S/N

ACTIVITY

COST

1

Hiring of machines

70000

2

Direct labor for the project

115000

3

Direct materials

240000

4

Plan and design of the house

35000

5

Environmental certification permit

30000

6

Electrical work

25000

7

Plumbing work

25000

8

Constuction of store room and settting up

20000

9

Site security

15000

10

transport and storage

25000

11

House decoration

130000

12

Interior design

15000

13

Painting

35000

14

Land scaping

30000

15

Waterproof laying and roofing

45000

16

purcahse of windows and doors

15000

17

bathroom fittings, and

20000

18

Heating, ventilation and Air conditioning system

45000

19

floor tiling

45000

20

security system installation

25000

CONSTRUCTION COST

1005000

21

CONTIGENCY

24000

TOTAL COST

1029000

 

 

PROJECT SCHEDULE

 

 

 

 

 

 

 

 

 

CONSTRUCTION OF A HOUSE IN ASHBURN, VIRGINIA

 

 

 

 

 

 

 

 

ESTIMATED COST

$1.2 MILLION

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

COST

ACTIVITY TO BE CARRIED OUT

COMMENCEMENT

PLANNED DURATION

ACTUAL START OF ACTIVITY

END

 

 

 

 

$60, 000

Activity No 1

Finalising on the design of the house

58 days

01/10/2019

07/09/2019

51 days

$150

Activity No 2

Issuance of permit to build the house

1 day

05/16/2019

05/17/2019

1 day

$132, 000

Activity No 3

Pre- Construction of the building

100 days

02/04/2019

05/05/2019

90 days

$210, 000

Activity No 4

setting up the construction crane on site

125 days

08/03/2019

12/04/2019

125 days

$190, 000

activity No 5

Setting up water lines underground

80 days

05/03/2019

08/25/2019

80 days

$90,000

Activity No 6

Pouring the building's concrete footings

30 days

09/16/2019

10/17/2019

30 days

$40, 000

Activity No 7

Construction of foundation walls

20 days

09/21/2019

10/13/2019

20 days

$30,000

Activity No 8

forming and pouring the slab

15 days

11/16/2019

12/02/2019

15 days

$70,000

Activity No 9

Back fill and Compact wall

17 days

11/19/2019

12/07/2019

17 days

$440, 000

Activity No 10

coming up with the structure of the building

120 days

12/11/2019

03/21/2020

120 days

$2, 000

Activity No 11

Decking the floor

30 days

02/21/2020

04/02/2020

30 days

$3, 200

Activity No 12

Construction of the 1st floor

24 days

04/11/2020

05/06/2020

24 days

$9, 000

Activity No 13

Erecting the staircase

14 days

04/16/2020

04/30/2020

14 days

$7, 000

Activity No 14

Concreting the slab of the basement

15 days

05/01/2020

05/15/2020

15 days

$160, 000

Activity No 15

Concreting the second floor

19 days

04/21/2020

05/09/2020

19 days

$150,000

Activity No 16

Installing an electrical system

5 days

04/20/2020

04/25/2020

5 days

$3, 000

Activity No 17

Installing the building's roofing

10 days

05/13/2020

05/23/2020

10 days

$7, 500

Activity No 18

Doors and windows

2 days

05/30/2020

06/02/2020

2 days

$2, 000

Activity No 19

Exterior finishes

21 days

06/04/2020

06/25/2020

21 days

$58, 070

Activity No 20

Contigencies

14 days

06/25/2020

07/07/2020

14 days