Project Management IV Research Paper
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
234
Mathematical and Quantative Methods
The Earned Value Management - A Measurement Technique of the
Performance of the Costs and Labor in the Project
Carmen Gasparotti1, Alina Raileanu2, Eugen Rusu3
Abstract: Most of the planned projects have problems due to the cost and time overruns from different
reasons. Earned value management (EVM) is a project performance evaluation technique that has been
used in many projects from several fields, but which has been adapted to be used in project management
to objectively track the physical accomplishment of certain work. The earned value analysis offers the
possibility to manage the project performances in early stages of the project to point out the need of the
eventual corrective action. This paper aims to present the main parameters involved in the calculation
of the Earned Value Analysis (EVA) for a ballast plant on shipboard.
Keywords: Earned Value Management; Earned Value Analysis; Cost Variance; Schedule Variance;
Planned Value
JEL Classification:
1. Introduction
An important tool required to deliver the project on time is Earned Value
Management (EVM).
Earned Value Management is a project management methodology for control the
project that is based on measuring work performance. It is a system that predicts the
final cost and duration of the project by comparing the work done with that planned.
In the same time, EVM is a warning tool, based on which the project manager
identifies and controls any problem before it becomes critical, being able to exploit
the project opportunities (Eun Hong et all, 2003, p. 375).
The concept of earned value management has been first introduced as a fundamental
approach in 1966 when the United States Air Force mandated earned value in
1 Associate Professor, PhD, “Dunarea de Jos” University, Romania, Address: 47 Domnească Str., Galati
800008, Romania, Corresponding author: [email protected]. 2 PhD, Danubius University of Galati, Romania, Address: 3 Galati Blvd., Galati 800654, Romania, Tel.:
+40372361102, E-mail: [email protected]. 3 Assistant Professor, “Dunarea de Jos” University, Romania, Address: 47 Domnească Str., Galati
800008, Romania, E-mail: [email protected].
AUDŒ, Vol. 13, no. 2, pp. 234-247
ŒCONOMICA
235
relationship with the other planning and controlling requirements on Air Force
programs (Abba, 1997, p. 58).
Regardless the field where this concept is applied, either in research and
development projects, or engineering, construction and contract administration
companies as well as large design-manufacturers such as aerospace companies, it
provides all levels of management with early visibility on cost and schedule
problems.
Nowadays EVM is used in programs from world-wide. It becames a requirement of
many U.S. Government agencies, including the Department of Defense, the National
Aeronautics and Space Administration, the Department of Energy, the Intelligence
Community, the Department of Homeland Security, the Federal Aviation
Administration and Department of Transportation, Health and Human Services, and
others (Abba, 2000).
This concept and its requirements have remained basically unchanged, although
some updates have been done regarding its title. These updates have been the
following:Cost/Schedule Control System Criteria, Earned Value Management
Systems Criteria and so on, the only purpose being to provide a formal version of
the „Earned Value” concept (Wesselius & Ververs, 1990, p. 319).
Even if there are still discussions and ongoing debates regarding its practical utility,
Earned Value is recommended for monitoring and controlling project execution. It
is a concept that must be appreciated because it shows how this performance
measurement technique can be a valuable management tool for the project.
Due to the fact that the projects do not generally achieve the required scope and they
are often late, the project performance must be managed using a logical technique
like earned value, with the expectation that the project results will soon improve
(Archibald, 2003).
EVM is regarded as a relationship between three variables that reflect the
performance of the project: budget- to see how the project fits in estimates; time- to
accomplish scope of the project and the work- to see how it was done physically and
the way by which it can measure progress (Anbari, 2003, p. 12).
In the planning phase of the project each work package within the Work Breakdown
Structure is assessed in terms of the cost estimates and the scheduling in a time
sequence. In this way it can be obtained the project cost baseline represented as a
graph of planned costs over time that represents in fact the planned value (PV). PV
is a numerical reflection of the budgeted value of the work that is scheduled to be
executed.
The project cost baseline or performance measurement baseline can be changed only
to reflect the cost changes or programming produced by changes in the project
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
236
content. This guideline describes how it is supposed to evolve the project throughout
the execution period, in each programmed point. It helps the project manager to
predict when the money must be spent and in what period.
The performance measurement performed in raport with the guideline (baseline) is
shown in Figure 1.
Figure 1. Comparison between the Baseline and the Earned Value
From this perspective, this paper aims to provide an overview of the way in which
the earned value (EV) and the actual costs (AC) are calculated and compared with
the planned value (PV) in a project that refers to a ballast plant on shipboard in order
to establish conclusions on the performance of the project.
2. The Earned Value Terminology
Earned Value Management offers a set of guidelines that guide the project managers
to perform a program for cost reduction when the cost is exceeded. This can be done
either by decreasing the scope in some areas of the project or providing an additional
budget to cover the overrun cost (Mohammad, 2010).
When the time is exceeded, it may plan another program for fast tracking to reduce
the time.
This technique uses the cost, that allows the measurement in currency, hours,
worker-days, or any other similar quantity, of the values associated with project work
(EunHong, 2003, p. 375).
To evaluate the project performance Earned Value technique uses the following
project parameters such as: Planned Value (PV) or budgeted cost of work scheduled,
Earned value (EV) or budgeted cost of work performed and Actual Cost (AC) or
actual cost for work performed.
ŒCONOMICA
237
The Earned Value method indicates the performed labor costs till a point in a project,
as well as the amount of the work already accomplished of the activity in question
(Gasparotti, 2014, p. 574).
EV of a project activity is the cost associated with that activity when the project
budget has been defined. It is determined by summing the individual value of each
activity in the project, considering fractional completion of each activity (Suketu,
2002).
To determine the actual cost AC it is required a registration system of the costs that
enables the data collection that refers to the recorded costs for labor and materials
used in the project.
The value of this cost is compared with the earned value (EV) from which resulting
the cost variance (CV).
The cost of work scheduled (PV) is used to compare the achievements with the plan.
Both PV and EV are expressed in money and measures the amount of work or the
achievements. To calculate PV it is need the following items: the estimated costs of
all activities from the tables with estimates; the date that the activities are scheduled
to begin, from the work schedule; the expenditure profile of each activity during its
performance (Kuehn, 2007).
The graph PV reported in time is drawn immediately after the costs of all activities
are estimated and it is developed a work schedule indicating when each task should
be executed.
The schedule variance (SV) results from the comparison of the works planned with
those performed, thus obtaining the difference between the outputs and the expected
values. The term used in the earned value system that measures the work done
compared to the plan expressed in financial terms. In other words, SV measures, in
money how much have progressed the works compared with the plan (Fleming,
2000, p. 212).
At the end of the project, PV reaches the agreed value for the estimated cost for the
end of the project, namely the project budget (PB), and the AC value summing the
total costs recorded in the project (Czarnigowska, 2008, p. 15).
Among the terms used for the costs control the following are important: total
estimated cost at completion (ECAC); the cost performance index (CPI), the
schedule performance index (SPI), the estimated completion date (EDC) and the cost
to complete (CTC).
The total estimated cost at completion (ECAC) can be interpreted by the project
manager, either considering that remaining works to be achieved will fit within the
values provided in the budget or remaining works will be carried out with the same
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
238
costs recorded as in the case of the completed works by that time. Depending on the
interpretation of ECAC, this is calculated differently (Kim et all, 2003, p. 375).
The cost performance index (CPI) is not a very safe clue in the early stages of the
project, when the percentage of the completed works is small, because it is based on
insufficient data. After the execution of more than 30% of the works and later, as the
works progress and the project draws near of 100% completion, it is appropriate to
use the CPI index within the calculations (Kerzner, 1984).
The schedule performance indicator (SPI) shows if the project is carried out faster
than plan or it is lagging behind.
When the project is nearing completion, the EV approaching the PV and the SPI
value tends to 1, regardless of the project duration.
The estimated completion date ECD is determined considering two alternative
interpretations (Kwak & Anbari, 2012, p. 77).
The first interpretation is the situation when it is assumed that all the remaining
works will be carried out in the rhythm indicated by the work schedule, in which the
estimated completion date ECD is obtained by adding or subtracting of the time lag
to/from the initial date of completion, as appropriate.
The second interpretation refers to the situation when it is assumed that the work
schedule for the remaining works not fall into the same delay as the works done so
far, when the estimated completion date ECD is obtained by multiplying the initial
date with the overcome factor (Vandevoorde & Vanhoucke, 2006, p. 289).
The cost to complete (CTC) is the estimated cost of the remaining works to be
executed by the end of the project, which is the most relevant cost in the decision to
continue or not a project. When the CTC value is higher than the likely benefits that
would be achieved if the project will be continued, there is need to take the decision
to cancel the project to avoid further losses (Pajares & Lopez-Parades, 2010).
Table 1. Terms use for the cost control in Earned Value Analysis (from Suketu, 2002)
Symbol Name Significance and formula
AC
Actual cost of work
performed until a certain
moment
It is calculated by collecting the recorded
data as the project progresses
EV
Budgeted cost of work
performed until a certain
moment
It is calculated by summing the value of
each work from the project taking into
account the completion percent of each
element
PV
Budgeted cost of work
scheduled
It is calculated by summing the value of
all scheduled works
CPI
Cost-Performance Indicator CPI= BCWP/ACWP
CPI>1 project is under budget (saving);
ŒCONOMICA
239
CPI=1, which is estimated =current;
CPI<1 project is over budget;
CTC
Cost to complete CTC=ECAC-ACWP
CV
Cost variance CV= BCWP-ACWP
CV<0 the project exceeded the budget
CV>0 the project has savings
SV
Schedule variance SV=BCWP-BCWS
SV <0 the project is behind the schedule;
SV> 0 the project is ahead of the
schedule;
ECAC
Total estimated cost at
completion
ECAC=PB-CV, if the unexecuted works
will be completed within the budgeted
limits
ECAC=PB X (ACWP/BCWP), if the
remaining works will be executed with the
same costs recorded for the completed
works until then
ECD
Estimated completion date ECD=ECD0 +/- gap,
if all the remaining work will be
performed in the rhythm indicated by the
initial planning;
ECD=ECD0 x overcome factor,
if the remaining work will be performed
by maintaining the gap of left behind of
the works;
overcome factor = BCWS/BCWP
SPI
Schedule Performance
Indicator
SPI=BCWP/BCWS
SPI> 1 project is ahead of programming;
SPI = 1 which is estimated = current;
SPI <1 project is delayed (over the limit);
PB
Project budget The estimated costs of the work
performed until the project completion
In figure 2 there are shown the terms from the Earned Value Analysis (Fleming,
2000, p. 212).
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
240
Figure 2. Terms use for the cost control in Earned Value Analysis (from Fleming,
2000, p. 212)
In Table 2 it can be observed what measures EVM, indicating what happens with the
project in terms of work scheduled and the budgeted resources.
Table 2. Performance measurement using EVM (Anbari, 2003)
Performance
measurement
SV & SPI
CV & CPI
>0 & >1 =0 & =1 < 0 & <1
>0 &
>1
In advance of the
programming and
the budget savings
According to the
programming and
the budget savings
Delayed to the
programming
and the budget
savings
=0 &
=1
In advance of the
programming and
according to the
budget
According to the
programming and
the budget
Delayed to the
programming
and according to
the budget
< 0 &
<1
In advance of the
programming and
over the budget
According to the
programming and
over the budget
Delayed to the
programming
and and over the
budget
3. Case Study, Earned Value Analysis for Monitoring Costs in Case of
Ballast Plant on Shipboard
The commercial ships are built for the transport of various cargoes or passengers.
When a ship is not fully loaded, the additional weight is required to provide the ship's
seaworthiness, to compensate the increased buoyancy which can lead in the lack of
ŒCONOMICA
241
the propeller immersion to an inadequate transversal and longitudinal inclination, as
well as other stresses on the ship’s hull (Gasparotti et all, 2013, p. 987). The material
that is used for the adding the weight on the ship is referred to ballast water. Even
when a ship is fully loaded it can require the ballast water operations due to a non-
equal distribution of weights on the ship or due to the bad weather conditions and
the sea conditions. As a result of these factors, the ship is fundamentally based on
the ballast water for safe operations as a function of their design and construction
(Gasparotti & Rusu, 2012, p. 1751), (Ivan et all, 2012, p. 1673).
The organizing of the work is the one of the first tasks for the program management
of implementing EVM. Within the organization (the shipyard) is defined the project
scope of work and the groups who will be responsible for performing work as is
showed in the Statement of Work (SOW). So, if is developed a Work Breakdown
Structure (WBS) of the project, that is the framework for the project effort which
breaks down the complex project into individual components by listing all the
products, components, software, data, and services to be delivered, this is used as a
common base for project planning, scheduling, budgeting, cost accumulation, and
reporting of the performance.
Once the project has begun, the performance of the project against the Performance
Measurement Baseline is checked regularly. The actual work performed, the
schedule, and the costs are monitored regularly and the reports are created.
The project of fabrication and mounting of the ballast plant from the Tulcea shipyard
is performed over a period of 48 weeks (12 months). The start data of the project is
18 August 2014 which corresponds with the finalization data of the hull mounting
from 12 August 2015. During the entire process are used 46 tones of equipment
including 40 tones of piping and 6 tones of valves.
The duration estimated by the staff at planning for fabrication was 4663 hours, but
actually there were consumed 5349 hours, more than the estimated value, and for
mounting there were estimated 7716 hours from which there were used 7162 hours,
less than the estimators expected, as it can see in figure 3.
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
242
Figure 3. The estimated duration of the project
The figure 3 represents the estimated consumption of 100% by the staff at the
planning.
The project budget is 3291102 euro which includes the cost of manufacture,
assembly, materials, labor, production, valves and employees.
Table 3. The activities of the fabrication and mounting
Block Process Start
data
Finish
data
Budgeted
(euro)
A Piping
Block 1
Prefab. Ballast system piping
block 1
28 Oct.
14
10 Jun.
15
235064.6
B Mounting ballast system piping
block 1
6 Jan.
15
29 Jun.
15
234766.6
C Piping
Block 2
Prefab. Ballast system piping
block 2
18
Aug.14
1 Jul. 15 234689.6
D Mounting ballast system piping
block 2
15
Dec.14
12
Aug.15
235108.6
E Piping
Block 3
Prefab. Ballast system piping
block 3
21
Aug.14
8 Jun. 1 235455.6
F Mounting ballast system piping
block 3
18
Dec.14
13 Jun.
15
236377.6
G Piping
Block 4
Prefab. Ballast system piping
block 4
12
Nov.14
10 Jun.
15
235229.6
ŒCONOMICA
243
H Mounting ballast system piping
block 4
6 Jan.15 10 Jul. 15 235877.6
I Piping
Block 5
Prefab. Ballast system piping
block 5
30
Nov.14
8 Jun. 15 234047.6
J Mounting ballast system piping
block 5
9 Jan.
15
29 Jun.
15
234169.6
(*) all dependencies are assumed to be FS – Finish to Start
Figure 4. The network of the project
Figure 5. Gantt chart of the initial planning
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
244
Table 4. The duration and the predecessors of the activities
Activity Immediate
predecessor (*)
Duration
(weeks)
Start data in the
week
A G 33 44
B D, F 26 2
C - 43 34
D A, I 30 50
E - 43 34
F A, I 27 50
G C, E 38 44
H D, F 26 2
I G 37 44
J B, H 26 2
(*) all dependencies are assumed to be FS – Finish to Start
Table 5. The costs from the earned value system
PV EV AC week
1567191,79 1567191,79 1567191,79 0
2350787,34 2045184,99 1820214,64 8
2507506,45 2382131,13 2120096,71 15
2664225,56 2451087,52 2205978,76 20
2820944,67 2595269,1 2439835,05 28
2977663,78 ─ ─ 36
3291102 ─ ─ 48
Calculation for the graphic of the earned value system
To apply the earned value method in the control and monitoring of project costs it is
considered that the progress report is drawn up after the first 28 weeks from the start
of the project, as is presented in Figure 6.
It considers that of the ballast plant execution project has a duration of 48 weeks and
a project budget PB= 3291102 euro.
CV=EV-AC=2595269,1-2439835,05 = 155434 euro (economii faţă de bugetul
iniţial)
SV=EV-PV=2595269,1-2820944,67= -225675 euro (lucrări rămase în urmă faţă de
planificarea iniţiala)
The Schedule Variance SV indicates how much the project is ahead or behind than
the initial planning.
ŒCONOMICA
245
In this case it has resulted from the calculations that the value of SV is negative
which means that the project are behind the initial planning.
To determine the estimated completion date ECD is necessary to consider two
alternatives:
1. If it is assuming that all the remaining work will be performed in the rhythm
indicated by the initial planning, then ECD will be:
ECDI =ECD0 +28/17 =48+28/17=50 weeks
2. If it is assuming that the remaining work will be performed by maintaining the
gap of left behind of the works.
ECDII =ECD0 X 28/17= 48 X 28/17=79 weeks
Figure 6. The curves of the Earned Value System
After the analyzing of the progress report of the project (after 28 weeks), it find out
that it has been spent less than estimated in the budget for the activities undertaken
up to the moment (AC <EV), but also the activities have remained as provided
behind to the initial programming (EV <PV).
ACTA UNIVERSITATIS DANUBIUS Vol 13, no 2, 2017
246
4. Conclusions
To use this tool called EVM, is necessary to plan resources, time and cost, to analyze
the performance with which they are made. It has been demonstrated that the earned
value concept is an effective technique in the project management. It permits the
project managers to receive early warning signals to modify the ultimate direction of
the project.
The major objectives of applying the Earned Value are to encourage the contractors
to use effective internal technical cost and schedule management control systems.
EVM allows a better and more effective management decision minimizing the
adverse impacts to the project.
Among the main advantages in using the earned value are:
a) The accuracy in the achievement of the reporting.
b) The early warning that provides a tool to project managers, allowing them to
take the necessary corrective actions if the project is spending more money than it
was physically planned.
The efficiency of the costs control system and the schedules is improved by
presenting on the same graph of the curves EV, AC and PV. They indicate the way
in which evolving the project in financial terms (by the relative positions of the
curves AC and EV) and which is the situation in terms of framing the results
obtained in the work schedule (the relative positions of the curves EV and PV). In
this way, it is demonstrated that the Earned Value Management (EVM) is a
management concept that integrates the technical performance requirements,
resource planning, schedules, while the risk is taken into consideration.
5. References
Abba, W. (1997). Earned Value Management-Reconciling Government and Commercial Practices.
Program Manager, 26, pp. 58-63.
Abba, W. (2000). How Earned Value Got to Primetime: A Short Look Back and A Glance Ahead. In
Project Management Institute Seminars and Symposium in Houston, TX.
Archibald, R.D. (2003). Managing High-Technology Programs and Projects. John Wiley & Sons,
Chichester.
Anbari, F. (2003). Earned Value Project Management Method & Extensions. Project Management
Journal, 34(4), pp. 12-23.
Czarnigowska, A. (2008). Earned value method as a tool for project control. Budownictwo Architektura,
3, pp. 15-32.
ŒCONOMICA
247
EunHong, K.; William, G.; Wells, Jr. & Michael, R. Duffey. (2003). A Model for Effective
Implementation of Earn Value Management Methodology. International Journal Of Project
Management, 21, pp. 375-382.
Fleming, Quentin W. & Koppelman, Joel M. (2000). Earned Value Project Management. Publisher
Project Management Institute, pp. 212. Web page. Retrieved from: http://www.ebay.com/ctg/earned-
value-project-management-joel-m-koppelman-and-quentin-w-fleming-2000-hardcover-/1773678.
Gasparotti, C. (2014). Application of the earned value method in monitoring of the project cost. Review
of Management and Economic Engineering, Vol. 13, no. 3 (53), pp. 574-588.
Gasparotti, C. & Rusu, E. (2012). Methods for the risk assessment in maritime transportation in the
Black Sea basin. Journal of Environmental Protection and Ecology 13(3-A), pp. 1751-1759.
Gasparotti, C.; Rusu, E. & Dragomir, S. (2013). The impact of anthropogenic activities on the water
quality in the Danube River Basin. Proceedings Ecology, Economics, Education and Legislation, vol.
I, pp. 987-994, Conference Albena, Bulgaria, June, 2013. DOI: 10.5593/sgem2013. Web page.
Retrieved from: http://sgem.org/SGEMLIB/spip.php?article3381&debut_articles_rubrique=75.
Ivan, A.; Gasparotti, C. & Rusu, E. (2012). Influence of the interactions between waves and currents
on the navigation at the entrance of the Danube Delta. Journal of Environmental Protection and
Ecology, 13, pp. 1673-1682.
Kerzner, H. (1984). Project Management: a systems approach to planning, scheduling and controlling.
New York: Van Nostrand Reinhold.
Kim, E.; Wells, Jr. W. & Duffey, M. (2003). A model for effective implementation of Earned Value
Management methodology. International Journal of Project Management, 21(5), pp. 375-382.
Kuehn, U. (2007). EVM. 05 Earned Value Analysis–Why am I forced to do it?. AACE International
Transactions.
Kwak, Y. & Anbari, F. (2012). History, practices, and future of earned value management in
government: Perspectives from NASA. Project Management Journal, 43(1), pp. 77-90.
Mohammad, A. Rajabi. (2010). Introduction to Earned Value Method, Web page. Retrieved from:
http://www.marajabi.com.
Pajares, J. & Lopez-Parades, A. (2010). An extension of the EVM analysis for project monitoring: The
Cost Control Index and the Schedule Control Index Science Direct. International Journal Of Project
Management.
Suketu, Nagrecha (2002). An introduction to Earned Value Analysis, Web page. Retrieved from:
http://www.pmiglc.org/COMM/Articles/0410_nagrecha_eva-3.pdf.
Vandevoorde, S. & Vanhoucke, M. (2006). A Comparison of different project duration forecasting
methods using Earned Value Metrics Science Direct. International Journal of Project Management 24,
pp. 289-302.
Wesselius, J. & Ververs, F. (1990). Some elementary questions on software quality control. Software
Engineering Journal, Vol.5, No.6, pp. 319-330.
Copyright of Acta Universitatis Danubius: Oeconomica is the property of Danubius University of Galati, Faculty of Law and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright holder's express written permission. However, users may print, download, or email articles for individual use.