Week 7 Final Project BUSN 420

profilek.warren5
T11TechPluginDataFile.xlsx

Sheet1

Software Development
Start Date Duration (Days) End Date
Scope 3/1/16 4 3/5/16
Analysis/ Software Requirements 3/4/16 14 3/18/16
Design 3/18/16 18 4/5/16
Development 4/1/16 24 4/25/16
Testing 4/15/16 21 5/6/16
Training 5/6/16 3 5/9/16
Documentation 5/12/16 5 5/17/16
Pilot 5/18/16 10 5/28/16
Deployment 6/1/16 3 6/4/16
Post Implementation Review 6/10/16 2 6/12/16