hinterland logistical relationships. Maritime Policy and Management, 36(2), 165–183.
Ruiz-Aliseda, F., & Wu, J. (2012). Irreversible investment in stochastically cyclical markets. Journal of Economics and Management Strategy, 21(3), 801–847.
Saeed, N., & Larsen, O. I. (2010). Container terminal concessions: A game theory application to the case of the ports of Pakistan. Maritime Economics and Logistics, 12(3), 237–262.
Schöne, M. (2014). Real options valuation: The importance of stochastic process choice in commodity price modelling. Wiesbaden: Springer Gabler.
Slack, B., & Frémont, A. (2005). Transformation of port terminal operations: From the local to the global. Transport Reviews, 25(1), 117–130.
Smit, H. (2003). Infrastructure investment as a real options game: The case of European airport expan- sion. Financial Management, 32(4), 27–57.
Sødal, S. (2006). Entry and exit decisions based on a discount factor approach. Journal of Economic Dynamics and Control, 30(11), 1963–1986.
Sødal, S., Koekebakker, S., & Aadland, R. (2008). Market switching in shipping – A real option model applied to the valuation of combination carriers. Review of Financial Economics, 17(3), 183–203.
Stopford, M. (2009). Maritime economics (3rd ed.). Abingdon: Routledge. Strandenes, S. P. (2014). Efficiency-enhancing port pricing models. In T. Vanelslander & C. Sys (Eds.),
Port business. Market challenges and management actions (pp. 43–60). Antwerp: University Press Antwerp.
Strandenes, S. P., & Marlow, P. B. (2000). Port pricing and competitiveness in short sea shipping. International Journal of Transport Economics/Rivista internazionale di economia dei trasporti, 27 (3), 315–334.
Suykens, F., & Van de Voorde, E. (1998). A quarter a century of port management in Europe: Objectives and tools. Maritime Policy and Management, 25(3), 251–261.
Szymanski, S. (1991). The optimal timing of infrastructure investment. Journal of Transport Economics and Policy, 25(3), 247–258.
Taneja, P. (2013). The flexible port. Delft: TU Delft. Retrieved from http://dx.doi.org/10.4233/uuid: a9f0c128-d4c3-41a2-8790-13aec89dca63
TRANSPORT REVIEWS 551
Tibben-Lembke, R. S., & Rogers, D. S. (2006). Real options: Applications to logistics and transportation. International Journal of Physical Distribution and Logistics Management, 36(4), 252–270.
Timperman, B. (2017). Walter Van Mechelen: “Uitstel Saeftinghe nefast voor Antwerpen”. Retrieved from http://www.flows.be/nl/shipping/walter-van-mechelen-uitstel-saeftinghe-nefast-voor-antwerpen
Tovar, B., & Trujillo, L. (2007). Econometric estimation of scale and scope economies within the port sector: A review. Maritime Policy and Management, 34(3), 203–223.
Trigeorgis, L. (1996). Real options: Managerial flexibility and strategy in resource allocation. Cambridge, MA: MIT Press.
Trigeorgis, L. (2005). Making use of real options simple: An overview and applications in flexible/ modular decision making. The Engineering Economist, 50(1), 25–53.
Van Der Horst, M. R., & De Langen, P. W. (2008). Coordination in hinterland transport chains: A major challenge for the seaport community. Maritime Economics and Logistics, 10(1–2), 108–129.
Van de Voorde, E., & Vanelslander, T. (2009). Market power and vertical and horizontal integration in the maritime shipping and port industry (OECD/ITF Joint Transport Research Centre Discussion Papers). Paris: Organisation for Economic Co-operation and Development. Retrieved from http://www.oecd-ilibrary.org/content/workingpaper/227458312782
Vanelslander, T. (2014). Port infrastructure: What are we talking about? In H. Meersman, E. Van de Voorde, & T. Vanelslander (Eds.), Port infrastructure finance (pp. 5–32). New York: Informa Law from Routledge.
Van Putten, A. B., & MacMillan, I. C. (2004). Making real options really work. Harvard business review, 82 (12), 134–142.
Veldman, S. J., & Bückmann, E. H. (2003). A model on container port competition: An application for the West European container hub-ports. Maritime Economics and Logistics, 5(1), 3–22.
Verbruggen, A. (2008). Economische benadering van milieu en milieubehoud. Antwerp: Garant. Verhoeven, P. (2015). Economic assessment of management reform in European seaports (PhD thesis).
University of Antwerp. Vilko, J. P. P., & Hallikas, J. M. (2012). Risk assessment in multimodal supply chains. International
Journal of Production Economics, 140(2), 586–595. Weeds, H. (2002). Strategic delay in a real options model of r&d competition. The Review of Economic
Studies, 69(3), 729–747. World Bank & PPIAF. (2007). Port reform toolkit (Tech. Rep. No. 2nd ed.). Washington, DC, USA. Xiao, Y. b., Fu, X., Oum, T. H., & Yan, J. (2017). Modeling airport capacity choice with real options.
Transportation Research Part B: Methodological, 100, 93–114. Xiao, Y. b., Fu, X., & Zhang, A. (2013). Demand uncertainty and airport capacity choice. Transportation
Research Part B: Methodological, 57(C), 91–104. Xiao, Y. b., Ng, A. K., Yang, H., & Fu, X. (2012). An analysis of the dynamics of ownership, capacity
investments and pricing structure of ports. Transport Reviews, 32(5), 629–652. Zhang, A. (2007). Congestion pricing and capacity investment in a gateway-hinterland intermodal
system. International conference on gateways and corridors, Vancouver, BC. Retrieved from http://www.gateway-corridor.com/roundconfpapers/documents/Zhang_Anming_Vancouver.pdf
Zhang, A. (2008). The impact of hinterland access conditions on rivalry between ports (OECD/ITF Joint Transport Research Centre Discussion Papers). Paris: Organisation for Economic Co-operation and Development. Retrieved from http://www.oecd-ilibrary.org/content/workingpaper/2354111 50338
Zhuang, W., Luo, M., & Fu, X. (2014). A game theory analysis of port specialization – implications to the Chinese port industry. Maritime Policy and Management, 41(3), 268–287.
552 M. BALLIAUW ET AL.
Copyright of Transport Reviews is the property of Routledge and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.
- Abstract
- 1. Introduction
- 2. Sources of uncertainty affecting port capacity investment decisions
- 2.1. Competitive position of the port: global logistics chains
- 2.2. Global evolutions in international trade
- 2.3. Technological change: environmental and legal uncertainties
- 3. Real options models to make better decisions under uncertainty
- 4. Real options in the transportation literature
- 5. Real options models to analyse port capacity investment decisions
- 5.1. The basic RO model of Dangl and its extensions
- 5.2. Inclusion of port expansion in the model
- 5.3. The impact of time to build
- 5.4. Installing the project in stages
- 5.5. Game-theoretic approaches
- 5.6. Alternative uncertainty processes: cyclicality and changes in legislation
- 6. Towards a real options application in ports
- 6.1. A framework to enhance port capacity investment decisions
- 6.2. Applying the framework
- 7. Conclusions
- Acknowledgments
- Disclosure statement
- ORCID
- References