Timeline (Missing Milestone labels)

The timeline is based on a normal office environment that only works Monday through Friday.

1. Initiation (Feb. 1st – Feb 3rd (3 days))

a. Assess whom in house can help with new system

i. Start: February 1, 2018 | End: February 1, 2018

b. Discuss stakeholders (President of company, technicians, customers)

i. Start: February 2, 2018 | End: February 2, 2018

c. Assign tasks for the construction of new system (Design website, assessment of security threats, etc.)

i. Start: February 3, 2018 | End: February 3, 2018

2. Planning (Feb. 5th – March 29th (43 Days))

a. Search / hire database designer and security analyst

i. Start: February 5th | End: February 19th , 2018 (10 days)

b. Design website

i. Start: February 5th | End: February 19th 2018 (10 days)

c. Search / hire interns

i. Start: February 15th | End: February 19th (5 days)

d. Design Database

i. Start: February 19th | End: March 19th (22 days)

e. Integrate new data base to website

i. Start: March 22nd | March 26th (5 days)

f. Security assessment

i. Start March 29th | End: March 29th (1 day)

3. Testing / troubleshooting (March 30th – May 25th (52 days)

a. Interns migrate data to new system.

i. Start: March 30th | End: May 11th (31 days)

b. Report errors

i. Start: March 30th | End: May 11th (31 days)

c. Test new system with a customer

i. Start: April 2nd | End: April 13th (10 days)

d. Report errors

i. Start: April 2nd | End: April 13th (10 days)

e. Security risk assessment 2

i. This is a final assessment of the overall security risks with the company and the customer.

ii. Start May 14th | May 14th (1 day)

f. Assess error reports

i. Start: May 14th | End: May 18th (5 days)

g. Resolve problems in the system

i. Start: May 21st | End: May 25th (5 days)

4. TOTAL TIME: approx. 98 days / 3 months

Overall Assessment:

· Hired database designer

· Hired security risk analyst

· Hired interns

· Designed website

· Designed database

· Integrate database

· Migrate information from old to new system

· Assess any security risks

· Report errors company / customer side of system

· Assessed errors

· Resolved errors