| Summary Milestone Schedule | September | | | | October | | | | November | | | | | December |
| | 6 | 13 | 20 | 27 | 3 | 10 | 17 | 24 | 1 | 8 | 15 | 22 | 29 | 5 | 12 | 19 | 26 |
| Project Planning | Project Start Date: September 6th |
| Develop Project charter and plan |
| Develop work plan and resource plan | | | | | | Project Plan approved: October 3rd |
| On-board resources for project |
| Snack food manufacturing |
| Identify Snack foods for production |
| Setup Darwin facility for test production |
| Produce test snack line-up for market | | | | | | | | | | | | Production for test market complete Nov 15th |
| Test Marketing |
| Market research for Northern territory |
| Identify retail food chains for partnership |
| Introduce snack foods in chains | | | | | | | | | | | | | Snack food introduction in all chains complete: 22 Nov |
| Monitor and Expand |
| Monitor customer feedback in test market |
| Make changes to product and roll-out |
| Identify plants for mass production |
| Project Close out |
| Setup Plant for mass production |
| Phase-out activities for project | | | | | | | | | | | | | Project End Date: December 26th |