project management
Using Figure 6-2, enter the activities, their durations (in days), and their relationships in Project 2016. Use a project start date of March 26, 2018 if you want the dates to match exactly. View the network diagram. Does it look like Figure 6-4? Print the network diagramon one page. Return to the Gantt chart view. To re-create Table 6-1, right-click the Select All button to the left of the Task Mode column heading and select Schedule. Alternatively, you can click the View tab and click the Tables button under the Data group and then select Schedule. You may need to move the split bar to the right to reveal all of the table columns. (See Appendix A—available on the Companion website for this text—for detailed information on using Project 2016.) Write a few paragraphs explaining what the network diagram and schedule table show about Project X’s schedule.
Consider Table 6-2. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. (Note that you can easily change this table to create multiple exercises.)
Table6-2.Network diagram data for a small project
|
Activity |
Initial Node |
Final Node |
Estimated Duration |
|
A |
1 |
2 |
2 |
|
B |
2 |
3 |
2 |
|
C |
2 |
4 |
3 |
|
D |
2 |
5 |
4 |
|
E |
3 |
6 |
2 |
|
F |
4 |
6 |
3 |
|
G |
5 |
7 |
6 |
|
H |
6 |
8 |
2 |
|
I |
6 |
7 |
5 |
|
J |
7 |
8 |
1 |
|
K |
8 |
9 |
2 |
a. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
b. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as a guide for how to represent each path.
c. What is the critical path for this project and how long is it?
d. What is the shortest possible time needed to complete this project?
Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network proceeds from Node 1 to Node 8. (Note that you can easily change this table to create multiple exercises.)
a. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
b. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as a guide for how to represent each path.
c. What is the critical path for this project and how long is it?
d. What is the shortest possible time needed to complete this project?
Table6-3.Network diagram data for a large project
|
Activity |
Initial Node |
Final Node |
Estimated Duration |
|
A |
1 |
2 |
10 |
|
B |
1 |
3 |
12 |
|
C |
1 |
4 |
8 |
|
D |
2 |
3 |
4 |
|
E |
2 |
5 |
8 |
|
F |
3 |
4 |
6 |
|
G |
4 |
5 |
4 |
|
H |
4 |
6 |
8 |
|
I |
5 |
6 |
6 |
|
J |
5 |
8 |
12 |
|
K |
6 |
7 |
8 |
|
L |
7 |
8 |
10 |