Supply Chain & Project Management
1. In 350 words, I would like each student to discuss JIT production versus Lean manufacturing. Please give the pros and cons of both and provide two examples, one for each method of a company that uses that method.
2. Wtach the folllowing videos:
https://www.youtube.com/watch?v=wEWhnodF6ig
https://www.youtube.com/watch?v=5dgGjW6Bakk
What is a work breakdown structure? Name at least three key factors in establishing a WBS.
What is a responsibility assignment matrix? How are they related?
3. Define the follwoing terms.
What does ES stand for?
What does EF stand for?
What does LS stand for?
What does LF stand for?
What is slack?
What is a critical path?
4. You are the owner of The Painting Company. You receive an RFP from a school to "paint the building". The RFP does not contain many details other than the school address and the due date for RFP response. While this sounds like an attractive project, what details must be clarified before submitting your bid. List at least five questions about the RFP.
5. You received bad news! Your family is coming to your place tonight at 730PM. It is now 5 PM. This will give you 150 minutes to prepare for the arrival. Hey, at least they called to let you know!
What is the quickest that you can finish a clean-up without waxing the floors?
What is the longest that it will take to finish a clean-up yet without waxing the floor?
If you wax the floor, what other cleaning activity can still be included? What needs to left out?
If a roommate would help and split the duites, what is the fastest time that the place could be cleaned? (include the calculation)
If the floors were waxed, could all the clean-up activities occur if your roommate assisted? (include the calculation)
Dust - MIN 15 minutes MAX 20 minutes
Vacuum - MIN 15 minutes MAX 20 minutes
Gather and take out trash - MIN 15 minutes MAX 30 minutes
Clean Dishes - MIN 30 minutes MAX 45 minutes
Clean counters where dishes were sitting- 15 minutes
Sweep the floors - MIN 15 minutes MAX 20 minutes
Clean the windows - MIN 10 minutes MAX 30 minutes
Wax Floors and Dry - 120 minutes