Information Systems #1 (260) TLOPRJCT EASYYYY
Timeline (Missing Milestone labels)
The timeline is based on a normal office environment that only works Monday through Friday.
1. Initiation (Feb. 1st – Feb 3rd (3 days))
a. Assess whom in house can help with new system
i. Start: February 1, 2018 | End: February 1, 2018
b. Discuss stakeholders (President of company, technicians, customers)
i. Start: February 2, 2018 | End: February 2, 2018
c. Assign tasks for the construction of new system (Design website, assessment of security threats, etc.)
i. Start: February 3, 2018 | End: February 3, 2018
2. Planning (Feb. 5th – March 29th (43 Days))
a. Search / hire database designer and security analyst
i. Start: February 5th | End: February 19th , 2018 (10 days)
b. Design website
i. Start: February 5th | End: February 19th 2018 (10 days)
c. Search / hire interns
i. Start: February 15th | End: February 19th (5 days)
d. Design Database
i. Start: February 19th | End: March 19th (22 days)
e. Integrate new data base to website
i. Start: March 22nd | March 26th (5 days)
f. Security assessment
i. Start March 29th | End: March 29th (1 day)
3. Testing / troubleshooting (March 30th – May 25th (52 days)
a. Interns migrate data to new system.
i. Start: March 30th | End: May 11th (31 days)
b. Report errors
i. Start: March 30th | End: May 11th (31 days)
c. Test new system with a customer
i. Start: April 2nd | End: April 13th (10 days)
d. Report errors
i. Start: April 2nd | End: April 13th (10 days)
e. Security risk assessment 2
i. This is a final assessment of the overall security risks with the company and the customer.
ii. Start May 14th | May 14th (1 day)
f. Assess error reports
i. Start: May 14th | End: May 18th (5 days)
g. Resolve problems in the system
i. Start: May 21st | End: May 25th (5 days)
4. TOTAL TIME: approx. 98 days / 3 months
Overall Assessment:
· Hired database designer
· Hired security risk analyst
· Hired interns
· Designed website
· Designed database
· Integrate database
· Migrate information from old to new system
· Assess any security risks
· Report errors company / customer side of system
· Assessed errors
· Resolved errors