General:

· Make good use of dates.

· Please make sure to include all aspects of the events (Booking of entertainment, Ticketing and hosting the Govt. guests are not included)

· No mention of a start date.

· Detailed explanation of the cost with justification for each aspect of the events and mention all resources used from the internet.

· Please note that the 50000 budget only cover the management of the venue but it does not include the beverage, foods and utility cost.

· Please make use of the option of visiting the venue one day prior the festival day as an activity.

· Most importantly, there is no mention of any details regarding making a minimum profit of 50000. Please include it in each aspect required in each task.

Task1:

· 1.1 Provide more objective and make it SMART as required.

· 1.2 You only identified stakeholders that can contribute to the success but no mention to the ones that can influence on failure of the project.

· 1.3 No mention of the major milestones and how they can be monitored with dates.

· 1.4 Regarding budget you only explained how it could be used but you did not provide methods on how to make sure it is utilized probably giving its outcomes. The same apply to the second critical factor, provide with way of measurements such as a survey. Finally, there is no mention of the profit generated you need to write about how to measure the success in terms of profit.

Task2:

· You only provided 19 activates, the minimum is 20.

· You did not use a tree diagram, which is required.

· Make sure all activities are broken down probably.

· Please consider the last comments in task 2 (to make sure of breaking down the activities to sub actives (not to use a general activities)

Task3:

· You were not using MS Project.

· You only scheduled the activities without giving exact dates with estimated time taking.

· You did not provide resources for each activity (People, Materials).

· Show me how each activities are done in brief.

· You are not provide more than one options of ways to implement the activities with justifications of choosing the best one.

Take 4:

Missing

Task 5:

Make sure you are using more than 5 risks and explains how they are linked to the smart objectives using (Probability Impact Risk Assessment Matrix) and develop comprehensive mitigation steps for each of the top five risks. You did not provide the last thing required (Important of risk management)