Group project 3

profilesaalecynthia123
SupplyChainManagementProject-Final2.xlsx

Intro

Project Plan and Cost for
Supply Chain Management System
Go to the Sheet Tap Bar to see the details

Project activities

Project Activities Definition
Project management Initiate the project and set-up the project structure and facilitate the project necessary tools and lead
Business blueprint Understand the business requirement and define the scope of the project and set up scope creep procedures and risk management method
Design Outline the conceptual design for solutions and develop a prototype of main process flows and activities
Build Develop the solution according to defined scope during the design phase
Testing Organize business representatives to perform User Acceptance Test and coordinate the testing and fixing activities until test sign-off
IT Platform Ensure the entire IT platform is ready for development and monitor system performance indicators secure technical go-live stability
Security Check and ensure all security aspects are covered in the project
System accesses Define business roles and authorizations and ensure accesses are checked and approved from segregation of duties perspective
Integration Identify all impacted integrated systems and developed the necessary interfaces and solutions
Migration Study what data to be migrated from the legacy system into the new system and conduct a cutover plan and methodology
Technical Go-live Identify the activities for technical go-live and ensure all mater data set up are completed
Change Management Develop information, news letters and training materials for end users
Implementation Select a pilot organization for testing the solutions and prepare pilot outcome approval checklist and develop rollout time plan for the entire organization
Handover Develop a system blueprint and other relevant materials and knowledge transfer to assigned IT people and guide how to support their organization
Post Go-live support Support the business onsite during two weeks along with the organization's IT department
Project closure Document final project report and lessons learned to terminate the project

Time plan

Supply Chain Management Project Time plan
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Project management
Business blueprint
Design
Build
Testing
IT Platform
Security
System accesses
Integration
Migration
Technical Go-live
Change Management
Implementation
Handover
Post Go-live support
Project closure

Resource Plan

Resource Plan
Project activities Number of resources Required Resources
Project management 1 Project manager
Business blueprint 3 Business Matter Expert, Solution architect, System Matter Expert
Design 4 Business Matter, Expert, Solution architect, System Matter Expert, System developer
Build 7 Business Matter, System Matter Expert, Solution architect, System development lead and 3 Developers
Testing 7 Business Matter, System Matter Expert, Solution architect, System development lead and 3 Developers
IT Platform 1 Infrastructure architect
Security 1 IT security expert
Business accesses 2 Roles and Authorization design and developers
Integration 2 System integration expert, system integration developer
Data migration 3 Data migration lead, 2 migration experts
Technical Go-live 5 Business Matter Expert, System Matter Expert, Solution architect, 2 System developers
Change Management 2 Change management lead, document and training materials developer
Implementation 5 Business Matter Expert, System Matter Expert, Solution architect, 2 System developers
Handover 4 Solution architect, Infrastructure architect, IT security expert, Development lead
Post Go-live support 5 Solution architect, Business matter expert, System matter expert, 2 developers
Project closure 2 Project manager, Solution architect

Time reporting

Project Resources Name Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
Project Manager Xxxxxxxx Xxxxxxxx 100% 168 168
Business Matter Expert Xxxxxxxx Xxxxxxxx 100% 165 165
Solution architect Xxxxxxxx Xxxxxxxx 100% 160 160
System Matter Expert Xxxxxxxx Xxxxxxxx 100% 155 155
System Matter Expert Xxxxxxxx Xxxxxxxx 100% 165 165
System development lead Xxxxxxxx Xxxxxxxx 100% 0
System developer-1 Xxxxxxxx Xxxxxxxx 100% 0
System developer-2 Xxxxxxxx Xxxxxxxx 100% 0
System developer-3 Xxxxxxxx Xxxxxxxx 100% 0
Infrastructure architect Xxxxxxxx Xxxxxxxx 100% 0
IT security expert Xxxxxxxx Xxxxxxxx 25% 0
Roles and Authorization design and developer Xxxxxxxx Xxxxxxxx 100% 0
Roles and Authorization design and developer Xxxxxxxx Xxxxxxxx 100% 0
System integration expert Xxxxxxxx Xxxxxxxx 50% 0
System integration developer Xxxxxxxx Xxxxxxxx 100% 0
Data migration lead Xxxxxxxx Xxxxxxxx 100% 0
Migration expert-1 Xxxxxxxx Xxxxxxxx 100% 0
Migration expert-2 Xxxxxxxx Xxxxxxxx 100% 0
Change management lead Xxxxxxxx Xxxxxxxx 100% 0
Document and training materials developer Xxxxxxxx Xxxxxxxx 100% 0
813 0 0 0 0 0 0 0 0 0 0 0 1626
81,300 81,300

Project Cost

Price Rate $100 per hour (one price rate for the sake of simplicity)
Avarage hours per month = 168
No vacation during the project
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total cost
Project activities Required number of resources Required efforts in FTE Required period in month Estimated resource hours Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Estimated cost Actual cost Difference Total estimated Total Actual Total difference
Project management 1 1 12 201,600.00 16,800.00 16,800.00 0.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 201,600.00 16,800.00 184,800.00
Business blueprint 3 3 1 50,400.00 50,400.00 48,000.00 2,400.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 50,400.00 48,000.00 2,400.00
Design 4 4 2 134,400.00 0.00 67,200.00 67,200.00 67,200.00 67,200.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 134,400.00 0.00 134,400.00
Build 7 7 3 352,800.00 0.00 0.00 0.00 117,600.00 117,600.00 117,600.00 117,600.00 117,600.00 117,600.00 0.00 0.00 0.00 0.00 0.00 0.00 352,800.00 0.00 352,800.00
Testing 7 7 2 235,200.00 0.00 0.00 0.00 0.00 0.00 0.00 117,600.00 117,600.00 117,600.00 117,600.00 0.00 0.00 0.00 0.00 235,200.00 0.00 235,200.00
IT Platform 1 0.5 9 75,600.00 0.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 8,400.00 0.00 0.00 75,600.00 0.00 75,600.00
Security 1 0.25 6 25,200.00 0.00 0.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 4,200.00 0.00 0.00 0.00 0.00 25,200.00 0.00 25,200.00
System accesses 2 2 7 235,200.00 0.00 0.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 0.00 0.00 0.00 235,200.00 0.00 235,200.00
Integration 2 1 7 117,600.00 0.00 0.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 16,800.00 0.00 0.00 0.00 117,600.00 0.00 117,600.00
Migration 3 3 4 201,600.00 0.00 0.00 0.00 0.00 0.00 50,400.00 50,400.00 50,400.00 50,400.00 50,400.00 50,400.00 50,400.00 50,400.00 0.00 0.00 0.00 201,600.00 0.00 201,600.00
Technical go-live 5 5 1 84,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 84,000.00 84,000.00 0.00 0.00 0.00 84,000.00 0.00 84,000.00
Change Management 2 2 7 235,200.00 0.00 0.00 0.00 0.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 33,600.00 0.00 235,200.00 0.00 235,200.00
Implementation 5 5 4 336,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 84,000.00 84,000.00 84,000.00 84,000.00 84,000.00 84,000.00 84,000.00 84,000.00 336,000.00 0.00 336,000.00
Handover 4 2 2 67,200.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33,600.00 33,600.00 33,600.00 33,600.00 67,200.00 0.00 67,200.00
Post go-live support 5 5 1 84,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 84,000.00 84,000.00 84,000.00 0.00 84,000.00
Project closure 2 2 0.5 16,800.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16,800.00 16,800.00 16,800.00 0.00 16,800.00
TOTAL 54 49.75 56.5 2,452,800.00 67,200.00 64,800.00 2,400.00 92,400.00 0.00 92,400.00 147,000.00 0.00 147,000.00 197,400.00 0.00 197,400.00 231,000.00 0.00 231,000.00 281,400.00 0.00 281,400.00 281,400.00 0.00 281,400.00 281,400.00 0.00 281,400.00 327,600.00 0.00 327,600.00 142,800.00 0.00 142,800.00 168,000.00 0.00 168,000.00 235,200.00 0.00 235,200.00 2,452,800.00 64,800.00 2,388,000.00

Cost Follow-up

Cost Follow-up Report
Estimate Cost Actual Cost Diff Comment
January 67,200.00 67,200.00
February 92,400.00 92,400.00
March 147,000.00 147,000.00
April 197,400.00 197,400.00
May 231,000.00 231,000.00
June 281,400.00 281,400.00
July 281,400.00 281,400.00
August 281,400.00 281,400.00
September 327,600.00 327,600.00
October 142,800.00 142,800.00
November 168,000.00 168,000.00
December 235,200.00 235,200.00
2,452,800.00 2,452,800.00