Running head: WEDDING PROJECT TASK PLAN 1
Wedding Project Task Plan
Task ID
Task summary Duration Start date End date Predecessor Resource
1 Development and submission of the project Charter
One week 05/02/2018 05/09/2018 Wilson Garcia
2 Approval of the project Charter One week 05/10/2018 05/17/2018 The project Charter Jones Miller 3 Selection of the project team One week 05/18/2018 05/25/2018 Approval of the project
Charter Wilson Garcia
4 Developing the project scope Three days
05/25/2018 05/28/2018 Selection of the project team
Wilson Garcia
5 Meeting with the bride and the groom
Three days
06/02/2018 06/05/2018 Development of the project scope
Wilson Garcia
6 Analysis of the potential donors and planning for the fundraising event
One day 06/06/2018 06/07/2018 The project scope Wilson Garcia and Shawn Stephen
7 Identifying a venue for the fundraising
Three days
06/10/2018 06/13/2018 Identification of potential donors and settling for a date
Wilson Garcia and Shawn Stephen
8 Printing and sending of the invitation cards
Two weeks
06/15/2018 06/30/2018 Venue identification Ava Olivia and Shawn Stephen
9 Hosting the fundraising event One day 08/15/2018 08/15/2018 Printing and sending of invitation cards
Ava Olivia, Wilson Garcia and Shawn Stephen
10 Selecting a wedding officiant One day 08/20/2018 08/20/2018 The fundraising event Ava Olivia, Wilson Garcia and Shawn Stephen
11 Drafting the guest list One day 08/25/2018 08/25/2018 Getting the officiant Ava Olivia, Wilson Garcia and Shawn Stephen
2 WEDDING PROJECT TASK PLAN
12 Printing the wedding cards One day 08/27/2018 08/27/2018 Drafting of the guest list Ava Olivia, Wilson Garcia and Shawn Stephen
13 Sending invitations One week 08/30/2018 09/06/2018 Printing of the invitation cards
Ava Olivia, Wilson Garcia and Shawn Stephen
14 Reserving of the venue One week 08/10/2018 08/18/2018 Sending of invitations Ava Olivia, Wilson Garcia and Shawn Stephen
15 Printing of the wedding program
One week 08/25/2018 09/02/2018 Reserving of the venue Ava Olivia, Wilson Garcia and Shawn Stephen
16 Venue visitation to check for suitability
One day 09/10/2018 09/10/2018 Printing of the wedding program
Ava Olivia, Wilson Garcia and Shawn Stephen
17 Arranging for hotel payments One day 09/12/2018 09/12/2018 Venue visitation Ava Olivia, Wilson Garcia and Shawn Stephen
18 Buying the venue décor One day 09/20/2018
09/20/2018 Arrangements for the hotel payments
Maryanne Smith
19 Finding caterers One week 09/25/2018 10/01/2018 Buying the venue décor Liam Brown 20 Paying for catering services Two days 10/05/2018 10/06/2018 Finding caterers Liam Brown
21 Selection of a suitable menu and refreshments
One day 10/10/2018 10/10/2018 Paying for catering services
Liam Brown
22 Selection of a dinner location One day 10/15/2018 10/15/2018 Selection of a suitable menu and refreshments
Ava Olivia
23 Purchase of the utensils Two days 10/20/2018 10/20/2018 Selection of a dinner location
Liam Brown
24 Selection of a cake design One day 10/22/2018 10/22/2018 Purchase of the utensils Liam Brown 25 Acquiring of music equipment Two days 10/25/2018 10/25/2018 Selection of a cake
design Shawn Stephen
26 Soliciting for a band One week 11/01/2018 11/07/2018 Acquisition of the music Shawn Stephen
3 WEDDING PROJECT TASK PLAN
equipment 27 Conducting dance lessons and
selection of a reception song One week 11/01/2018 11/07/2018 Soliciting for a band Shawn Stephen
28 Acquiring a DJ One week 11/01/2018 11/07/2018 Conducting dance lessons and selection of a reception song
Maryanne Smith
29 Acquiring a light system Two days 11/01/2018 11/07/2018 Acquiring a DJ Maryanne Smith 30 Arranging for dinner
entertainment Three days
11/8/2018 11/11/2018 Acquiring a light system Maryanne Smith
31 Analysis of threats in the environment
One day 11/12/2018 11/12/2018 Arranging for dinner entertainment
Ava Olivia
32 Acquiring of security personnel
One day 11/15/2018 11/15/2018 Analysis of threats in the environment
Ava Olivia
33 Formulation of strategies to mitigate risks
One day 11/17/2018 11/17/2018 Acquiring of security personnel
Ava Olivia
34 Getting the wedding gown One day 11/18/2018 11/18/2018 Formulation of strategies to mitigate risks
Maryanne Smith
35 Hiring of a florist One day 11/19/2018 11/19/2018 Getting the wedding gown
Maryanne Smith
36 Purchase of flowers One day 11/20/2018 11/20/2018 Hiring a florist Maryanne Smith 37 Choosing color and theme One day 11/21/2018 11/21/2018 Purchase of flowers Maryanne Smith 38 Acquiring the maids and the
maidens’ outfit One day 11/22/2018 11/22/2018 Choosing color and
theme Maryanne Smith
39 Acquiring accessories One day 11/23/2018 11/23/2018 Acquiring the maids and the maidens’ outfit
Maryanne Smith
40 Getting hair and make-up artist One day 11/24/2018 11/24/2018 Acquiring accessories Maryanne Smith 41 Purchase of the rings One day 11/25/2018 11/25/2018 Getting hair and make-
up artist Maryanne Smith
42 Contracting a photographer One day 11/26/2018 11/26/2018 Purchase of the rings Maryanne Smith 43 Sourcing for media coverage One day 11/27/2018 11/27/2018 Contracting a
photographer Wilson Garcia
44 Decorating cars One day 11/28/2018 11/28/2018 Sourcing for media Maryanne Smith
4 WEDDING PROJECT TASK PLAN
coverage 45 Acquiring of cars One day 11/29/2018 11/29/2018 Decorating cars Ava Olivia 46 Acquiring of drivers One day 11/30/2018 11/30/2018 Acquisition of cars Ava Olivia
47 Paying for the guest's transportation
One day 11/31/2018 11/31/2018 Acquisition of drivers Ava Olivia
48 Printing of the venue maps One day 12/01/2018 12/01/2018 Paying for the guest's transportation
Ava Olivia
49 Setting a carpooling service One day 12/02/2018 12/02/2018 Printing of the venue maps
Ava Olivia
50 Bride and the groom’s transportation
One day 12/03/2018 12/03/2018 Setting a carpooling service
Ava Olivia
51 The wedding event (reception of guests, preaching, exchange of vows, signing of the marriage certificate, gifting the bridal party and taking photographs)
One day 12/20/2018 12/20/2018 Bride and the groom’s transportation
The project team
52 Honeymoon destination location
One day 12/21/2018 12/21/2018 The wedding event The project team
53 Paying for the hotel and flights One day 12/22/2018 12/22/2018 Destination location The project team 54 Acquiring the passport and
visas One day 12/23/2018 12/23/2018 Paying for the hotel and
the flights Ava Olivia
55 Conducting exit meetings One day 12/26/2018 12/26/2018 Acquiring the passport and visas
The project team